delivered the opinion of the Court.
Chapter 2253 of the Texas Government Code, historically called the McGregor Act, requires a prime contractor on a public-work contract to execute a payment bond to protect laborers and materialmen who work on or supply materials for the project. See Tex. Gov’t Code § 2253.021(a)(2). In this case, an electrical subcontractor on a bonded public-work project walked off the job, leaving his supplier of electrical parts unpaid. The supplier missed the McGregor Act deadline to pursue a claim on the bond, and filed this suit against the prime contractor for violation of the Texas Construction Trust Fund Act, Tex. Prop. Code §§ 162.001(a), 162.031(a), and breach of a separate Joint Check Agreement designed to ensure payment for materials supplied to the subcontractor. We must decide whether the McGregor Act provides the supplier’s exclusive remedy. We hold that it does not. Accordingly, we reverse the court of appeals’ judgment and remand the case for the court to consider the remaining issues it did not address.
I. Background
Scoggins Construction Company, Inc. (SCC) entered into a $5,751,000.00 public-work contract with Mercedes Independent School District (MISD) in February 2001 for the construction of an elementary school in Mercedes, Texas. 1 Pursuant to section 2253.021(a)(2) of the McGregor Act, SCC executed a payment bond with Fidelity and Deposit Company of Maryland (Fidelity) and Colonial American Casualty and Surety Company (Colonial). SCC subcontracted with Art Bujanos d/b/a Diamond Industries (Diamond) to provide electrical labor and materials for $662,000.00. 2 In March 2001, SCC, Diamond, and Dealers Electrical Supply Co. (Dealers) entered into a Joint Check Agreement whereby, in an effort to “induce [Dealers] to extend or continue extending credit to [Diamond],” SCC agreed to “make all payments for all materials and/or services furnished by [Dealers] to the project by check made jointly payable to [Diamond] and [Dealers].” Based on this agreement, Dealers sold and delivered electrical materials to Diamond for the project between January 1, 2002, and May 2, 2002. In early May 2002, Diamond walked off the job, leaving Dealers unpaid for electrical supplies it had provided.
Dealers sued SCC and SCC’s president, Bill Scoggins (collectively, Scoggins), and Diamond, jointly and severally, for violating Chapter 162 of the Texas Property Code, known as the Texas Construction Trust Fund Act, Tex. Prop.Code § 162.001-.033, and for breaching the Joint Check Agreement. Dealers also sued Scoggins, Fidelity, and Colonial, jointly and severally, under the McGregor Act to recover on the payment bond, but later dropped that claim because it failed to comply with the Act’s mandatory notice requirements.
See
Tex. Gov’t Code §§ 2253.041, 2253.073. After a bench trial, the court ruled that Scoggins violated the Trust Fund Act by receiving payment for electrical materials supplied to the project and failing to pay Dealers for them, and that SCC failed to guarantee payment as
Scoggins appealed, contending the McGregor Act was Dealers’ exclusive remedy. In the alternative, Scoggins challenged the evidence to support a judgment for violation of the Joint Check Agreement or the Trust Fund Act, and the evidence to hold Bill Scoggins personally liable for the debt. Finally, Scoggins claimed that Dealers failed to refute affirmative defenses that Scoggins proved under the Trust Fund Act. The court of appeals agreed that the McGregor Act was Dealers’ sole remedy and reversed the trial court’s judgment, rendering a take-nothing judgment against Dealers on its alternative claims.
II. Discussion
A. The McGregor Act’s Purpose
The McGregor Act was enacted to protect public-work laborers and material-men, since a lien cannot generally be asserted against a public improvement.
See Mosher Mfg. Co. v. Equitable Surety Co.,
The McGregor Act is intended to be a simple and direct method for claimants who supply labor and materials for public-work projects to give notice and perfect their claims under the Act.
Capitol Indem. Corp. v. Kirby Rest. Equip. & Chem. Supply Co.,
B. Does the McGregor Act Preclude a Remedy under the Texas Construction Trust Fund Act?
Scoggins contends the remedy available to an unpaid public-work laborer or mate-rialman under the McGregor Act is exclusive. First, Scoggins points to
Commercial Union Insurance Co. v. Spaw-Glass Corp.,
1. Commercial Union and Bunch
The court of appeals relied on
Commercial Union,
In
Commercial Union,
a prime contractor agreed to build a school for Judson Independent School District.
The court of appeals denied Commercial Union’s claim, reasoning that because the suppliers failed to comply with the McGre-gor Act’s notice requirements, the suppliers would not have been entitled to recover from Commercial Union or the prime contractor on the bond.
Id.
at 540. Thus, Commercial Union should not be allowed to stand in the suppliers’ shoes.
Id.
Recognizing that Commercial Union’s suit was not a McGregor Act claim, the court noted that the Act’s notice requirements “must be strictly complied with if there is to be recovery from a payment bond,” and that allowing Commercial Union to assert a claim the suppliers failed to perfect would eviscerate the notice requirements’ purpose.
Id.
