Defendant VDE Corporation (VDE) appeals from the district court’s grant of summary judgment in favor of plaintiff St. Paul Fire & Marine Insurance Company (St. Paul) releasing St. Paul from its obligations under a construction performance bond. After careful review, we affirm.
I.
The relevant facts are largely undisputed. In the spring and summer of 2005, VDE аrranged for the construction and financing of a residential real estate project, Villas Del Este Project, in Gurabo, Puerto Rico (the project). In April 2005, VDE entered into a construction contract with F & R Contractors Corporation (F & R), engaging the company to serve as contractor for the project. VDE obtained financing for the project from Banco Santander Puerto Rico (BSPR).
On June 28, 2005, St. Paul, as surety, issued a performance bond (the bond) for the benefit of VDE, as obligee, to guarantee performance under the construction contract by F & R, as principal. The bond was a standard document, the American Institute of Architects document A312 performance bond (AIA A312). That same day, St. Paul issued a “dual obligee rider” to the bond, adding BSPR as a co-obligee.
Paragraph 4 of the surety bond sets forth St. Paul’s options for performance in the event that F & R defaults under the construction contract. Paragraph 4 provides:
When the Owner [VDE] has satisfied thе conditions of Paragraph 3 [settingforth requirements for declaring contractor default], the Surety [St. Paul] shall promptly and at the Surety’s expense take one of the following actions:
4.1 Arrange for the Contractor [F & R], with consent of the Owner, to perform and complete the Construction Contract; or
4.2 Undertake to perform and complete the Construction Contract itself, through its agents or through independent contractors; or
4.3 Obtain bids or negotiated proposals from qualified contractors acceptable to the Owner for a contract for performance and completion of the Construction Contract, arrangе for a contract to be prepared for execution by the Owner and the contractor selected with the Owner’s concurrence, to be secured with performance and payment bonds executed by a qualified surety equivalent to the bonds issued on the Construction Contract, and pay to the Owner the amount of damages as described in Paragraph 6 in excess of the Balance of the Contract Price incurred by the Owner resulting from the Contractor’s default; or
4.4 Waive its right to perform and complete, arrange for completion, or obtain a new contractor and with reasonable promptness under the circumstances:
.1 After investigation, determine the amount for which it may be liable to the Owner and, as soon as practicable after the amount is determined, tender payment therefor to the Owner; or
.2 Deny liability in whole or in part and notify the Owner citing reasons therefor.
(Emphasis added.)
On November 7, 2007, VDE declared F & R in default on its obligations as contractor and terminated F & R’s right to continue work on the project. In support of its declaration of default, VDE stated that F & R had refused to abide by its contractual obligations, failed to work at a reasonable pace, abandoned work on the project, insisted on collecting payments not due, and failed to act in good faith. Two days later, VDE notified St. Paul that it had declared F & R in default and requested that St. Paul perform its obligations under the bond. VDE informed St. Paul that it “oppose[d] that the project be completed with F & R as contractor, either directly or indirectly.”
On November 16, St. Paul requested certain documentation from VDE in order to investigatе VDE’s allegations of contractor default. St. Paul also acknowledged VDE’s statement that it opposed the use of F & R as completion contractor and advised VDE that “should the Surety choose to complete under Paragraph 4.2 of the Bond, the terms of the Bond do not allow the Obligee to opрose the contractor that the Surety selects as its own completion contractor, whether it be the Principal or otherwise.”
On December 6, St. Paul informed VDE that it had not yet received much of the requested documentation related to its investigation of VDE’s allegations of contractor default. St. Pаul listed the missing documents and asked that VDE provide the information as soon as possible. VDE responded that same day, asserting that “[t]he time for the surety to act has expired” and declaring St. Paul in default on its obligations under the bond.
On December 14, following VDE’s declaration that St. Paul was in default, St. Paul filed this declaratory judgmеnt action against VDE and BSPR in federal district court. St. Paul requested a declaration
On December 26, VDE provided St. Paul with some of the documentation previously requested, and stated again that it would “not consent to F & R performing additional work at the project, either directly or indirectly.” VDE further stated that it would provide St. Paul with an additional fifteen-day period to perform. On January 10, 2008, St. Paul notified VDE that it intended to undertake completion of the project pursuant to Paragraph 4.2 of the bond, using F & R as completion contractor. St. Paul explained that if VDE “maintains the position that the Surety may not use F & R Contractors to comрlete under Paragraph 4.2 of the Performance Bond, VDE will be in breach of the terms and conditions of the Bond and not only will VDE be waiving its rights under the Bond, but this will also serve to discharge the obligations of the Surety thereunder.” VDE responded the following week, maintaining that under Paragraph 4.2 of the bond it had the authority to withhold consent to the use of F & R as the completion contractor.
