History
  • No items yet
midpage
Washington Gas Light Co. v. Public Service Commission
61 A.3d 662
| D.C. | 2013
Read the full case

Background

  • Washington Gas, a DC public utility, faced a rate case before the PSC and refused to produce the full Accenture MSA contract with appendices during discovery.
  • The PSC ordered production of the entire MSA; Washington Gas disclosed portions and offered to allow in-camera review of missing parts.
  • Order 14383 compelled responses by July 23, 2007; subsequent orders 14384 and 14385 intensified production and defined the scope as the whole agreement with appendices.
  • Washington Gas eventually produced the contract in full after the forfeiture order was issued; the PSC imposed a $350,000 fine under DC Code §§ 34-706 and 34-708.
  • Washington Gas sought reconsideration and later appealed after this court held the Commission lacked authority to impose forfeiture without Superior Court action.
  • The Superior Court ultimately ruled in Washington Gas I that the forfeiture authority was improper, and Washington Gas paid the sum under protest; the current appeal concerns the proper sanction calculation and related conversion claim.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Whether the forfeiture sanction was properly imposed. Washington Gas argues the order was ambiguous and the sanction was improper. Commission contends a knowing violation of a lawful order warranted per diem fines. Sanction valid but start date limited to after reconsideration period.
When do per diem sanctions commence for a willful violation? Gas asserts reconsideration period should delay start of penalties. Commission argues penalties accrue during the violation period; reconsideration does not suspend it unless stayed. Per diem fines commence after the time for reconsideration expires.
Is Washington Gas liable for conversion regarding the $350,000 payment? Gas contends the Commission cannot convert or seize funds it paid under protest. District and Commission maintain the conversion claim fits a tort/damages regime and § 12-309 notice applies. Gas entitled to summary judgment on conversion; prejudgment interest measured from protest payment.
Does the action implicate the interplay of § 34-905 vs § 34-706/34-708 penalties? Gas argues § 34-905 is the exclusive penalty provision for orders enforcing production. Penalties under § 34-706 and § 34-708 are cumulative and apply to willful violations of lawful orders. Penalty scheme properly applied; cumulative penalties permitted; per diem determined as above.

Key Cases Cited

  • Washington Gas Light Co. v. Pub. Serv. Comm’n, 982 A.2d 691 ((D.C.2009)) (forfeiture authority; appellate reversal on authority grounds)
  • Snowder v. District of Columbia, 949 A.2d 590 ((D.C.2008)) (conversion claims may be unliquidated and subject to §12-309 notice)
  • World Fire & Marine Ins. Co., 68 A.2d 222 ((D.C.1949)) (World Fire cited regarding liquidated vs unliquidated tort claims)
  • District Cablevision Ltd. P’ship v. Bassin, 828 A.2d 714 ((D.C.2003)) (analyzing ascertainable sums for liquidated claims)
  • District of Columbia v. Pierce Assocs., Inc., 527 A.2d 306 ((D.C.1987)) (affirms method for determining liquidated claims)
  • One 1995 Toyota Pick-Up Truck v. District of Columbia, 718 A.2d 558 ((D.C.1998)) (excessive fines framework guidance)
  • Owens v. District of Columbia, 993 A.2d 1085 ((D.C.2010)) (strict construction of notice requirements)
Read the full case

Case Details

Case Name: Washington Gas Light Co. v. Public Service Commission
Court Name: District of Columbia Court of Appeals
Date Published: Feb 28, 2013
Citation: 61 A.3d 662
Docket Number: Nos. 12-CV-106, 12-CV-150
Court Abbreviation: D.C.