History
  • No items yet
midpage
139 Conn. App. 65
Conn. App. Ct.
2012
Read the full case

Background

  • Worth Construction contracted to expand Engelman Hall at SCSU for $33,497,050 with a $3,000/day liquidated damages clause for late substantial completion.
  • Contract time originally 1068 days; a change order added 394 days, totaling 1462 days to June 12, 2005.
  • Plaintiff achieved substantial completion on August 25, 2005, 74 days late.
  • Defendant notified plaintiff on October 17, 2005 that damages may be assessed for delay beyond June 12, 2005.
  • Daigle prepared field reports miscalculating total days (stating 1552 instead of 1462) and recommended no liquidated damages; Jellison’s letter later notified damages.
  • Trial court found no waiver by defendant; defendant prevailed on its liquidated damages counterclaim; plaintiff appeals on waiver grounds.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Waiver of liquidated damages requires knowledge and intentional relinquishment Daigle’s miscalculation shows denial of damages; waiver occurred Daigle lacked knowledge of damages right; no waiver Waiver not clearly erroneous; no intelligent waiver shown
Does Daigle’s mistaken calculation preclude waiver under case law Mistake invalidates claim of waiver Mistake did not prove intent to relinquish rights Court distinguished Jenkins and held no waiver due to lack of knowledge and intentionality

Key Cases Cited

  • AFSCME, Council 4, Local 704 v. Dept. of Public Health, 272 Conn. 617 (2005) (waiver as a factual question; knowing right required)
  • Lehn v. Marconi Builders, LLC, 120 Conn. App. 459 (2010) (standard of review for waiver findings)
  • Gordon v. Tobias, 262 Conn. 844 (2003) (clear-error review; defer to trial court on factual inferences)
  • Krevis v. Bridgeport, 262 Conn. 813 (2003) (waiver requires intelligent action considering context)
  • Rosenthal v. State Bar Examining Committee, 116 Conn. 409 (1933) (waiver must be intentional, not based on mistake of fact)
  • Jenkins v. Indemnity Ins. Co., 152 Conn. 249 (1964) (distinguishes knowledge of a potential claim from certainty of its correctness)
  • Rosado v. Bridgeport Roman Catholic Diocesan Corp., 292 Conn. 1 (2009 (cert. denied)) (consideration of conduct in waiver analysis)
  • New Haven v. Local 884, Council 4, AFSCME, AFL-CIO, 237 Conn. 378 (1996) (contractual rights; waiver/estoppel relevance)
  • Harlach v. Metropolitan Property & Liability Ins. Co., 221 Conn. 185 (1992) (assent requires knowledge of rights; not mere acquiescence)
Read the full case

Case Details

Case Name: Worth Construction Co. v. Department of Public Works
Court Name: Connecticut Appellate Court
Date Published: Nov 6, 2012
Citations: 139 Conn. App. 65; 54 A.3d 628; 54 A.3d 627; 2012 WL 5357926; 2012 Conn. App. LEXIS 524; AC 33699
Docket Number: AC 33699
Court Abbreviation: Conn. App. Ct.
Log In
    Worth Construction Co. v. Department of Public Works, 139 Conn. App. 65