ZACHRY CONSTRUCTION CORPORATION, Petitioner, v. PORT OF HOUSTON AUTHORITY OF HARRIS COUNTY, Texas, Respondent.
No. 12-0772.
Supreme Court of Texas.
Argued Nov. 6, 2013. Decided Aug. 29, 2014.
Rehearing Denied Dec. 19, 2014.
449 S.W.3d 98
Joe F. Canterbury Jr., Canterbury Stuber Elder Gooch, Surratt, Shapiro & Stein P.C., Dallas, TX, for Amicus Curiae, Associated General Contractors of Texas, Inc.
James Corbin Van Arsdale, Vice President & General Counsel, Austin, TX, for Amicus Curiae, Associated General Contractors-Texas Building Branch.
Robert H. Fugate, Assistant City Attorney, Arlington City Attorney‘s Office, Arlington, TX, for Amicus Curiae, City of Arlington, Texas.
Charles Steven Estee, Office of the Dallas City Attorney, Dallas, TX, Amicus Curiae, City of Dallas, Texas.
Christopher Bedford Mosley, Sr. Assistant City Attorney, Fort Worth, for Amicus Curiae, City of Fort Worth, Texas.
Malinda York Crouch, Sr. Assistant City Attorney, Houston, TX, for Amicus Curiae, City of Houston.
Robert Caput, DFW Airport, TX, for Amicus Curiae, Dallas/Fort Worth International Airport Board.
Vincent L. Marable III, Paul Webb, P.C., Wharton, TX, for Amicus Curiae, Electrical Contractors Association, National Systems Contractors Association.
Bruce S. Powers, Assistant County Attorney, Vincent Reed Ryan Jr., Houston, TX, for Amicus Curiae, Harris County, Texas.
Hugh Rice Kelly, Austin, TX, for Amicus Curiae, Texans for Lawsuit Reform.
Jose E. De La Fuente, Lloyd Gosselink Rochelle & Townsend, P.C., Austin, TX, for Amicus Curiae, Texas Aggregates and Concrete Association.
George S. Christian, Texas Civil Justice League, Austin, TX, for Amicus Curiae, Texas Civil Justice League.
John B. Dahill, Austin, TX, for Amicus Curiae, Texas Conference of Urban Counties.
Heather Mahurin, Austin, TX, for Amicus Curiae, Texas Municipal League.
Richard Gary Thomas, Thomas Feldman & Wilshusen, LLP, Dallas, TX, for Amicus Curiae, The American Subcontractors Association, Inc.
David A. Escamilla, Sherine Elizabeth Thomas, Austin, TX, for Amicus Curiae, Travis County, Texas.
Michael Keeley, Dallas, TX, for Amicus Curiae, Zurich Surety.
David E. Keltner, Marianne M. Auld, Kelly Hart & Hallman LLP, Fort Worth, TX, Catherine B. Smith, Michael A. Heidler, Marie R. Yeates, William D. Sims Jr., Vinson & Elkins LLP, David Hurst Brown, Brown & Kornegay, LLP, Karen Tucker White, Karen T. White, P.C., Lawrence J. Fossi, Fossi & Jewell LLP, Houston, TX, for Respondent Port of Houston Authority of Harris County, Texas.
Chief Justice HECHT delivered the opinion of the Court, in which Justice GREEN, Justice GUZMAN, Justice DEVINE, and Justice BROWN joined.
The common law permits a contractor to recover damages for construction delays caused by the owner, but the parties are free to contract differently. A contractor may agree to excuse the owner from liability for delay damages, even when the owner is at fault. The contractor thereby assumes the risk of delay from, say, an owner‘s change of plans, even if the owner is negligent. But can a no-damages-for-delay provision shield the owner from liability for deliberately and wrongfully interfering with the contractor‘s work? Before this case, a majority of American jurisdictions—including Texas courts of appeals, courts in all but one jurisdiction to consider the issue, and five state legislatures—had answered no. We agree with this overwhelming view and also conclude that the answer is the same if the owner is a local governmental entity for which immunity from suit is waived by the Local Government Contract Claims Act.1
Contractors are usually paid as work progresses and, in exchange for payment, must waive liens and claims related to the work paid for. But does such a general waiver release a claim the contractor has already asserted? Not, we think, unless the claim is specifically mentioned or the intent to do so is clear.