The district court granted summary judgment to St. Paul. The court reasoned that VDE materially breached the bond by insisting that St. Paul could not undertake to complete the project using F & R as completion contractor, contrary to the plain language of Paragraph 4.2, and released St. Paul from its obligations under the bond. The district court dismissed the counterclaims with prejudice.
VDE filed this timely appeal from the judgment. 1
II.
VDE contends that the district court erroneously granted summary judgment to St. Paul because, under Paragraph 4 of the bond, St. Paul may not undertake to perform and complete the construction contract through the original contractor without VDE’s consent. VDE further argues that even if consent is not ordinarily required by Paragraph 4, it is required where, as here, VDE has alleged that the original contractor acted in bad faith.
Summary judgment is properly granted where “the pleadings, the discovery and disclosure materials on file, and any affidavits show that there is no gеnuine issue as to any material fact and that the movant is entitled to a judgment as a matter of law.” Fed.R.Civ.P. 56(c). We review the district court’s grant of summary judgment de novo, drawing all reasonable inferences from the facts in the nonmoving party’s favor.
Velez v. Thermo King de Puerto Rico, Inc.,
This case arises under our diversity jurisdiction, and therefore we apply Puеrto Rico law.
See Erie R.R. Co. v. Tompkins,
In this case, the text of Paragraph 4 of the bond is unambiguous on the point at issue. Paragraph 4.2, under which the surety assumes primary responsibility for completion of the construction contract, contains no provision requiring the project owner’s consent as to the completion contrаctor. In proceeding under Paragraph 4.2, St. Paul must “[u]ndertake to perform and complete the Construction Contract itself, through its agents or through independent contractors.” By its terms, Paragraph 4.2 places no restrictions on whom St. Paul can use to complete the project.
See St. Paul Fire & Marine Ins. Co. v. Green River,
The absence of a consent requirement in Paragraph 4.2, and the presence of such a requirement in Paragraphs 4.1 and 4.3, sensibly reflects the different obligations assumed by a surety electing to proceed under each of these provisions. In choosing to proceed under Paragraph 4.2, which requires the surety to
undertake
to perform and complete the construction contract, St. Paul “assumed primary responsibility to complete the contract, and with that responsibility came the freedom to assemble the project team of its choosing.”
Green River,
In contrast, a surety electing to proceed under Paragraph 4.1 must
arrange for
the original contractor to perform and complete the construction contract with the owner’s consent, by financing the original contractor’s continuing performance.
See
Wisner & Knox,
supra,
at 245-46. Under this provision, the surety “does not assume primary responsibility for completing the contract, and the owner is required to maintain an ongoing contractual relationship with the terminated contractor.”
Green River,
Our interpretation of Paragraph 4.2 is also consistent with common practices in the construction industry. The surеty performance options contained in Paragraph 4 of the AIA A312 bond, the bond at issue here, are “standard in the industry.”
Green River,
VDE’s arguments in support of a contrary interpretation of Paragraph 4.2 are unavailing. VDE argues that Paragraph 4.2 is ambiguous as to whether it requires ownеr consent. VDE contends that the capitalized term “Contractor,” as used in Paragraph 4.1, refers to the original contractor, in this case F & R. VDE reasons that the term “agents” as used in Paragraph 4.2 cannot also refer to the original contractor. We do not understand these terms to create any ambiguity. If the surety elects to undertake completion of the contract using F & R as the completion contractor, as permitted under Paragraph 4.2, then F & R’s role has shifted from that of original contractor to that of agent of the surety.
VDE also suggests that because Paragraph 4.2 neither requires nor expressly disрenses with owner consent, “a well-founded objection to a selected ‘agent’ prevents its selection and use by the surety.” However, the text of the bond does not support this reading. As discussed above, Paragraphs 4.1 and 4.3 both expressly require owner consent as to the completion contractоr, while Paragraph 4.2 contains no such consent requirement. We cannot rewrite Paragraph 4.2 to require owner consent in cases where the owner voices a “well-founded objection” to the selected contractor.
III.
We conclude, as the distriсt court did, that VDE materially breached the bond by insisting that St. Paul could not employ F & R as completion contractor under Paragraph 4.2.
See Green River,
Affirmed.