Additionally, the court stated that “the Act provides the exclusive remedy for laborers and suppliers on a public project.”
Id.
(citing
Bunch,
In
Bunch,
Tex-Craft Builders, Inc. contracted with the Housing Authority of the City of Crockett, Texas, to construct a public-housing project.
While there is some language in
Commercial Union
and
Bunch
that might appear to support Scoggins’ position, neither case turned on the McGregor Act’s exclusivity. The history of the McGregor Act, as well as the case long cited for the Act’s
exclusivity
—South
Texas Lumber,
At the time
South Texas Lumber
was decided, the McGregor Act required that a contractor on a public-work project obtain “the usual penal bond, with the additional obligation that such contractor shall promptly make payments to all persons supplying him or them with labor and materials in the prosecution of the work provided for.” Act of Mar. 19, 1929, 41st Leg., R. S., ch. 226, § 1, 1929 Tex. Gen. Laws 481, 481. Any laborer or material-man seeking payment for work or supplies had the “right to intervene and be made a party to any action instituted by the [governmental entity] on the bond ... subject, however, to the priority of the claims and judgment of the [governmental entity].”
Id.
However, if the governmental entity failed to bring suit “within six months from the completion and final settlement of [the] contract,” the governmental entity would lose priority, and any laborer or material-man could prosecute a suit on the bond. Act of Mar. 20, 1913, 33rd Leg., R.S., ch. 99, § 2, 1913 Tex. Gen. Laws 185, 185-86 Any claim by a laborer or materialman against the bond, though, was required to be brought within one year from the completion and final settlement of the public-work project.
Id.
at § 3,
In
South Texas Lumber,
A.E. Quay contracted with the City of Houston for the construction of certain public improvements. The Indemnity Insurance Company of North America was Quay’s surety.
South Texas Lumber,
2. The Trust Fund Act’s Language
Beyond focusing on the exclusivity language found in
Commercial Union
and
Bunch,
the court of appeals cited two decisions interpreting earlier versions of the Trust Fund Act.
See Truckers, Inc. v. S. Tex. Constr. Co.,
Until 1987, the Trust Fund Act, by its terms, did not apply to
“receipts
under a construction contract if the full contract amount [was] covered by a corporate surety bond.” Act of May 27, 1983, 68th Leg., R.S., ch. 576, § 1, 1983 Tex. Gen. Laws 3475, 3721 (amended 1987) (current version at Tex. Prop.Code § 162.004) (emphasis added). Thus, until 1987, Dealers would not have been entitled to assert a trust-fund claim against Scoggins, as the prime contract in this case was covered by a corporate surety bond. However, in 1987 the Act was amended, eliminating the language that excluded receipts under a bonded project. Act of May 25,1987, 70th Leg., R.S., ch. 578, § 2, 1987 Tex. Gen. Laws 2283, 2283. As amended, the Trust Fund Act instead exempts from liability “a
corporate surety
who issues a payment bond covering the contract for the construction or repair of the improvement.” Tex. Prop.Code § 162.004(a)(3) (emphasis added). By narrowing the statutory exemption in this manner, the Legislature unequivocally expanded the Trust Fund Act’s purview.
See Fleming Foods of Tex. v. Rylander,
The court of appeals, however, determined that the change in the Trust Fund Act’s language was non-substantive, and relied on cases interpreting the Act prior to the 1987 amendment.
Additionally, since neither the McGregor Act nor the current version of the Trust Fund Act are expressly exclusive of the other, they can only be exclusive by implication.
See Holmans v. Transource Polymers, Inc.,
As noted earlier, the purpose of the McGregor Act is to provide unpaid public-work laborers and materialmen with an additional remedy and a simple and direct method to perfect their claims to that remedy.
See Capitol Indem. Corp.,
3. Double-Liability and Public-Policy Considerations
Scoggins raises an additional concern, contending that the McGregor Act’s notice requirement is irreconcilable with the Trust Fund Act’s four-year limitations period.
7
See
Tex. Gov’t Code § 2253.041. According to Scoggins, if a public-work laborer or materialman provides timely notice under the McGregor Act, the prime contractor will withhold payment from the subcontractor and promptly pay the McGregor Act claimant; thereafter, the prime contractor will deduct that amount from what it pays the subcontractor. Scoggins claims this statutory scheme allows the prime contractor to pay all subcontractors once the notice period has passed, safe in the assumption that no more claims may be asserted. If trust-fund claims may be brought beyond the notice period, Scoggins contends, prime contractors will be reluctant to pay their subcontractors until four years after the laborer or materialman’s work is completed, causing subcontractors to institute litigation with resultant costs and delays that will hinder public-work projects. Scoggins also argues that a prime contractor may be subject to double liability when the prime
First, the argument presupposes that the McGregor Act was intended to benefit contractors by shielding them from all non-McGregor Act liability after the ninety-day notice deadline passes. The Act, however, was enacted to protect unpaid laborers and materialmen by providing them an additional funding source — a payment bond — in the event the prime contractor fails to meet its obligations. Foreclosing laborers’ and materialmens’ alternative remedies if the McGregor Act’s strict notice requirements are not met would undermine its overarching purpose, particularly considering that many laborers and suppliers might have difficulty complying with the Act’s notice requirements without the assistance of legal counsel.
