midpage
Sign in to see your projects.
153 F. Supp. 3d 894
E.D. La.
2015
Read the full case

Background

  • Helis sought a Corps §404 permit to construct a well pad and surface facilities to drill a vertical exploratory well (Phase 1) and later a potential horizontal/fracking well (Phase 2); Corps required Helis to limit the permit to Phase 1 and reduce the pad to ~3.13 acres of wetland fill.
  • Corps published public notices (original and revised) and received hundreds of comments; Corps requested supplemental information from Helis after the comment period and Helis submitted ~500 pages of responses on January 2, 2015.
  • Corps’ Memorandum for Record (including EA, 404(b)(1) Guidelines evaluation, Public Interest Review, and Statement of Findings) concluded no significant environmental impact and issued the permit on June 8, 2015.
  • Town of Abita Springs sued under the APA, CWA, and NEPA, arguing (1) inadequate public notice/opportunity to comment on material submitted after the comment period and (2) flawed 404(b)(1) alternatives analysis (failure to consider practicable non-wetland alternatives and to apply the presumption against wetland alternatives).
  • District court considered cross-motions for summary judgment on the administrative record and denied Abita Springs’ motions while granting the Corps’ cross-motion, finding the Corps did not act arbitrarily or violate procedural or substantive rules.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Standing Town says aesthetic, economic, and water-protection injuries (brand, lost visitors/residents, aquifer risk) are concrete and redressable Corps/Helis: injuries speculative, premised on future fracking/third‑party perceptions, and unsupported by admissible evidence Court questioned sufficiency of evidence for standing but reached merits; concluded Corps’ decision would be upheld even assuming standing
Adequacy of public notice / opportunity to comment Corps issued notice on an incomplete application and relied on >500 pages submitted after close of comment; thus public lacked meaningful chance to comment on alternatives and key data Corps: initial public notice and application were sufficient; post-comment applicant responses are properly requested information and Corps has discretion whether to reopen comment period Corps acted within its discretion; public notice was sufficient and Corps reasonably declined to reopen comment period; no prejudicial error shown
Reliance on non-public materials Abita Springs: Corps relied on non-public exhibits, geologic-review input, and Helis’ response not available for comment, so rationale differed from public record Corps: supplemental materials only elaborated previously disclosed matters and were not central, and materials were posted online; Corps’ experts (LGS) participated in review Court found materials did not differ substantially from public information and were not decisive such that lack of supplemental notice prejudiced public participation
Alternatives analysis under 404(b)(1) Corps failed to apply presumption that non-wetland practicable alternatives exist and limited alternatives to nearby wetland sites; did not analyze offsite non-wetland options Corps/Helis: project purpose (gather geologic data on a specific subsurface zone) and overall project purpose are site‑specific; offsite, non-wetland alternatives would not meet project purpose, so presumption was rebutted Court upheld Corps’ definition of overall project purpose and found Corps reasonably concluded Helis rebutted presumption and that considered alternatives were practicable; no arbitrary or capricious action

Key Cases Cited

  • Citizens to Preserve Overton Park v. Volpe, 401 U.S. 402 (1971) (standard for arbitrary and capricious review of agency action)
  • Motor Vehicle Mfrs. Ass'n v. State Farm Mut. Auto. Ins. Co., 463 U.S. 29 (1983) (arbitrary-and-capricious review principles)
  • Friends of the Earth, Inc. v. Laidlaw Envtl. Servs., 528 U.S. 167 (2000) (standing standards for environmental plaintiffs)
  • Auer v. Robbins, 519 U.S. 452 (1997) (deference to agency interpretations of its own regulations)
  • Clapper v. Amnesty Int'l USA, 568 U.S. 398 (2013) (requirement that threatened injury be certainly impending for Article III standing)
  • Sierra Club v. U.S. Army Corps of Eng'rs, 450 F. Supp. 2d 503 (D.N.J. 2006) (Corps’ discretion not to reopen comment period on applicant responses)
  • Ohio Valley Envtl. Coal. v. U.S. Army Corps of Eng'rs, 674 F. Supp. 2d 783 (S.D.W. Va. 2009) (public notice insufficient where pivotal data withheld)
  • Van Antwerp v. U.S. Army Corps of Eng'rs, [citation="362 F. App'x 100"] (11th Cir. 2010) (limits on defining project purpose to avoid evading wetlands‑protection presumption)
Read the full case

Case Details

Case Name: Town of Abita Springs v. U.S. Army Corps of Engineers
Court Name: District Court, E.D. Louisiana
Date Published: Dec 23, 2015
Citations: 153 F. Supp. 3d 894; 82 ERC (BNA) 1055; 2015 U.S. Dist. LEXIS 171767; 2015 WL 9315745; CIVIL ACTION NO: 15-451
Docket Number: CIVIL ACTION NO: 15-451
Court Abbreviation: E.D. La.
Log In