976 F.3d 832
9th Cir.2020Background
- In 2005–09 the U.S. and Japan agreed to realign forces by relocating roughly 8,000 Marines from Okinawa to Guam; Japan committed substantial funding. The relocation was implemented through a series of agency decisions memorialized in Records of Decision (2010 Relocation ROD; 2015 Relocation SEIS ROD).
- The Navy’s Joint Guam Program Office (JGPO) prepared a Relocation EIS (2010) addressing moving Marines to Guam and certain Tinian/CNMI training facilities; the CJMT Draft EIS separately proposed expanded ranges on Tinian and Pagan.
- Tinian Women Association (TWA) sued to set aside the Relocation EIS/SEIS under NEPA and the APA, alleging (1) the relocation and CNMI training actions were “connected” and should have been covered in a single EIS or their cumulative impacts considered together, and (2) the Navy failed to consider stationing alternatives beyond Guam and the CNMI.
- The district court granted summary judgment to the Navy on the procedural NEPA claim and dismissed the alternatives claim (and found a third claim waived). TWA appealed to the Ninth Circuit.
- The Ninth Circuit affirmed: it held the relocation and CNMI training were not "connected" for NEPA purposes and cumulative impacts could be deferred to the forthcoming CJMT EIS; the alternatives claim was dismissed for lack of standing (non-redressable because relief would require altering the U.S.–Japan agreement); a supplemental-EIS claim was waived for late pleading.
Issues
| Issue | Plaintiff's Argument | Defendant's Argument | Held |
|---|---|---|---|
| Whether the Guam relocation and CNMI training are "connected actions" requiring a single EIS | The relocation and proposed CNMI ranges are part of one larger project and must be evaluated together | The actions have independent utility and purposes; separate EISs are permissible | Not connected; separate analyses allowed (agency action upheld) |
| Whether Relocation EIS must include cumulative impacts of CJMT proposals | Cumulative impacts of CNMI ranges foreseeably magnify relocation effects and must be addressed now | Navy issued a notice and will consider cumulative effects in the CJMT EIS; deferral is appropriate | Deferral acceptable because Navy committed to analyze impacts in future EIS |
| Whether court can order consideration of alternatives beyond Guam/CNMI | Navy improperly limited stationing alternatives; must consider locations outside Guam/CNMI | Treaty/Agreement with Japan largely fixes relocation to Guam, constraining Navy's ability to choose other locations | Dismissed for lack of standing (not redressable): remedy would require rescinding/modifying the U.S.–Japan agreement |
| Whether TWA preserved a claim that Navy failed to supplement the Relocation EIS after changed circumstances | TWA later argued changes warranted supplementation of the Relocation EIS | Navy argued the claim was not pleaded and was raised too late | Waived: district court did not abuse discretion denying leave to amend; claim raised first at summary judgment |
Key Cases Cited
- Lands Council v. McNair, 629 F.3d 1070 (9th Cir. 2010) (standard for APA arbitrary-and-capricious review)
- Lujan v. Defenders of Wildlife, 504 U.S. 555 (1992) (Article III standing framework)
- Great Basin Mine Watch v. Hankins, 456 F.3d 955 (9th Cir. 2006) (independent utility defeats "connected actions" theory)
- Native Ecosystems Council v. Dombeck, 304 F.3d 886 (9th Cir. 2002) (prohibition on segmenting projects to avoid NEPA)
- Northern Alaska Envtl. Ctr. v. Kempthorne, 457 F.3d 969 (9th Cir. 2006) (permitting deferral of some cumulative-impact analysis to future EIS when agency commits to do so)
- Salmon Spawning & Recovery Alliance v. Gutierrez, 545 F.3d 1220 (9th Cir. 2008) (procedural standing and limits on redressability when remedy would upend treaty-level decisions)
- Center for Environmental Law & Policy v. U.S. Bureau of Reclamation, 655 F.3d 1000 (9th Cir. 2011) (agency promise to analyze future impacts can bind agency and affect judicial review)
- Robertson v. Methow Valley Citizens Council, 490 U.S. 332 (1989) (NEPA protects cognizable environmental interests and requires consideration of alternatives)
- Navajo Nation v. U.S. Forest Service, 535 F.3d 1058 (9th Cir. 2008) (claim‑raising requirements; claims must be adequately pleaded)
- William Inglis & Sons Baking Co. v. ITT Continental Baking Co., 668 F.2d 1014 (9th Cir. 1981) (notice/prejudice factors in denying late amendments)
