History
  • No items yet
midpage
513 S.W.3d 543
Tex. App.
2016
Read the full case

Background

  • In 2004 Zachry contracted with the Port of Houston to build a 1,660-foot wharf using a soil-freezing ("in the dry") method; the Port selected Zachry in part for the environmental benefits of that method.
  • Change Order 4 (Sept. 27, 2005) expanded the wharf by 332 feet; Zachry proposed a perpendicular frozen cutoff wall to allow phased "in the dry" work so a crane shipment could be accommodated by Milestone A.
  • The Port returned Zachry’s frozen-cutoff-wall submission with a "revise and resubmit" (R&R) response, expressing concerns about effects on existing shafts; Zachry ultimately abandoned the cutoff wall and switched to "in the wet."
  • Zachry sued for breach, seeking as damages the increased costs of working "in the wet" plus withheld liquidated damages; the jury found breach and awarded roughly $19.99 million (including liquidated damages less an offset for defective fenders).
  • On initial appeal this court rendered judgment for the Port; the Texas Supreme Court reversed on immunity, enforceability of the no-damages-for-delay clause, release of liquidated damages, and attorney-fee issues, and remanded for further consideration of remaining Port arguments.
  • On remand the Fourteenth Court of Appeals considered Port challenges to liability, damages/causation, condition-precedent notice provisions, exclusion of Port offset evidence, jury instructions (fraud and apparent authority), pass-through recovery, and attorney-fees; the court affirmed the judgment for Zachry.

Issues

Issue Plaintiff's Argument (Zachry) Defendant's Argument (Port) Held
Whether the Port breached by issuing R&R that controlled Zachry’s means/methods (§5.10 vs §5.22) §5.10 made means/methods Zachry’s responsibility; frozen cutoff wall was Zachry’s chosen means and not subject to §5.22 revise/resubmit §5.22 allowed Port to require revise/resubmit of submittals (including safety plans) and thus to reject the frozen cutoff wall Jury finding of breach under §5.10 supported; evidence legally sufficient — affirm
Whether Zachry’s damages model and expert (Draper) were legally sufficient Damages measured as difference between actual "in the wet" costs and hypothetical "in the dry" costs; methodology tied to contemporaneous plans and schedules Model rested on incorrect factual assumptions (pipe removal, sheet-pile timing) making expert opinion unreliable Model admissible; jury discounted amounts; evidence legally sufficient — affirm
Whether expert testimony was required to prove causation between Port’s breach and Zachry’s damages Non-expert testimony (project managers, geotechnical evidence) established Port-caused delay and foreseeability of resulting costs Port contended expert proof was necessary (citing non-contract precedents) No blanket rule requiring expert in breach-of-contract causation; evidence legally sufficient — affirm
Whether procedural notice provisions (§5.41/5.42) were conditions precedent barring Zachry’s claim Sections govern contractual change procedures, not breaches of owner control; also 5.42 would be a <90‑day pre-suit notice and conflict with Tex. Civ. Prac. & Rem. Code §16.071; owner who breaches cannot invoke procedural protections Port argued failure to comply with notice/change procedures bars R&R claim Court held §§5.41/5.42 inapplicable as pleaded and, in any event, Port’s breach prevents reliance on those procedural bars; §16.071 issues noted — affirm
Whether trial court abused discretion excluding Port’s late-disclosed offset evidence Zachry argued Port failed to timely disclose offset theory and amounts; trial court excluded most categories as discovery sanction and under Rule 403 Port argued disclosures sufficiently put Zachry on notice and later evidence was admissible (also contended Zachry opened the door) Exclusion not an abuse: Port failed to show good cause; limited exception for items with timely disclosure; limited opening of door did not overcome prejudice/403 concerns — affirm
Whether fraud instruction in no-damages-for-delay exception improperly allowed reckless conduct to qualify as fraud Zachry relied on Supreme Court’s prior holding approving the charge formulation Port argued the fraud definition improperly allowed reckless misrepresentations to satisfy exception Law-of-the-case: Supreme Court already approved the charge language; no error — affirm
Whether apparent authority instruction was improper (CH2M Hill) Zachry pleaded and produced evidence that CH2M Hill acted as Port’s representative and that Zachry relied on CH2M communications Port argued Zachry failed to plead apparent authority and CH2M lacked power to issue R&R Pleadings adequate (no special exception) and evidence supported submission; instruction proper — affirm
Whether Zachry could recover subcontractor (pass-through) costs incurred after corporate reorganization Zachry relied on Management Services Agreement and Pass-Through Agreement showing Zachry’s continuing liability to subcontractor and obligation to remit recoveries Port argued pass-through barred because subcontractor employed after breach and immunity concerns Interstate pass-through doctrine applies; evidence Zachry remained liable to Sub; governmental immunity did not bar pass-through here — affirm

Key Cases Cited

  • City of Keller v. Wilson, 168 S.W.3d 802 (Tex. 2005) (legal-sufficiency standard and viewing evidence in light most favorable to verdict)
  • Zachry Constr. Corp. v. Port of Houston Auth. of Harris Cty., 449 S.W.3d 98 (Tex. 2014) (Supreme Court reversed earlier appellate judgment; held LGCCA waived immunity and addressed enforceability of no‑damages‑for‑delay exception)
  • Interstate Contracting Corp. v. City of Dallas, 135 S.W.3d 605 (Tex. 2004) (recognizing and authorizing contractor pass‑through claims)
  • Seagull Energy E & P, Inc. v. Eland Energy, Inc., 207 S.W.3d 342 (Tex. 2006) (contract interpretation—ascertaining parties’ intent)
  • Gen. Elec. Co. v. Moritz, 257 S.W.3d 211 (Tex. 2008) (principle that owner who retains right to control contractor’s work may be liable for negligent exercise of that right)
  • J.M. Davidson, Inc. v. Webster, 128 S.W.3d 223 (Tex. 2003) (contract construction — harmonize provisions so none are rendered meaningless)
Read the full case

Case Details

Case Name: the Port of Houston Authority of Harris County, Texas v. Zachry Construction Corporation
Court Name: Court of Appeals of Texas
Date Published: Dec 15, 2016
Citations: 513 S.W.3d 543; 2016 Tex. App. LEXIS 13306; 2016 WL 7323304; NO. 14-10-00708-CV
Docket Number: NO. 14-10-00708-CV
Court Abbreviation: Tex. App.
Log In
    the Port of Houston Authority of Harris County, Texas v. Zachry Construction Corporation, 513 S.W.3d 543