History
  • No items yet
midpage
Thomas J. Davis, Inc.
ASBCA No. 62634
| A.S.B.C.A. | Jul 1, 2021
Read the full case

Background

  • Contract awarded April 10, 2012 to Thomas J. Davis, Inc. (TJD) to design an aircraft corrosion control facility at Osan AB, Korea, including a Restoration Bay intended for sanding/painting aircraft.
  • Contract required iterative design submittals (10%, 30%, 90%, 95%, 100%) and incorporated FAR clauses making the A‑E contractor responsible for professional quality and technical accuracy.
  • TJD’s 30% design (June 2012) showed painting facilities; by August 2012 TJD changed its proposed exhaust/filtration approach (from roof-mounted three‑stage filters to floor‑mounted dust collectors) and provided product brochures.
  • The government’s administrative reviewers did not, according to government declarations, recognize that the revised filtration system precluded painting; Bio‑Environmental rejected the ventilation system on Sept. 28, 2017 after airflow tests.
  • Contracting Officer issued a claim on Nov. 20, 2019 seeking recovery for alleged defective design; TJD moved for summary judgment arguing the claim was time‑barred under the Contract Disputes Act because it accrued more than six years earlier.
  • The Board denied TJD’s summary‑judgment motion, finding genuine disputes of material fact about when the government knew or should have known of the alleged design defects.

Issues

Issue TJD's Argument Government's Argument Held
Whether the government’s claim is time‑barred under the CDA (6‑year accrual rule) Accrual occurred in 2012 (or by Nov. 19, 2013) because TJD’s submittals and August 2012 filter info should have put the government on notice Government did not know and could not have known of the defect until 2017 (airflow tests/Bio‑Environmental rejection); CORs were not experts and relied on TJD as the specialist Denied summary judgment—triable factual dispute whether claim accrued before Nov. 19, 2013
Whether the government directed TJD to remove painting capability from the Restoration Bay TJD claimed government personnel instructed removal between 30% and 90% submittals Government produced affidavits and meeting minutes showing the painting requirement remained and no such direction was given Board found TJD’s claim unsupported and contradicted; no evidence government directed removal
Whether TJD’s 2012 plans and filter brochures made the defect objectively obvious to government reviewers The brochure/spec submissions should have alerted any reviewer that the dust‑collector approach was incompatible with painting Plans and attachments did not plainly show inability to support painting; reviewers lacked filtration expertise and reasonably relied on TJD’s technical responsibility Triable factual dispute remains; cannot resolve as a matter of law on summary judgment
Whether subsequent actions (e.g., 2016 contract modification) reset accrual or justify later accrual date (TJD) argues accrual earlier; (Gov’t) suggested later events could be relevant Government proposed 2016 modification might mark accrual; Board saw no basis to retroactively change accrual date if defect was recognizable earlier Board rejected using the 2016 modification to retroactively alter the accrual analysis for statute‑of‑limitations purposes

Key Cases Cited

  • Celotex Corp. v. Catrett, 477 U.S. 317 (1986) (movant bears burden to show absence of genuine issue of material fact on summary judgment)
  • Anderson v. Liberty Lobby, 477 U.S. 242 (1986) (non‑movant must present specific facts showing a genuine factual dispute)
  • First Nat’l Bank of Ariz. v. Cities Serv. Co., 391 U.S. 253 (1968) (summary judgment standards and requirement to show genuine issue)
  • United States v. Diebold, Inc., 369 U.S. 654 (1962) (significant doubt on factual issues resolved for non‑movant)
  • Mingus Constructors v. United States, 812 F.2d 1387 (Fed. Cir. 1987) (applying summary judgment standards in government contract disputes)
  • Sikorsky Aircraft Corp. v. United States, 773 F.3d 1315 (Fed. Cir. 2014) (CDA claim accrual and final decision timing)
  • Kellogg Brown & Root Servs., Inc. v. Murphy, 823 F.3d 622 (Fed. Cir. 2016) (accrual determined by FAR, contract terms, and case facts)
  • Electric Boat Corp. v. Sec’y of the Navy, 958 F.3d 1372 (Fed. Cir. 2020) (accrual analysis under FAR 33.201)
Read the full case

Case Details

Case Name: Thomas J. Davis, Inc.
Court Name: Armed Services Board of Contract Appeals
Date Published: Jul 1, 2021
Docket Number: ASBCA No. 62634
Court Abbreviation: A.S.B.C.A.