Our conclusions require us to reverse the judgment of the court of appeals2 and remand the case to that court for further proceedings.
I3
Petitioner, Zachry Construction Corporation, contracted to construct a wharf on the Bayport Ship Channel for respondent, the Port of Houston Authority of Harris County, Texas. The wharf would be a concrete deck supported by piers, extending out over the water. It would be used for loading and unloading ships carrying containerized goods and would be long enough—1,660 feet—for two ships to dock stern to bow. It would be built in five sections, each 135 feet wide and 332 feet long. The channel was to be dredged to a
The contract made Zachry an independent contractor in sole charge of choosing the manner in which the work would be conducted. Specifically, Section 5.10 of the contract provided:
The Port Authority shall not have the right to control the manner in which or prescribe the method by which the Contractor [Zachry] performs the Work. As an independent Contractor, the Contractor shall be solely responsible for supervision of and performance of the Work and shall prosecute the Work at such time and seasons, in such order or precedence, and in such manner, using such methods as Contractor shall choose....
The provision benefitted the Port, insulating it from the liability to which it would be exposed were it exercising control over Zachry‘s work.4 Still, the Port was fully engaged in reviewing Zachry‘s plans and overseeing construction.
Zachry‘s plan was innovative. It would use soil dredged from the channel to construct an 8-foot-wide earthen berm starting from the shore at either end of the worksite, extending out toward the center of the channel, then running parallel to the shore, forming a long, flat U-shaped wall in the channel around the construction area. Zachry would install a refrigerated pipe system in the wall and down into the channel floor that would carry supercooled brine, freezing the wall to make it impenetrable to the water in the channel. Zachry would then remove the water from the area between the wall and the shore. In this way, Zachry could work “in the dry“, using bulldozers and other land equipment for the excavation and revetment work. Another advantage to this freeze-wall approach was that it would lower diesel emissions and require fewer nitrous oxide credits under environmental laws, giving the Port more flexibility in other construction projects. Zachry believed this approach would make the work less expensive and allow it to be completed more quickly.
And time was of the essence to the Port. Work began in June 2004 and was to be completed in two years. But two sections of the wharf had to be completed within 20 months—by February 2006—so that a ship from China could dock, delivering cranes to be used on the wharf. Zachry agreed to pay $20,000 per day as liquidated damages for missing the deadlines.
Nine months into the project, the Port realized that it would need two 1,000-foot berths to accommodate the ships it ultimately expected to service. A sixth 332-foot section would have to be added to the wharf. As a practical matter, only Zachry could perform the additional work, and Zachry and the Port began discussions on a change order. To complete the two sections of the wharf needed by February 2006, and to continue to work “in the dry“, Zachry proposed to build another freeze-wall—a cutoff wall—through the middle of the project, perpendicular to the shoreline out to the existing wall, splitting the project into two parts. Zachry would finish the west end where the ship from China would dock, remove the wall barricading water from that area, then continue working on the east end “in the dry“.
Two weeks later, the Port ordered Zachry to revise and resubmit its plans without the cutoff wall. The practical effect of the Port‘s order was to refuse to allow construction of the cutoff wall. Zachry protested that, under Section 5.10 of the contract, the Port had no right to determine the method and manner of the work, but the Port would not budge. Zachry‘s only option was to finish the westmost sections in time for the ship from China to dock, then remove the wall altogether and continue to work “in the wet“, which would delay completion of the project and increase its cost.