Second, since the Trust Fund Act was amended in 1987, bond and trust-fund claims appeal to have co-existed harmoniously in the private-construction context even though such bond claims, too, generally come with stringent notice requirements.
See Perry & Perry Builders, Inc. v. Galvan,
No. 03-02-0091-CV,
Third, the Trust Fund Act provides an affirmative defense when the trust funds not paid to a laborer or materialman were used to pay the trustee’s “actual expenses directly related to the construction or repair of the improvement.” Tex. Prop.Code § 162.031(b). Such expenses include payments to subcontractors for costs actually and directly tied to the improvement.
See Taylor Pipeline Constr., Inc. v. Directional Road Boring, Inc.,
Finally, Scoggins’ concern that the availability of non-McGregor Act claims will hinder the timely payment of laborers and materialmen on public-work contracts raises a policy concern that is within the Legislature’s realm to decide; that the Legislature has not chosen to make the McGregor Act remedy exclusive, despite its obvious ability to do so, is the best indication of its policy.
See, e.g., Tex. Dep’t of Transp. v. Jones Bros. Dirt & Paving Contractors,
C. The Joint Check Agreement
Although the parties disagree as to the effect of the Joint Check Agreement, one fact is uncontested: the Joint
According to Dealers, the Joint Check Agreement was an unconditional guarantee by SCC to pay for any materials Dealers provided to Diamond. We disagree. In relevant part, the agreement provides that “[SCC] agrees to make all payments for all materials ... furnished by [Dealers] ... by check made jointly payable to [Diamond] and [Dealers].” The agreement’s unambiguous language guarantees only that SCC will make payment by joint check. Thus, SCC complied with the agreement to the extent checks were made jointly payable to Diamond and Dealers, and the trial court erred by expanding the agreement’s scope. SCC has challenged the sufficiency of Dealers’ evidence to support a breach of the joint-payment provision, and we remand the issue to the court of appeals for consideration along with the remaining points.
III. Conclusion
While Texas cases and the statute itself support a conclusion that the McGregor Act provides a laborer or materialman’s mandatory and exclusive remedy against a surety and obligor on a public-work payment bond, that exclusivity does not extend beyond suit against the bond itself. Accordingly, we reverse the court of appeals’ judgment and remand the case to the court of appeals to consider the parties’ remaining arguments that were not addressed.
Notes
. For purposes of the McGregor Act, a " 'Lg]ovemmental entity' means a governmental or quasi-governmental authority authorized by state law to make a public work contract, including ... a school district.” Tex. Gov't Code § 2253.001(1)(C). A “ ‘[public work contract’ means a contract for con-strutting ... a public building.” Therefore, the contract between SCC and MISD is a public-work contract.
. After two subsequent change orders, the total contract amount between SCC and Diamond was $665,789.00.
. " 'Payment bond beneficiary’ means a person for whose protection and use [the Act] requires a payment bond.” Tex. Gov’t Code § 2253.001(2). It is undisputed that Dealers is a payment bond beneficiary under the Act.
. In 1959, the Legislature took direct action to eradicate several problems created by die statutory scheme. First, the McGregor Act was amended to provide that "[a]ny bond furnished by any prime contractor in attempted compliance with [the Act] shall be treated and construed in conformity with the requirements of [the Act] as to rights created, limitations thereon, and remedies provided.” Act of April 13, 1959, 56th Leg., R.S., ch. 93, § 1, 1959 Tex. Gen. Laws 155, 155. In doing so, it seems the Legislature meant to clarify the precise issue presented in South Texas Lumber, effectively eliminating any argument that a laborer or materialman could assert a common law action against a McGregor Act bond. Additionally, the Legislature implemented the requirement that — with regard to public-work contracts of a certain minimum amount — the prime contractor obtain two bonds: (1) a performance bond to protect the governmental body; and (2) a payment bond to protect "all claimants supplying labor and material.” Id. By requiring separate bonds, the Legislature appears to have eliminated the need for governmental-entity priority in a suit against a single bond.
. The court of appeals indicated that the Trust Fund Act does not protect unpaid laborers or materialmen in the private construction context.
. See Act of May 27, 1967, 60th Leg., R.S., ch. 323, §§ 1-7, 1967 Tex. Gen. Laws 770, 770-71, repealed by Act of May 27, 1983, 68th Leg., R.S., ch. 576, § 6, 1983 Tex. Gen. Laws 3475, 3729-30 (current version at Tex. Prop. Code §§ 162.001-.004, §§ 162.031-,033).
. The McGregor Act requires notice to be mailed on or before the fifteenth day of the third month after labor or materials was supplied. Tex. Gov’t Code § 2253.041(b). The Trust Fund Act does not provide a statule of limitations. When a statute of limitations is not provided, a four-year limitations period applies. Tex. Civ. Frac. & Rbm.Code § 16.051.
