District of Columbia v. Pierce Associates, Inc.District of Columbia v. Pierce Associates, Inc.
Pursuant to a contract with the District of Columbia, appellees Pierce Associates (Pierce) performed construction work on the District of Columbia Convention Center. When the District failed to make timely payment of its final balance due, Pierce brought this action for breach of contract. After the complaint was filed, the District paid the principal of this final payment, but a dispute remained concerning the amount of interest the District owed Pierce in compensation for the loss of the use of the funds during the period in which the final payment was withheld. Pierce moved for summary judgment, arguing that
The District appeals arguing (1) that, as a matter of law, prejudgment interest for liquidated debts or damages in breach of contract actions is, in the absence of an express contractual provision, limited by
I
Most of the facts are not in dispute. Pierce Associates is the surviving partner of a joint-venture that entered a June 9, 1981 contract with the District of Columbia to install the mechanical portion of the District’s Convention Center. The contract obligated the District to pay the joint-venture $10.6 million for the work. Article 3 of the contract provided for a “change order” procedure by which the District could request modifications to the original construction plans. Under this arrangement, the District authorized and approved requested work with the issuance of change order tickets. Within 30 days of completion of such work, it was to submit these change order tickets, together with its re
Article 8 of the contract obligated the District to make monthly progress payments on itemized estimates submitted by Pierce and approved by the contracting officer. Article 8 also authorized the District to withhold a retainage of 10% of progress payments “until completion and acceptance of the Contract work.” 3 After substantial completion of the work, the contracting officer was empowered, but not required, to release excess retainages if the District’s interests were adequately protected. 4 Final payment of the retainage was due only upon completion and acceptance of all work by the contracting officer and after Pierce had executed a final voucher and release of all claims arising under the contract. Article 11 of the contract provided for inspection of all work by the District; the District agreed to make acceptance and payment “as promptly as practicable after completion and acceptance of all work required by the Contract.”
Although the District timely paid the bulk of the contract price through progress payments to Pierce as the work proceeded, a dispute arose as to when certain final payments under the contract were due. Pierce’s complaint alleges that it “substantially completed” its contractual obligations and had “expended 99.5% of its final recorded costs” as of April 1, 1983, and that the District’s final payments became due at this time. The District disputed that Pierce substantially completed its obligations under the contract as of this date. It is undisputed, however, that Pierce submitted change order vouchers throughout the summer and fall of 1983 and that on November 4, 1983, Pierce submitted a list of change proposals for which it had not been paid. This list contained a request for payment of $362,822 for work completed or billed after April 1, 1983. The District made payments on several, but not all, of these requested change orders after April 1.
On December 5, 1983, Pierce presented, at the District’s request, its final bill to the District’s contracting officer for all outstanding payments due. This statement indicated that the District had made payments of $11.28 million, and that $485,-283.85 remained unpaid. The bill was accompanied by a form release, dated December 6, 1983, specifying that Pierce would release the District from all further claims upon payment of the remaining amount. In December 1983 and January 1984, the District’s contracting officer approved the remaining change orders submitted by Pierce, and, in a May 1, 1984 letter, agreed that the District owed Pierce $485,283.85. Although the District acknowledged its indebtedness, it did not pay Pierce this amount until September 25, 1984, over a month after the complaint in the instant case was filed on August 16, 1984. 5
In its complaint in the Superior Court, Pierce, relying on
The District also filed a motion for summary judgment. In its motion, the District argued that, as a matter of law, any interest due Pierce should be restricted by
The trial court entered summary judgment for Pierce,
8
holding that interest at a rate of 15.99% was to be paid by the District for the period in which it delayed payment of the principal debt of $485,-283.85. In an oral opinion, the court concluded that the debt was disputed, and therefore unliquidated, because the District failed to pay the debt for a significant period of time after it became due. The court therefore determined that
Alternatively, the trial court held that even if the debt was deemed acknowledged and liquidated, the 6% limit still could not apply, because “public policy and basic equity” required that awards under
Ill
The District first contends that the trial court erred by imposing the market rate of interest because such interest is limited by
As a threshold matter, we observe that
Prejudgment interest is available under
The general rule of
We further observe that neither
Under the common law, prejudgment interest was viewed as a penalty to be imposed to punish the wrongdoing of the delinquent debtor, rather than as compensation for the losses of the creditor. Out of this view, the dichotomy between unliq-uidated and liquidated amounts arose: while a person who failed to pay a debt which was fixed and certain was considered a wrongdoer subject to penalty, it was
In modern times the “penalty theory” of prejudgment interest increasingly has given away to the “loss” or “unjust enrichment” theory. This concept characterizes prejudgment interest as merely another element of damages, rather than as punishment for the wrongdoing of the defendant. Under the loss theory, whether the amount of the debt is readily ascertainable is irrelevant; the important question is whether the plaintiff has been deprived of the use of the money withheld and should be compensated for the loss.
