History
  • No items yet
midpage
Western Surety Company v. U.S. Engineering Company
211 F. Supp. 3d 302
D.D.C.
2016
Read the full case

Background

  • U.S. Engineering (Defendant) subcontracted sheet-metal work to United Sheet Metal (Subcontractor) under a subcontract that included an arbitration clause applying to controversies or claims between Contractor and Subcontractor.
  • United Sheet Metal obtained a $585,000 performance bond from Western Surety (Plaintiff), which identified United Sheet Metal as “Contractor,” Western as “Surety,” and U.S. Engineering as “Owner.” The bond incorporated the construction contract and included a clause permitting proceedings under the bond to be instituted in court.
  • A dispute arose; U.S. Engineering terminated United Sheet Metal and sought $417,379 in damages while United Sheet Metal sought arbitration for $331,242. Arbitration between those parties is ongoing.
  • U.S. Engineering sought to join Western Surety in the arbitration and to make a claim on the bond. Western refused and filed this declaratory/injunctive action seeking a ruling that it is not required to arbitrate.
  • The central legal question is whether Western, a non-signatory surety whose bond incorporates the subcontract, is bound by the subcontract’s arbitration clause (and by extension whether it agreed to arbitrate arbitrability).

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Whether Western is bound to arbitrate disputes under the subcontract's arbitration clause Western: did not consent to arbitration; the bond does not clearly bind it to arbitration and the bond explicitly allows court proceedings U.S. Eng.: the bond incorporates the subcontract by reference, so Western is bound by the subcontract's arbitration clause (including arbitrability) Court: Western is not bound by the subcontract arbitration clause; grant summary judgment for Western
Whether arbitrability was committed to an arbitrator Western: no clear and unmistakable evidence Western agreed to arbitrate arbitrability U.S. Eng.: subcontract adopted AAA rules which may delegate arbitrability to arbitrators Court: no clear and unmistakable evidence Western agreed to arbitrate arbitrability; court decides arbitrability

Key Cases Cited

  • Rent-A-Ctr., W., Inc. v. Jackson, 561 U.S. 63 (arbitration is contractual; enforce agreements according to their terms)
  • BG Group, PLC v. Republic of Argentina, 134 S. Ct. 1198 (a party cannot be compelled to arbitrate disputes absent agreement)
  • Aliron Int’l, Inc. v. Cherokee Nation Indus., Inc., 531 F.3d 863 (arbitrability disputes evaluated under summary-judgment-type review)
  • First Options of Chicago, Inc. v. Kaplan, 514 U.S. 938 (heightened standard: clear and unmistakable evidence required to show parties agreed to arbitrate arbitrability)
  • Moses H. Cone Mem’l Hosp. v. Mercury Constr. Corp., 460 U.S. 1 (federal policy favoring arbitration)
  • Sheriff v. Medel Elec. Co., 412 A.2d 38 (when a contract incorporates another writing, the documents are read together)
  • Exchange Mut. Ins. Co. v. Haskell Co., 742 F.2d 274 (discussed for contrast: broad arbitration clause held to bind surety)
  • J.S. & H. Constr. Co. v. Richmond County Hosp. Auth., 473 F.2d 212 (discussed for contrast: broad arbitration clause in prime contract bound non-signatories via incorporation)
Read the full case

Case Details

Case Name: Western Surety Company v. U.S. Engineering Company
Court Name: District Court, District of Columbia
Date Published: Sep 30, 2016
Citation: 211 F. Supp. 3d 302
Docket Number: Civil Action No. 2015-0327
Court Abbreviation: D.D.C.