Van Stone v. Stillwell & Bierce Manufacturing Co.Van Stone v. Stillwell & Bierce Manufacturing Co.
after stating the case, delivered the opinion of the court.
It is manifest from an inspection of this assignment that it is entirely too general to meet the requirements of the 21st rule of this court. It was evidently framed with reference to the code practice of the State in which the cаuse was tried; but nothing is better settled in this court than the proposition that “ in regard to . . . bills of exceptions, courts of the United States ai;e independent of any statute or practice prevailing in the courts of the Stаte in which the trial was had.”
Fishburn
v. Chicago,
Milwaukee &c. Railway Co.,
It requires nothing more than a mere statement to show that the first error assigned is without foundation. Under the pleadings as framed and the issues 'thus- made up, it was not only not error for the court to admit evidenсe in the case, but it would have been a grave error to have refused to allow the admission of evidence. Moreover, the record fails to show that any objection of any kind or character was madе by plaintiff in error to the introduction of evidence.
With respect to the third and eighth errors assigned,-it.may be said that they are as untenable as the first. A general demurrer to the evidence was interposed by the plaintiff in еrror at the close of the testimony offered by the plaintiff below,
With respect to the fourth error assigned, it is sufficient to say that the overruling of a motion for a new trial in the court below cannot be assigned for error, and no authorities need be cited in support of the proposition.
The fifth and sixth alleged errors go more to the merits of the action than any we have yet considered. “ A motion in arrest of judgment can only be maintained for a dеfect apparent upon the face of the record, and the evidence is no part of the record for this purpose.”
Bond
v.
Dustin,
The argument against the right of the court to enter up a judgment recognizing and enforcing a mechanics’ lien is based on the theory that the contract between Schupp and Van. Stone, under which the mill was built, providing, as it .did, for the payment of the price in instalments to become due after the time limited by the statute (9 months) within which an action to enforce the lien is required to be commenced, which deferred payments were to be secured upon real estate of the plaintiff in error, was an express waiver of the lien, and
This argument rests upon a misconception as to the nature and character of a mechanics’ lien. This lien is a creature of the statute, and was not recognized at common law. It may be defined to be a claim created by law for the purpose of securing a priority of payment of the price and value оf work performed and materials furnished in erecting or repairing a building or other structure, and as such it attaches to the land as well as the buildings erected thereon. 15 Amer. & Eng. Encyc. Law, 5. Now, it is not the contract for ereсting or repairing the building which creates the lien, but it is the use of the materials furnished and the work' and labor expended by the contractor, whereby the building becomes a part of the freehold, that gives the material man and laborer his lien under the statute. The lien is brought into operation by virtue of the statute, and the contract for building is entered into presumably in view of, or with reference to, the statute.
The rule seems to be established in Missouri, аnd it is so in many of the other States, that a contractor does not waive his right to file a mechanics’ lien by receiving from the owner of the building a promissory note for the amount due, payable at a time beyond the expiration of the period within which he is required to file his lien, but within the period within which suit must be commenced to enforce the lien, the taking of the note merely suspending the right of action. McMurray v. Taylor, 30 Missouri, 263; Ashdown v. Becker, 31 Missouri, 465; Jones v. Hurst, 67 Missouri, 568, 572. This rule is based upon the principlе, recognized in that State, that the execution of a note for a preexisting debt is not a payment of the debt, but only presumptively so; but a party relying upon that principle must, in an action on the original debt, prоduce the note for cancellation. Authorities last cited; Brooks v. Mastin, 69 Missouri, 58; Doebling v. Loos, 45 Missouri, 150.
Under this rule of law, the contention of the plaintiff in error must fail. For,
a fortiori,
would the right to file the lien remain, where, as in this case, no notes were given at all, but the agrеement to give them was broken by the owner of
But one alleged error remains to be considered, viz., the seventh. Exhibit “A,” referred to therein, is a letter from Van Stone to Schupp, as follows:
“ Marshall, Mo., Aug. 6, 1885.
“ F. J. Schupp, Esq., Marshall,
“ Dear Sir: The flour mill put up by you for me is satisfactory to mе and is hereby accepted. The corn-rolls do not work to my satisfaction. Whenever such rolls are put in or shall do satisfactory work. I shall be ready to pay for the entire work.
“0. H. Van Stone.”
It is urged that the court below erred in construing this letter to be a waiver of the time within which the mill was to be built. So far as concerns that portion of the letter relating to the part of the mill used for the manufacture of flour, it is an unconditional acceptance. It could not be made more positive. Nor do we think the latter part of .the letter relating to the corn-rolls is susceptible of any other construction than the one put upon it by the court. By the language thеre used the plaintiff in error bound himself to pay for the entire work whenever it should be completed so that the corn-rolls
Judgment affirmed.