History
  • No items yet
midpage
Twp. of Bordentown v. Fed. Energy Regulatory Comm'n
903 F.3d 234
3rd Cir.
2018
Read the full case

Background

  • Transcontinental (Transco) sought and FERC granted a conditional certificate under the Natural Gas Act (NGA) for the Garden State Expansion Project to increase interstate pipeline capacity serving NJNG; issuance was conditioned on obtaining applicable state permits (including CWA §401 certification).
  • NJDEP granted Freshwater Wetlands and dewatering permits; petitioners (Bordentown, Chesterfield, PPA) requested adjudicatory hearings under New Jersey law within the 30‑day window; NJDEP denied the hearing requests solely on its view that the NGA preempted such state administrative review.
  • Petitioners challenged FERC’s certificate (asserting CWA and NEPA violations, inadequate notice, Green Acres concerns, and lack of demonstrated need) and NJDEP’s denial of hearings; petitions were consolidated for review in the Third Circuit.
  • FERC issued an Environmental Assessment finding no significant environmental impact (EA) subject to mitigation; it segmented review of the Project from PennEast and declined to federalize environmental review of the intrastate SRL.
  • The Third Circuit upheld FERC on the federal claims but held NJDEP erred as a matter of law in concluding the NGA preempted New Jersey’s intra-agency adjudicatory-hearing process; remanded to NJDEP to reconsider hearing requests.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Whether FERC violated CWA §401 by issuing a certificate before state §401 certification FERC’s certificate authorized activities leading to discharge (e.g., condemnation and project commencement) and thus §401 clearance was required first FERC issued a conditional certificate that did not authorize discharge‑creating construction until state permits obtained; conditional issuance complies with CWA Held for FERC: conditional certificate lawful because it did not itself authorize discharge‑creating activity prior to §401 approval
Whether FERC improperly segmented the Project from PennEast under NEPA (connected action analysis) Project lacks independent utility because its capacity was contracted to serve gas expected from PennEast and SRL; must be considered together Project and PennEast have independent utility (different shippers, contracts, and fungible gas pooling); contractual obligations show Project stands on its own Held for FERC: segmentation reasonable; PennEast not a connected action
Whether FERC erred on NEPA cumulative impacts (SRL) and potable-well impacts FERC failed to analyze cumulative impacts of the SRL and did not adequately evaluate/mitigate effects on nearby private wells (did not identify number/location prior to certificate) FERC reasonably limited geographic area of influence, considered SRL cumulatively where appropriate, imposed enforceable mitigation/monitoring conditions for wells; impacts were minor/temporary Held for FERC: cumulative analysis adequate; well impacts adequately considered and mitigated via conditions and monitoring
Whether NJDEP permissibly denied adjudicatory hearings as preempted by NGA §717r(d)(1) NJDEP: NGA vests exclusive, original jurisdiction in federal courts over review of state agency actions made pursuant to federal law, so state adjudicatory process is preempted Petitioners: §717r(d)(1) covers civil actions in courts of law (judicial review), not intra‑agency adjudicatory proceedings; states retain internal administrative review Held for petitioners re NJDEP: NGA does not preempt state administrative hearings; NJDEP’s denial based on misreading of federal law was unreasonable — remand for reconsideration

Key Cases Cited

  • Del. Riverkeeper Network v. Sec’y of Pa. Dep’t of Envtl. Prot., 870 F.3d 171 (3d Cir. 2017) (discusses interplay of NGA and CWA and states’ role)
  • Del. Riverkeeper Network v. Sec’y Pa. Dep’t of Envtl. Prot., 833 F.3d 360 (3d Cir. 2016) (prior Third Circuit exposition of NGA/CWA interaction)
  • Del. Riverkeeper Network v. FERC, 857 F.3d 388 (D.C. Cir. 2017) (upholding conditional certification practice re §401 timing)
  • Sierra Club v. FERC, 867 F.3d 1357 (D.C. Cir. 2017) (NEPA hard-look / informational standards)
  • Myersville Citizens for a Rural Cmty., Inc. v. FERC, 783 F.3d 1301 (D.C. Cir. 2015) (need/market‑support and contract evidence for certificates)
  • Nat’l Comm. for the New River v. FERC, 373 F.3d 1323 (D.C. Cir. 2004) (four‑factor test for federalization of non‑jurisdictional facilities)
  • Kleppe v. Sierra Club, 427 U.S. 390 (U.S. 1976) (NEPA requires agency to take a ‘hard look' but courts defer to agency expertise)
Read the full case

Case Details

Case Name: Twp. of Bordentown v. Fed. Energy Regulatory Comm'n
Court Name: Court of Appeals for the Third Circuit
Date Published: Sep 5, 2018
Citation: 903 F.3d 234
Docket Number: 17-1047; 17-3207
Court Abbreviation: 3rd Cir.