In negotiating Change Order 4, the Port had promised not to impose liquidated damages for delay as long as the ship from China could dock when it arrived, although the Port had refused to put its promise in writing. Nevertheless, after the ship successfully docked, the Port began withholding liquidated damages from Zachry‘s payments. Eventually the Port desisted, but not until it had withheld $2.36 million. Zachry completed the project in January 2009, more than two-and-one-half years after the contract deadline.
In November 2006, several weeks after the Port refused to allow construction of the cutoff wall, Zachry sued. Zachry eventually claimed some $30 million in damages from delays caused by the Port. The Port countered that Section 5.07 of the contract precluded delay damages. That provision states:
[Zachry] shall receive no financial compensation for delay or hindrance to the Work. In no event shall the Port Authority be liable to [Zachry] or any Subcontractor or Supplier, any other person or any surety for or any employee or agent of any of them, for any damages arising out of or associated with any delay or hindrance to the Work, regardless of the source of the delay or hindrance, including events of Force Majeure, AND EVEN IF SUCH DELAY OR HINDRANCE RESULTS FROM, ARISES OUT OF OR IS DUE, IN WHOLE OR IN PART, TO THE NEGLIGENCE, BREACH OF CONTRACT OR OTHER FAULT OF THE PORT AUTHORITY. [Zachry‘s] sole remedy in any such case shall be an extension of time.
Zachry argued, and the trial court ultimately agreed, that such a no-delay-damages provision could not be enforced if the Port‘s intentional misconduct caused the delay.
Zachry also sought recovery of the $2.36 million in delay damages withheld by the Port. The trial court held that the contract‘s liquidated damages provisions were invalid, and the Port has not challenged that ruling on appeal. But the Port responded that Zachry‘s claim to the liquidated damages was precluded by the releases it executed to obtain the periodic payments from which liquidated damages were withheld. The releases shared language stating:
[Zachry] hereby acknowledges and certifies that [the Port] has made partial payment to [Zachry] on all sums owing on Payment Estimate Number [—] and that it has no further claims against [the Port] for the portion of the Work completed and listed on the Schedule of Costs in Payment Estimate Number [—].5
The trial court concluded that this language did not unambiguously release Zachry‘s claim to the liquidated damages withheld and asked the jury to decide what effect it had.
After a three-month trial, the jury found that the Port breached the contract by rejecting Zachry‘s cutoff wall design, causing Zachry to incur $18,602,697 in delay damages.6 The jury also found that the delay “was the result of the Port‘s ... arbitrary and capricious conduct, active interference, bad faith and/or fraud.”7 The jury failed to find that Zachry had released its claim to the $2.36 million liquidated damages the Port withheld, but found that the Port was entitled to offset $970,000 for defective wharf fenders. The trial court rendered judgment for Zachry on the verdict.
Both the Port and Zachry appealed. The court of appeals held that the no-
We granted Zachry‘s petition for review.12
II
Zachry argues that the no-damages-for-delay provision of the contract (Section 5.07) is invalid. The Port disagrees but also argues that even if the provision has no effect, the contract is otherwise silent on the recovery of delay damages, and the Local Government Contract Claims Act (“the Act“)13 does not waive governmental immunity from suit for any recovery a contract does not itself provide for. The court of appeals concluded that the no-damages-for-delay provision is enforceable and thus found it unnecessary to reach the immunity issue.14 That approach was impermissible. Immunity “implicates a court‘s subject-matter jurisdiction over pending claims“,15 and “[w]ithout jurisdiction the court cannot proceed at all in any cause; it may not assume jurisdiction for the purpose of deciding the merits of the case.”16 We must consider first whether the Act waives a local governmental entity‘s immunity from suit on a contract claim for delay damages the contract does not call for.
