History
  • No items yet
midpage
207 Conn.App. 551
Conn. App. Ct.
2021
Read the full case

Background:

  • NJR (general contractor) contracted with the DOT to replace a bridge with an 8‑week detour; DOT contract paid $3,000/day incentive (max $60,000) for early reopening and imposed $3,000/day disincentives for delay. NJR triggered the detour by closing the bridge June 13, 2016.
  • United Concrete (subcontractor) agreed to furnish ten prestressed deck beams for $244,672.50, with delivery required “on or before June 7, 2016” and a “time is of the essence” clause. NJR later scheduled delivery for June 29 based on supplier representations.
  • United Cement failed multiple pours; it notified NJR two days before the June 29 shipment that beams would not be ready. Beams were delivered July 26; project finished August 31. NJR paid part of the subcontract then withheld the balance.
  • United sued NJR and surety Aegis under contract and the Little Miller Act (§§ 49‑41a, 49‑42). NJR counterclaimed for breach and CUTPA; trial court found United materially breached but had its UCC claim allowed because NJR accepted the goods; awarded United the contract balance, denied § 49‑41a relief, awarded NJR damages, attorney’s fees under the subcontract, and found a CUTPA violation. The trial court also ruled for Aegis on the bond claim.
  • On appeal this court affirmed most rulings but reversed only the trial court’s judgment for Aegis under § 49‑42, holding the surety’s liability under the payment bond is not conditioned on United’s § 49‑41a entitlement to interest/fees and remanded count three for a new trial.

Issues:

Issue Plaintiff's Argument Defendant's Argument Held
Proper start date for NJR’s damages (June 7 vs June 29) / inclusion of lost incentive June 29 was the operative delivery date NJR requested; use of June 7 inflated damages and incorrectly included $60,000 incentive Subcontract required beams to be ready by June 7; scheduling June 29 did not relieve supplier; even if June 29 used, NJR could have earned the incentive Using June 7 was not clearly erroneous; court’s timeline (worst‑case 36 days) supports inclusion of incentive; alternative harmlessness also shown
Failure to mitigate (NJR accelerating after July 26 delivery) NJR should have accelerated work after beams arrived to reduce disincentive damages NJR reasonably abandoned fast‑track once incentive was lost; acceleration would have been unrecoverable and imprudent Trial court’s finding that NJR reasonably mitigated was supported by evidence; no failure to mitigate
Liability of surety Aegis under payment bond (§ 49‑42) Aegis is liable for unpaid balance notwithstanding trial court’s denial of § 49‑41a interest/fees Trial court treated bond claim as dependent on § 49‑41a substantial performance finding and denied it Reversed as to Aegis: bond and § 49‑42 enforcement are distinct; surety is jointly/severally liable for amounts principal owes unless a statutory defense applies; remand for new trial on bond claim
Award of interest and attorney’s fees to subcontractor under § 49‑41a United says NJR waived “time is of the essence,” so United substantially performed and is entitled to § 49‑41a relief NJR says United materially breached and the § 49‑41a fees/interest are properly denied; waiver argument not raised at trial Appellate court declined to reach waiver argument raised first on appeal; trial court’s denial stands
CUTPA liability and NJR’s contractual attorney’s fees award United: its conduct was a mere breach, no aggravating conduct to support CUTPA; and NJR did not incur fees from a supplier default NJR: supplier made knowingly false assurances, causing extra expense and preventing remediation; subcontract expressly allows recovery of fees for supplier default CUTPA finding affirmed (misrepresentations were immoral/unscrupulous and caused ascertainable loss); award of attorney’s fees under the subcontract affirmed (contract language permits recovery for supplier’s failure of promptness/diligence)

Key Cases Cited

  • Bernstein v. Nemeyer, 213 Conn. 665 (Conn. 1990) (material breach excuses nonbreaching party’s performance)
  • Connecticut Light & Power Co. v. Proctor, 324 Conn. 245 (Conn. 2016) (standard of review for factual findings)
  • Sun Val, LLC v. Commissioner of Transportation, 330 Conn. 316 (Conn. 2018) (mitigation duty; reasonableness is factual)
  • Blakeslee Arpaia Chapman, Inc. v. EI Constructors, Inc., 239 Conn. 708 (Conn. 1997) (Little Miller Act is remedial; separate remedies under §§ 49‑41a and 49‑42)
  • Nor’easter Group, Inc. v. Colossale Concrete, Inc., 207 Conn. 468 (Conn. 1988) (statutory notice under § 49‑41a not a prerequisite to suit under § 49‑42)
  • Joseph Gen. Contracting, Inc. v. Couto, 317 Conn. 565 (Conn. 2015) (contract interpretation principles and ambiguity)
  • Harris v. Bradley Memorial Hospital & Health Ctr., Inc., 296 Conn. 315 (Conn. 2010) (CUTPA unfairness criteria)
  • Ledyard v. WMS Gaming, Inc., 330 Conn. 75 (Conn. 2018) (distinction between final judgment and supplemental attorney’s fee awards)
Read the full case

Case Details

Case Name: United Concrete Products, Inc. v. NJR Construction, LLC
Court Name: Connecticut Appellate Court
Date Published: Sep 21, 2021
Citations: 207 Conn.App. 551; 263 A.3d 823; AC42244
Docket Number: AC42244
Court Abbreviation: Conn. App. Ct.
Log In