Westrock Virginia Corp. v. United States
15-355
Fed. Cl.Feb 9, 2018Background
- WestRock Virginia Corp. owns a paper mill and an open-loop biomass cogeneration facility that produces electricity and extracts steam for mill process use; construction began in 2011 and the facility was placed in service in 2013.
- WestRock applied under Section 1603 (ARRA) seeking 30% of a claimed qualified cost basis of $286,191,571 (requesting $85,857,471). Treasury adjusted the eligible basis downward to 48.9% (49.1% for steam diversion and a 0.22% fossil-fuel startup reduction) and awarded $38,881,758.
- NREL reviewed the application and estimated ~49.1% of steam energy was used for electricity and ~0.22% of fuel use was fossil fuel for startup/stabilization.
- WestRock sued in the Court of Federal Claims seeking the difference (~$39M), moving for partial summary judgment; the government filed a cross-motion. Extensive briefing, discovery, supplemental briefs, and oral argument occurred.
- The central legal questions were (1) whether Section 1603 reimburses costs attributable to process steam (non‑qualifying activity) as well as electricity, and (2) whether WestRock reasonably allocated its cost basis between qualifying (electricity) and non‑qualifying (steam) activities.
Issues
| Issue | Plaintiff's Argument | Defendant's Argument | Held |
|---|---|---|---|
| Whether Section 1603 reimburses costs for process steam at an open‑loop biomass cogeneration facility | WestRock: Section 1603 does not require producing only electricity; costs for facility should qualify without excluding steam production | United States: Section 1603 (read with IRC §§45/48) targets electricity production; process steam is a non‑qualifying activity and not reimbursable | Held: Section 1603 reimburses only costs attributable to electricity production; steam production is non‑qualifying and excluded |
| Whether Treasury guidance requiring allocation of cost basis between qualifying and non‑qualifying activities is entitled to deference | WestRock: Section 1603 is silent on allocation; Treasury guidance should not control to limit recovery | United States: Treasury guidance reasonably fills the statutory gap and requires reasonable allocation between qualifying and non‑qualifying uses | Held: Treasury guidance is reasonable and entitled to Skidmore deference; WestRock must allocate cost basis between electricity and steam |
| Whether WestRock’s proposed allocation methodologies reasonably allocate eligible cost basis | WestRock: Offered five allocation methods (efficiency comparison, electricity production share, necessary‑property removal, cost per kW, or court-crafted method) and argued one should apply | United States: The offered methods either fail to allocate all qualified property used for both activities or lack evidentiary support for this facility | Held: WestRock did not present a reasonable, fully‑supported allocation; proposed methods are flawed or unsupported |
| Remedy / case disposition where plaintiff fails to prove a reasonable allocation | WestRock: Court could adopt an allocation or allow further proceedings | United States: Failure to carry burden defeats recovery; summary judgment appropriate | Held: Government’s cross‑motion granted; WestRock’s motion denied; complaint dismissed for failure to prove eligible basis and entitlement to additional payment |
Key Cases Cited
- W.E. Partners II, LLC v. United States, 119 Fed. Cl. 684 (court applied three‑part test and required reasonable allocation for cogeneration facilities)
- GUSC Energy, Inc. v. United States, 129 Fed. Cl. 118 (court reduced eligible basis by comparing plant efficiency to electricity‑only plants)
- LCM Energy Sols. v. United States, 107 Fed. Cl. 770 (recognizing Section 1603 as money‑mandating)
- Chevron U.S.A., Inc. v. Natural Res. Def. Council, Inc., 467 U.S. 837 (framework for judicial deference to agency interpretations)
- Skidmore v. Swift & Co., 323 U.S. 134 (standard for lesser deference to agency interpretations)
