History
  • No items yet
midpage
526 S.W.3d 709
Tex. App.
2017
Read the full case

Background

  • CTC (general contractor) hired Vast (subcontractor) to perform Cornish Street work for $355,000; the signed Subcontract was silent as to which party must obtain permits and included an "entire agreement" merger clause and termination/cure provisions.
  • Vast obtained several permits, sought a lane-closure permit (requiring a traffic control plan), invoiced CTC for mobilization, but CTC did not pay Vast before Vast ceased work in mid‑March 2014 and cancelled permits and bonds.
  • CTC notified Vast of default (failure to prosecute, comply, and interference/abandonment), hired A&M to finish the work for higher cost, and sued Vast for breach seeking the difference in costs; Vast counterclaimed for breach, prompt-payment violations, and violation of the Texas Construction Trust Fund Act (TCTFA).
  • At trial the court excluded Vast’s pre-bid proposal (which expressly excluded permits), submitted broad-form questions whether Vast or CTC failed to comply, and the jury found Vast breached and CTC did not; jury awarded CTC $91,900 in damages and the trial court awarded CTC attorneys’ fees under Tex. Civ. Prac. & Rem. Code § 38.001.
  • On appeal the court affirmed the breach and damages findings (breach supported by undisputed evidence that Vast abandoned the job), rejected Vast’s evidentiary and charge-error arguments, but held the award of attorneys’ fees under § 38.001 against an LLC was erroneous and modified the judgment to remove all fee awards.

Issues

Issue Plaintiff's Argument (CTC) Defendant's Argument (Vast) Held
Whether Vast breached the Subcontract Vast abandoned the project and therefore breached; jury should decide Vast argued as matter of law Subcontract did not require it to obtain permits so no breach Court: Affirmed breach verdict — broad-form question allowed finding of breach (abandonment) supported by legally sufficient evidence
Admissibility of Vast’s pre-bid proposal Exclusion proper under parol-evidence/merger; Subcontract controls Proposal should be admitted to show permits were excluded Court: Even if exclusion erroneous, any error was harmless because abandonment alone supported verdict
Requested materiality instruction Not necessary given evidence of substantial breach Materiality instruction required for jury Court: Refusal not reversible error; other findings (abandonment) made instruction unnecessary
Sufficiency of damages award Award within range of evidence (difference between CTC’s completion costs and Vast’s price) Award unsupported because A&M contract covered extra items (bonds, fire line, permits) Court: Award supported by factual evidence; jury discretion; not so contrary to weight of evidence as to be unjust
Prompt-payment statute claim (Tex. Prop. Code) N/A (CTC plaintiff) Vast argued CTC received owner payment and failed to timely pay subcontractor, entitling Vast to relief and fees as matter of law Court: Jury found CTC did not breach; Vast could not show entitlement as matter of law; prompt-payment claim and fee request denied
TCTFA jury question N/A Vast argued CTC misapplied trust funds by paying unrelated attorneys’ fees Court: No evidence CTC used trust funds for improper purposes; refusal to submit question proper
Attorneys’ fees under Tex. Civ. Prac. & Rem. Code § 38.001 Sought fees for breach of contract against Vast Vast argued LLC is not an individual or corporation under § 38.001 Court: Sustained Vast’s claim; § 38.001 does not authorize fees against an LLC — vacated all attorney fee awards

Key Cases Cited

  • City of Keller v. Wilson, 168 S.W.3d 802 (Tex. 2005) (standard for legal sufficiency review and viewing evidence in light most favorable to the verdict)
  • Meek v. Bishop Peterson & Sharp, P.C., 919 S.W.2d 805 (Tex. App.—Houston [14th Dist.] 1996) (court determines contractual duties as legal questions)
  • Hammerly Oaks, Inc. v. Edwards, 958 S.W.2d 387 (Tex. 1997) (broad-form jury charge governs when not objected to on appeal)
  • Marathon Corp. v. Pitzner, 106 S.W.3d 724 (Tex. 2003) (standards for sustaining legal-sufficiency/no-evidence challenges)
  • Dealers Elec. Supply Co. v. Scroggins Constr. Co., 292 S.W.3d 650 (Tex. 2009) (TCTFA trust-fund principles and beneficiary status)
  • Thota v. Young, 366 S.W.3d 678 (Tex. 2012) (harmless-charge-error standard)
  • Epps v. Fowler, 351 S.W.3d 862 (Tex. 2011) (American Rule and that fees are recoverable only by statute or contract)
  • Alta Mesa Holdings, L.P. v. Ives, 488 S.W.3d 438 (Tex. App.—Houston [14th Dist.] 2016) (§ 38.001 does not authorize recovery of attorney’s fees against an LLC)
Read the full case

Case Details

Case Name: Vast Construction, LLC v. CTC Contractors, LLC
Court Name: Court of Appeals of Texas
Date Published: Jul 6, 2017
Citations: 526 S.W.3d 709; 2017 WL 2882197; 2017 Tex. App. LEXIS 6146; NO. 14-16-00005-CV
Docket Number: NO. 14-16-00005-CV
Court Abbreviation: Tex. App.
Log In