History
  • No items yet
midpage
831 F.3d 564
D.C. Cir.
2016
Read the full case

Background

  • Buckeye Wind sought an incidental take permit (ITP) under ESA §10 to build a ~250 MW wind farm in Champaign County, Ohio, where Indiana bats forage and migrate; Buckeye submitted a Habitat Conservation Plan (HCP) with siting, operational limits (feathering and variable cut‑in speeds up to 6.0 m/s), habitat protection (217 acres), and funding commitments.
  • The Service prepared a Draft and Final EIS, analyzed Buckeye’s proposal, a No Action Alternative, a Minimal Alternative (5.0 m/s cut‑in during high‑risk hours), and a Max Alternative (shut down turbines at night April–October), and issued the ITP finding Buckeye’s HCP "minimizes and mitigates" impacts "to the maximum extent practicable."
  • Buckeye’s proposal estimated ~5.2 Indiana bats taken per year; the Max Alternative would eliminate take but was projected to cause substantial lost energy and revenue and likely prevent the project from being built.
  • Union Neighbors challenged issuance of the ITP in district court, arguing (1) NEPA required analysis of a reasonable, economically feasible alternative that would take fewer bats (e.g., higher permanent cut‑in speeds); and (2) the Service misinterpreted ESA §10(a)(2)(B)(ii) concerning what "impacts" must be minimized and the meaning of "to the maximum extent practicable."
  • The district court upheld the Service; the D.C. Circuit reversed in part (NEPA) and affirmed in part (ESA), remanding for further NEPA analysis while upholding the Service’s ESA interpretation under Skidmore.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Whether the EIS considered a "reasonable range of alternatives" under NEPA Service failed to analyze any economically feasible alternative that would take fewer bats (e.g., higher cut‑in speed like 6.5 m/s) Service considered reasonable alternatives (Buckeye plan, Minimal, Max, No Action); infinite permutations need not be analyzed; Max offers a useful comparison Court: NEPA violation — Service failed to analyze a reasonable, economically feasible alternative that would reduce take below Buckeye’s plan; remand required
Proper interpretation of "impacts" in ESA §10(a)(2)(B)(ii) (what must be minimized/mitigated) "Impacts" means discrete individual takings (must minimize number of individual bats) "Impacts" refers to biological effects on populations/subpopulations and species‑level consequences; Service’s interpretation persuasive Court: Defer to Service under Skidmore — "impacts" means population/subpopulation/species effects, not solely raw count of individuals; Service’s findings not arbitrary
Meaning and application of "to the maximum extent practicable" and whether minimize/mitigate are sequential Minimization (reduce number taken) must be maximized first; then mitigation considered; Service applied an improper combined standard Service treats "minimize and mitigate" jointly (assess adequacy of measures and practicability together); economic feasibility considered where relevant; combined approach reasonable Court: Service’s joint treatment persuasive; its finding that combined minimization+mitigation offset impacts satisfied the statutory standard
Whether Gerber requires independent agency finding that reduced‑impact alternatives are impracticable Gerber requires the Service to make an independent finding that any known reduced‑impact alternative is impracticable before issuing permit Service made practicability findings re: Max Alternative (economic/production losses; project likely would not be built); for other alternatives court reserved whether further findings may be required after remand Court: On this record, Service’s rejection of Max Alternative suffices; Gerber claim not a basis to set aside the ESA findings now (may require more if new alternatives are adopted on remand)

Key Cases Cited

  • WildEarth Guardians v. Jewell, 738 F.3d 298 (D.C. Cir. 2013) (NEPA requires adequate consideration of environmental effects and alternatives)
  • New York v. NRC, 681 F.3d 471 (D.C. Cir. 2012) (NEPA is procedural, ensures informed agency decisionmaking)
  • Vt. Yankee Nuclear Power Corp. v. NRDC, 435 U.S. 519 (1978) (NEPA’s procedural mandate and limits on courts substituting judgment)
  • Baltimore Gas & Elec. Co. v. NRDC, 462 U.S. 87 (1983) (NEPA’s twin aims: consider environmental impacts and inform the public)
  • Gerber v. Norton, 294 F.3d 173 (D.C. Cir. 2002) (agency must address reduced‑impact alternatives or explain impracticability)
  • Chevron U.S.A., Inc. v. NRDC, 467 U.S. 837 (1984) (framework for judicial deference to agency statutory interpretations)
  • Skidmore v. Swift & Co., 323 U.S. 134 (1944) (agency interpretations receive deference proportional to persuasiveness)
  • Motor Vehicle Mfrs. Ass’n v. State Farm, 463 U.S. 29 (1983) (arbitrary and capricious standard for agency action)
  • Babbitt v. Sweet Home Chapter of Communities for a Greater Oregon, 515 U.S. 687 (1995) (Congress delegated broad discretion to Secretary under ESA)
  • Citizens Against Burlington, Inc. v. Busey, 938 F.2d 190 (D.C. Cir. 1991) ("rule of reason" governs EIS alternatives analysis)
Read the full case

Case Details

Case Name: Union Neighbors United, Inc. v. Sally Jewell
Court Name: Court of Appeals for the D.C. Circuit
Date Published: Aug 5, 2016
Citations: 831 F.3d 564; 82 ERC (BNA) 2089; 2016 U.S. App. LEXIS 14377; 2016 WL 4151237; 15-5147
Docket Number: 15-5147
Court Abbreviation: D.C. Cir.
Log In
    Union Neighbors United, Inc. v. Sally Jewell, 831 F.3d 564