See
Recent Developments,
supra,
15 Stan.L.Rev. at 109-10. Although courts have been slow to give up the traditional dichotomy between liquidated and unliquidated debts, the increasing acceptance of the loss theory has been reflected in the creation of statutes and judicial exceptions, such as that in
In this light, the discretionary equitable authority of § 15-109 to award prejudgment interest in breach of contract actions involving unliquidated claims can be reasonably viewed as the legislature’s attempt to equalize the treatment of liquidated and unliquidated amounts, providing an exception to the common law prohibition against prejudgment interest in cases where the damages are not initially known. Therefore, for purposes of clarification, we now hold that the statutory limit on prejudgment interest expressed in
Having determined that prejudgment interest must be limited to the statutory rate, we must now decide which Code section and corresponding time frame for recovery applies in the instant case. As stated
supra,
to determine whether §§ 15-108 or -109 applies, we must determine whether the debt is liquidated or unliqui-dated.
See Giant Food, Inc., supra,
In this case, the District disputed neither the amount of the debt nor the fact that it was required to pay it. The District only disputed
when
the payment was due, rejecting the April 1, 1983 date on which Pierce claimed it had substantially performed; the District maintained instead that the payment was due at a later time, after it approved and accepted Pierce’s work.
11
Indeed, “[i]t would be somewhat
Given that the amount due on the contract was a liquidated sum, Pierce was entitled to. prejudgment interest pursuant to
IV
We now turn to the District’s final contention, that the court erred in granting summary judgment to Pierce because genuine issues of material fact existed concerning the dates on which the debt became due and the interest began to accrue. 12 The trial court determined that the District’s debt became due and payable to Pierce on April 1, 1983, the date Pierce avers that it had substantially completed its obligations under the contract. We conclude, however, that the trial court erred in this determination because the contract expressly states that such debts become due and payable only upon final completion by Pierce and acceptance by the District of the contract work. Article 3 mandates the District’s acceptance of the change orders as a precondition to payment; Article 8 mandates the completion and acceptance of all work before the return of the 10% retain-age. 13
Summary judgment is permissible only when no genuine issue of material fact exists, after all inferences in the record are drawn against the moving party.
Spellman v. American Security Bank,
We remand the case to the trial court for a hearing to determine the dates of the District’s acceptance of the change orders and the final acceptance of all work for purposes of the return of the retainage, with instructions that prejudgment interest shall be assessed at 6% from these dates, in accordance with
Reversed and remanded for further proceedings consistent with this opinion.
Notes
. We note at the outset that such cases involving the District as a contracting party are unlikely to recur because of enactment of the District of Columbia Quick Payment Act,
. Article 3C provides: ‘If any change ... causes an increase in the Cont-actor’s cost of, or the time required for the performance of any part of the work under this contract, ... an equitable adjustment shall be made and the contract modified in writing accordingly.” Under Article 7, in the event of a dispute concerning equitable adjustments, Pierce was to present its claims to the contracting ofñcer, and if dissatisfied with his actions, to appeal to the Contract Appeals Board.
. This contractual provision is mandated by
. Under
. District funding for the Convention Center had run out and additional funds could not be obtained until District officials requested, and Congress approved, additional monies on August 23, 1984.
.
Interest on judgment for damages in contract or tort.
In an action to recover damages for breach of contract the judgment shall allow interest on the amount for which it is rendered from the date of the judgment only. This section does not preclude the jury, or the court, if the trial be by the court, from including interest as an element in the damages awarded, if necessary to fully compensate the plaintiff.
.
Interest on judgment for liquidated debt.
In an action in ... the Superior Court of the District of Columbia to recover a liquidated debt on which interest is payable by contract
or by law or usage the judgment for the plaintiff shall include interest on the principal debt from the time when it was due and payable, at the rate fixed by the contract, if any, until paid.
Rate of interest not expressed and on judgments.
The rate of interest in the District upon the loan or forbearance of money, goods, or things in action in the absence of expressed contract, is 6 percent per annum.
.The court rejected Pierce’s claim that the District's conduct had been fraudulent. It also dismissed Pierce’s claims against individual District officials. Pierce does not appeal from these rulings.
. It should be noted that the federal district court has awarded prejudgment interest under
. While we agree with the trial court’s concern that
. On December 5, 1983, Pierce presented the District with a final bill for $485,283.85. Of this sum, $476,288.32 represented work done pursuant to change orders 23 through 30. The con-
. Given our disposition in Part III, supra, we need not reach the District’s related contention — that it was also error for the trial court to grant summary judgment because there was a genuine issue of material fact concerning the then-prevailing market interest rate.
. The dates of the District’s acceptance are not discernible from the record before us. It appears that different portions of the final bill of $485,283.85 became due and payable at different times. On December 5, 1983, Pierce presented the District with a final bill for $485,-283.85. Of this sum, $476,288.32 represented work done pursuant to change orders 23 through 30. Some of these change orders were approved by the District’s contracting officer on December 8, 1983, some on January 9, 1984, and the remainder on January 26, 1984. The remainder of the bill was the retainage kept by the District, which under Article 8 was due after completion and acceptance of all work by the District. The District was apparently willing to concede at oral argument, however, that it finally accepted and became liable for all change orders and other work effective 30 days after Pierce presented its final bill on December 5, 1983, or January 4, 1984. It therefore now suggests that this should be the appropriate starting date for the accrual of prejudgment interest.