955 F.3d 100
D.C. Cir.2020Background
- Turner contracted to build the South African embassy and subcontracted work to U.S. Engineering, which in turn subcontracted sheet-metal work to United Sheet Metal.
- United Sheet Metal defaulted; U.S. Engineering declared it in default and terminated the subcontract on September 9, 2013.
- U.S. Engineering did not notify Western Surety (the performance-bond surety for United Sheet Metal) of the default and termination until June 9, 2014—about nine months later—after U.S. Engineering had pursued alternative remedies.
- The bond at issue is the standardized AIA A312-2010 performance bond, which requires the owner to declare default, terminate the subcontract, and notify the surety before the surety’s obligations under section 5 arise.
- Western Surety sued for declaratory and injunctive relief, arguing the late notice discharged its bond obligations; the district court granted summary judgment for Western Surety.
- U.S. Engineering appealed, contending the bond required only notice (without a timeliness requirement) and that any failure to give notice should be excused unless the surety shows actual prejudice.
Issues
| Issue | Plaintiff's Argument (Western Surety) | Defendant's Argument (U.S. Engineering) | Held |
|---|---|---|---|
| Whether the A312 bond requires "timely" notice of default/termination (a condition precedent) before surety obligations attach | Timely notice is implied because the bond grants the surety rights to remedy the default under §5 that would be meaningless if obligee cured the default without notice | Bond language only requires notice, not a time limit; implied timeliness would forfeit protections for the obligee and should be construed for obligee | Timely notice is a condition precedent: owner must notify surety before self-help remedies; failure to do so discharges surety’s obligations (Hunt controlling) |
| Whether §4’s actual-prejudice limitation applies to failures to give notice under §3.2 (default/termination notice) | §4’s actual-prejudice rule applies only to failures under §3.1; §3.2 failures are independent condition precedents and do not require the surety to show prejudice | If a timeliness requirement is implied, §4’s prejudice standard should nonetheless apply to excuse forfeiture | §4’s actual-prejudice requirement applies only to §3.1; plain language shows no §3.2 prejudice requirement; even if prejudice were required, the surety here was inherently prejudiced by the delayed notice |
Key Cases Cited
- Hunt Constr. Grp. v. Nat’l Wrecking Corp., 587 F.3d 1119 (D.C. Cir. 2009) (timely notice is a condition precedent to surety obligations under an AIA bond when the bond gives the surety the right to remedy)
- St. Paul Fire & Marine Ins. Co. v. VDE Corp., 603 F.3d 119 (1st Cir. 2010) (surety-bond language is construed liberally for the beneficiary but courts must respect clear contract terms)
- Citibank v. Grupo Cupey, Inc., 382 F.3d 29 (1st Cir. 2004) (principle that liberal construction of surety bonds does not override parties’ agreements)
- Wash. Props., Inc. v. Chin, Inc., 760 A.2d 546 (D.C. 2000) (doubtful contract language is generally construed as promise rather than condition)
- Int’l Fid. Ins. Co. v. Americaribe-Moriarty JV, [citation="681 F. App'x 771"] (11th Cir. 2017) (under A312 bond, hiring a new subcontractor before giving the surety an opportunity to respond can discharge the surety because it thwarts §5 remedies)
