History
  • No items yet
midpage
Tindall Corp. v. Mondelez International, Inc.
248 F. Supp. 3d 895
N.D. Ill.
2017
Read the full case

Background

  • Mondelez planned a $23M+ precast concrete package for “Project Arthur” and retained Stellar as construction manager; Stellar recommended Tindall for precast work.
  • Tindall submitted proposals and attended meetings; on March 20, 2013 Tindall’s VP Palumbo met Mondelez procurement lead Nicot; parties dispute whether an oral contract was formed at that meeting.
  • On March 21, Palumbo emailed a detailed “recap” listing 22 Items and 5 Next Steps (including execution of a written contract, a $3M down payment contingent on execution, and a target to finalize terms by April 29); Nicot replied “I am ok with what you have detailed below with the following comments.”
  • Subsequent conduct: some engineering meetings and shop drawings took place, Stellar drafted an engineering agreement (which Tindall refused to sign), Mondelez did not provide the $3M down payment, land for the project was not purchased until July, and no precast was manufactured.
  • In July 2013 Mondelez chose cast-in-place concrete and engaged a Mexican supplier; Tindall sued for breach of contract and promissory estoppel. The district court granted Mondelez summary judgment.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Whether a binding oral contract was formed at the March 20 meeting Palumbo says Nicot accepted terms orally and directed Tindall to reserve capacity; the March 21 email memorializes agreed terms Mondelez says discussions were preliminary, parties intended a written contract, and Nicot’s statements were not an acceptance No; as a matter of law the parties intended a written contract and no enforceable oral agreement existed
Whether the March 21 email exchange formed a binding contract The Palumbo Email (offer) and Nicot Response (acceptance) established mutual assent to the listed terms Mondelez contends the email was a recap with open, indefinite terms and conditions precedent to a written contract No; emails were too indefinite, left material terms open, and Nicot’s response was not an objective acceptance
Whether there was an enforceable engineering services contract Tindall claims Nicot agreed to engineering services and price at March 20 meeting Mondelez says Stellar would contract with Tindall for engineering and Tindall refused Stellar’s draft agreement No; Stellar’s draft was rejected by Tindall and no engineering contract was formed
Whether promissory estoppel supplies relief absent a contract Tindall asserts Mondelez made unambiguous promises and Tindall relied to its detriment (reserved plant capacity, lost other work) Mondelez argues statements were not unambiguous promises and promissory estoppel cannot replace a missing contract where contract elements were alleged No; promises were ambiguous/not binding and estoppel fails where contract claim fails

Key Cases Cited

  • Matsushita Elec. Indus. Co. v. Zenith Radio Corp., 475 U.S. 574 (summary judgment standard inferences)
  • Anderson v. Liberty Lobby, Inc., 477 U.S. 242 (genuine issue for trial standard)
  • Celotex Corp. v. Catrett, 477 U.S. 317 (movant’s burden on summary judgment)
  • Quake Constr., Inc. v. Am. Airlines, Inc., 565 N.E.2d 990 (Ill. 1990) (reduction-to-writing intent bars oral contract)
  • Ceres Illinois, Inc. v. Illinois Scrap Processing, Inc., 500 N.E.2d 1 (Ill. 1986) (post-agreement conduct informs intent to be bound)
  • Ocean Atl. Dev. Corp. v. Aurora Christian Sch., Inc., 322 F.3d 983 (7th Cir. 2003) (staged agreement and writings do not automatically negate a binding preliminary agreement)
  • Dumas v. Infinity Broadcasting Corp., 416 F.3d 671 (7th Cir. 2005) (promissory estoppel cannot circumvent contract law when contract claim fails)
Read the full case

Case Details

Case Name: Tindall Corp. v. Mondelez International, Inc.
Court Name: District Court, N.D. Illinois
Date Published: Mar 29, 2017
Citation: 248 F. Supp. 3d 895
Docket Number: No. 14 C 05196
Court Abbreviation: N.D. Ill.