History
  • No items yet
midpage
A.M. Cohron & Son, Inc. v. City of Columbus, Nebraska
4:21-cv-03066
D. Neb.
Jul 7, 2021
Read the full case

Background

  • AMC (Iowa corp.) and City of Columbus entered a construction contract (Dec. 2016) for two grade-separated crossings; project was federal-aid with NDOR payments on the City's behalf.
  • AMC encountered rebar clearance problems on the viaduct, performed extra work (thicker deck), and submitted a change-order request on or about May 22, 2018; the Project Engineer denied the request on June 4, 2018.
  • The City assessed $394,179 in liquidated damages for delay; AMC alleges damages exceeding $456,762.45 and alleges the City breached by withholding sums and failing to grant time/compensation.
  • AMC filed suit in federal court on March 18, 2021 for breach of contract; the City moved to dismiss under Rule 12(b)(6), arguing AMC failed to satisfy Neb. Rev. Stat. § 16-726 conditions precedent and that the claim is time-barred; the parties disputed whether the Nebraska Construction Prompt Pay Act (§ 45-1210) or § 16-726 applied.
  • The court held the NCPPA (§ 45-1210) excluded federal-aid projects (post-2014 amendment), concluded § 16-726 governs claims against a city of the first class, found AMC did not allege timely filing with the city clerk within 90 days, and dismissed the complaint with prejudice.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Which Nebraska statute governs recovery for construction claims against the City? NCPPA (§ 45-1210) governs because this is a construction contract. § 16-726 governs; NCPPA excludes federal- or state-aid projects paid by the state. § 16-726 applies; NCPPA excludes federal-aid projects after the 2014 amendment.
Did AMC satisfy § 16-726 conditions precedent (timely written claim filed with city clerk)? AMC contends submitting claims to the Project Engineer complied (or NCPPA controlled). AMC did not file a claim in the city clerk’s office within 90 days; Project Engineer is not the clerk. AMC failed to allege filing with the city clerk within 90 days; conditions precedent not met.
Is AMC’s breach-of-contract claim time-barred? AMC argues challenge to liquidated damages is not time-barred; seeks compensation for withheld sums. The accrual (denial of claim/assessment of damages) occurred in 2018; suit (2021) was too late absent required 90-day filing. Claim accrued by June/April 2019 at latest; no 90-day city-clerk filing alleged; claim is time-barred.
Could AMC amend to cure pleading defects? (No amendment requested) AMC did not request leave to amend or allege facts that would make the claim timely. Dismissal appropriate because defects are substantive and unremedied. Court found no basis to allow amendment and dismissed with prejudice.

Key Cases Cited

  • Ashcroft v. Iqbal, 556 U.S. 662 (standards for pleadings and plausibility)
  • Bell Atl. Corp. v. Twombly, 550 U.S. 544 (pleading standard requiring plausibility)
  • Corrado v. Life Inv'rs Ins. Co. of Am., 804 F.3d 915 (application of Iqbal/Twombly in Eighth Circuit)
  • Varner v. Peterson Farms, 371 F.3d 1011 (statute-of-limitations dismissal on Rule 12(b)(6))
  • Schmidt v. Newland, 927 F.3d 1038 (limitations defense and tolling on Rule 12(b)(6))
  • Travelers Indem. Co. v. Int'l Nutrition, Inc., 734 N.W.2d 719 (statutes in existence at contract formation become part of contract)
  • Centric Jones v. City of Kearney, Neb., 324 F.3d 646 (§ 16-726 filing requirement functions as time bar)
  • Irving F. Jensen Co. v. State, Dep't of Roads, 719 N.W.2d 716 (accrual of contract claim upon denial of payment)
Read the full case

Case Details

Case Name: A.M. Cohron & Son, Inc. v. City of Columbus, Nebraska
Court Name: District Court, D. Nebraska
Date Published: Jul 7, 2021
Citation: 4:21-cv-03066
Docket Number: 4:21-cv-03066
Court Abbreviation: D. Neb.