History
  • No items yet
midpage
Vintage Construction, Inc. v. Feighner
2017 MT 109
| Mont. | 2017
Read the full case

Background

  • Myers ( homeowner and attorney ) hired Vintage to finish construction after a prior contractor quit; parties had no fully signed contract but Vintage’s written estimate ($398,880.46) and oral agreements (including a 10% contractor fee) framed the deal.
  • Vintage began work Feb 28, 2013; by Sept 2013 Vintage provided a $91,107.50 completion estimate to Myers and U.S. Bank based on subcontractor bids; a subcontractor (Sisson) later produced a lower bid that proved insufficient and then walked off the job.
  • Myers hired another mason (Brawley) who completed stonework using a pallet of Bighorn stone Vintage had paid for; Myers withheld $4,310 paid to Brawley and $2,973 (cost of the pallet) and disputed a 10% fee on Leonardi’s driveway work.
  • Myers’ counterclaims alleging defective masonry and remediation costs were hampered by his failure to timely disclose experts and damage amounts; the district court excluded or limited expert testimony and found Myers failed to prove damages.
  • The district court found Vintage’s lien was properly filed but declined to permit foreclosure or award attorney’s fees because of Myers’ dissatisfaction with some masonry work; however the court awarded Vintage $8,317 in contractual damages (10% on Leonardi work, $4,310 withheld payment, and $2,973 for the stone pallet).
  • On appeal the Montana Supreme Court affirmed the damages award, affirmed dismissal of Myers’ counterclaims, but reversed and remanded the lien-foreclosure/attorney’s-fees denial, holding the lien covered work substantially completed and attorney’s fees are mandatory for an established lien.

Issues

Issue Vintage's Argument Myers' Argument Held
Whether district court properly awarded contractual damages to Vintage Vintage: estimate + parties’ conduct established contract terms (including 10% fee) and Vintage was owed withheld sums and cost of stone Myers: driveway/stone purchases were outside contract or Vintage breached so Myers could deduct costs Affirmed — substantial evidence supported award of $8,317 (10% fee on Leonardi, $4,310, $2,973)
Whether Vintage could foreclose its construction lien and recover attorney’s fees under § 71-3-124, MCA Vintage: lien statutes require work be completed or substantially completed and lienable materials incorporated — not subjective satisfaction; an established lien mandates attorney’s fees Myers: poor/unsatisfactory masonry work defeats foreclosure and fees Reversed — lien covered work/materials substantially completed (including stone pallet); attorney’s fees are mandatory for established liens and must be awarded

Key Cases Cited

  • dck Worldwide Holdings v. CH SP Acquisition, LLC, 380 Mont. 215, 355 P.3d 724 (Mont. 2015) (construction-lien statutory interpretation and remedial purpose)
  • Mt. W. Bank, N.A. v. Cherrad, 369 Mont. 492, 301 P.3d 796 (Mont. 2013) (standard for reviewing district-court factual findings and damages)
  • Johnston v. Palmer, 337 Mont. 101, 158 P.3d 998 (Mont. 2007) (definition of substantial evidence and appellate review limits)
  • Lewistown Miller Constr. Co. v. Martin, 363 Mont. 208, 271 P.3d 48 (Mont. 2011) (statutory mandate to award attorney’s fees for an established construction lien)
  • LHC, Inc. v. Alvarez, 337 Mont. 294, 160 P.3d 502 (Mont. 2007) (presumption materials delivered to site were incorporated into improvement)
  • Gwynn v. Cummins, 333 Mont. 522, 144 P.3d 82 (Mont. 2006) (lien arises upon completion or substantial completion)
  • Van Stone v. Stillwell & Bierce Mfg. Co., 142 U.S. 128 (U.S. 1891) (use of materials and labor gives rise to lien under statute)
Read the full case

Case Details

Case Name: Vintage Construction, Inc. v. Feighner
Court Name: Montana Supreme Court
Date Published: May 9, 2017
Citation: 2017 MT 109
Docket Number: DA 16-0338
Court Abbreviation: Mont.