A.M. COHRON & SON, INC., Plaintiff, vs. CITY OF COLUMBUS, NEBRASKA, Defendant.
4:21CV3066
IN THE UNITED STATES DISTRICT COURT FOR THE DISTRICT OF NEBRASKA
July 7, 2021
Cheryl R. Zwart, United States Magistrate Judge
MEMORANDUM AND ORDER
This matter is before the court on Defendant City of Columbus’ (“the City“) motion to dismiss pursuant to
STATEMENT OF FACTS
Plaintiff AMC‘s complaint alleges:
AMC, an Iowa Corporation and the City, a political subdivision of the State of Nebraska, entered into a construction contract for a project in Platte County, Nebraska in December 2016. (Filing No. 1 at CM/ECF pp. 1-2). The project involved construction of grade-separated crossings of the Union Pacific Railroad Corridor at two locations in the сity; one was a pedestrian overpass, the other a vehicular viaduct. (Filing No. 1 at CM/ECF p. 5). During its work on the viaduct,
Under the contract, the project was to be completed within 587 calendar days, with terms allowing liquidated damages if AMC failed to complete the project within the specified time frame. (Filing No. 1 at CM/ECF p. 6). The City assessed $394,179.00 in liquidated damages against AMC because of the delayed completiоn of the project. AMC asserts the City‘s damages are significantly less than the liquidated damages assessed. (Filing No. 1 at CM/ECF p. 8). AMC alleges that as a direct and proximate cause of the City‘s breaches of the Contract, AMC has been damaged in an amount exceeding $456,762.45. (Filing No. 1 at CM/ECF p. 9).
The projеct was a federal-aid project. The Nebraska Department of Roads (“NDOR“) made payments to AMC on behalf of the City, and NDOR delegated to the City as Local Public Agency Owner under
STANDARD OF REVIEW
To survive a
Generally, a motion to dismiss may be granted when a claim is barred under a statute of limitations. Varner v. Peterson Farms, 371 F.3d 1011, 1016 (8th Cir. 2004). If a defendant raises a statute of limitations defеnse and the face of the complaint indicates that the limitations period has expired, the plaintiff can survive a
ANALYSIS
A. Applicable Nebraska Statute: Neb. Rev. Stat. § 45-1210 or Neb. Rev. Stat. § 16-726 .
At the core of this motion, the parties disagree as to which statute provides the apрropriate means for seeking recovery of contractual damages from the City. AMC argues that
Prior to enacting the NCPPA,
The NCPPA was enacted in 2010 and dictates certain payment terms when construction work is performed in accordance with the provisions of a cоntract. AMC asserts the NCPPA, not
The City asserts the NCPPA is inapplicable because AMC is not a ‘contractor’ as defined by the NCPPA.
The NCPPA, enacted in 2010, was amended by LB 961 in 2014. The 2014 amendment, effeсtive July 18, 2014, added the clause excluding public works contractors and subcontractors from coverage under the bill.2 The complaint alleges the contract at issue in this case, entered into after the July 2014 amendments to the NCPPA, specifically states that the construction projеct was “a federal-aid project of a political subdivision in which the Nebraska Department of Roads (‘NDOR‘) made payments to AMC on behalf of the City.” (Filing No. 1 at CM/ECF p. 2).
B. Plaintiff‘s claim under Neb. Rev. Stat. § 16-726 .
Under
Here, AMC‘s complaint does not allege that it timely filed a claim with the City Clerk in compliance with the
In opposition to the City‘s motion to dismiss, AMC argues that the City does not have a right to assess liquidated damages because it would qualify as an illegal penalty. AMC‘s brief contains an anаlysis of liquidated damages and what limited damages may have been appropriate under the circumstances. But the briefing fails to explain how the entirety of the claim is not defeated by the statute of limitations. AMC simply asserts, without support, that a request for a determination that liquidated damages were improperly assessed “cannot be a time-barred claim.” (Filing No. 14 at CM/ECF p. 8).
AMC‘s complaint for breach of contract does not request declaratory relief, or “a determination that the liquidated damages were improperly assessed.” Rather, it asserts thаt the City withheld sums from AMC and “as a result of an unenforceable liquidated damages provision, the City breached the contract.”
The Nebraska Supreme Court has stated:
Generally, a cause of action accrues and the period of limitations begins to run upon the violation of a legal right, that is, when the aggrieved party has the right to institute and maintain suit. Snyder v. EMCASCO Ins. Co., 259 Neb. 621, 611 N.W.2d 409 (2000); Reinke Mfg. Co. v. Hayes, 256 Neb. 442, 590 N.W.2d 380 (1999). A cause of action in contract accrues at the time of breach or the fаilure to do the thing agreed to. Snyder v. EMCASCO Ins. Co., supra; Hoeft v. Five Points Bank, 248 Neb. 772, 539 N.W.2d 637 (1995). This is so even though the nature and extent of damages may not be known. Cavanaugh v. City of Omaha, 254 Neb. 897, 580 N.W.2d 541 (1998); L.J. Vontz Constr. Co. v. Department of Roads, 232 Neb. 241, 440 N.W.2d 664 (1989).
Irving F. Jensen Co. v. State, Dep‘t of Roads, 272 Neb. 162, 167, 719 N.W.2d 716, 720 (2006).
In Jensen, the Nebraska Supreme Court stated that regardless of whether the Department of Roads breached the contract by refusing to modify the contractual obligations or expressly аuthorize extra work, the failure to pay Jensen for the extra work performed would, “if proved, constitute a separate and distinct breach of contract that did not accrue until the DOR refused Jensen‘s claim for extra compensation.” Applying that logic, and the provisions of
The complaint alleges the project was open to the public as of February 7, 2019, “but the engineer did not stop charging days until April 29, 2019.” (Filing No.
When this action was filed in March 2021, there was no allegation that AMC had satisfied the conditions precedent by filing a claim within 90 days of the accrual of the action in the office of the city clerk. Thus, AMC‘s claim for breach of contract is time-barred and will be dismissed.5
For all the foregoing reasons,
IT IS ORDERED:
- Defendant‘s motion to dismiss (
Filing No. 10 ) is granted. - Plaintiff‘s motion for hearing (
Filing No. 15 ) is denied. - A separate judgmеnt of dismissal, with prejudice, will be entered.
Dated this 7th day of July, 2021.
BY THE COURT:
s/ Cheryl R. Zwart
United States Magistrate Judge
Notes
1) Plaintiff did not make a claim to the City Clerk.
2) Plaintiff did not timely file its lawsuit after any claim made was denied.
3) AMC‘s lawsuit was filed in the wrong court. Any suit under the NCPPA “shall be commenсed in the district court of the county in which the construction project at issue was located.”