The issue has two parts. One is whether the Act‘s limitations on recovery help define and restrict the scope of the waiver of immunity. If not, those limitations have no role in determining a court‘s jurisdiction over a claim.17 If so, as we conclude, the second part of the immunity issue is whether the delay damages Zachry seeks are permitted by the Act, so that the
A
The Act waives immunity from contract suits for local governmental entities, such as the Port.18 Section 271.152 of the Act states:
A local governmental entity that is authorized by statute or the constitution to enter into a contract and that enters into a contract subject to this subchapter waives sovereign immunity to suit for the purpose of adjudicating a claim for breach of the contract, subject to the terms and conditions of this subchapter.19
A “contract subject to this subchapter” includes “a written contract stating the essential terms of the agreement for providing goods or services to the local governmental entity that is properly executed on behalf of the local governmental entity“.20 The contract between the Port and Zachry qualifies.
The “terms and condition of this subchapter” referred to in Section 271.152 are found in the Act‘s other nine sections. Section 271.153 states:
(a) Except as provided by Subsection (c), the total amount of money awarded in an adjudication brought against a local governmental entity for breach of a contract subject to this subchapter is limited to the following:
(1) the balance due and owed by the local governmental entity under the contract as it may have been amended, including any amount owed as compensation for the increased cost to perform the work as a direct result of owner-caused delays or acceleration;
(2) the amount owed for change orders or additional work the contractor is directed to perform by a local governmental entity in connection with the contract;
(3) reasonable and necessary attorney‘s fees that are equitable and just; and
(4) interest as allowed by law, including interest as calculated under
Chapter 2251, Government Code .(b) Damages awarded in an adjudication brought against a local governmental entity arising under a contract subject to this subchapter may not include:
(1) consequential damages, except as expressly allowed under Subsection (a)(1);
(2) exemplary damages; or
(3) damages for unabsorbed home office overhead.
(c) Actual damages, specific performance, or injunctive relief may be granted in an adjudication brought against a local governmental entity for breach of a contract described by Section 271.151(2)(B).21
Section 271.154 provides for enforcement of contractual adjudication procedures.22 Section 271.155 preserves defenses other than immunity.23 Section 271.156 limits the Act‘s waiver of immunity to suits filed in state court.24 Section 271.157 makes clear that the waiver of immunity does not extend to tort claims.25 Section 271.158 provides that the Act only waives immunity and does not grant it.26 And Section 271.160 precludes a finding of joint enterprise.27
Whether the various provisions of the Act define the scope of the waiver of immunity depends on the statutory text. As a rule, a modifier like the last “subject to” phrase in Section 271.152 applies to the nearest reasonable referent.28 The candidates are “contract“, “claim“, “adjudicating“, and “waives“. We do not think the phrase modifies “contract“. Earlier in the sentence, the Act is made applicable to any “contract subject to this subchapter“, and it would be needlessly redundant to reiterate a few words later that the contract is subject to the Act‘s terms and conditions.29 Nor do we think the phrase modifies “claim“. Section 271.158,30 for example, provides only that the Act does not grant immunity and says nothing about the nature of the claim for which immunity is waived. And we do not think the “subject to” phrase modifies “adjudicating“. If it did, only the adjudicatory process would be governed by the Act‘s terms and conditions. This reading might make sense for the recovery limits and preservation of procedures and defenses provided in Sections 271.153,31 271.154,32 and Section 271.155,33 respectively. Those three sections relate to the litigation and adjudica-
The “subject to the terms and conditions” phrase in Section 271.152 incorporates the other provisions of the Act to define the scope of its waiver of immunity. The waiver does not extend to tort suits, suits in federal court, or allow recovery beyond that permitted by Section 271.153. But Section 271.152, as qualified by this “subject to” phrase also does not preclude other defenses or other contractual procedures, or confer immunity or suggest joint enterprise. The “subject to” phrase most reasonably refers to “waives“, thus making the provisions of the Act limitations on the waiver of immunity. Section 271.152 must be read as follows: “A local governmental entity ... waives sovereign immunity to suit ... subject to the terms and conditions” of the Act.
We reached this result in Tooke v. City of Mexia38 without the analysis just laid out because it seemed obvious. The Tookes sued the City of Mexia for breach of contract, “asserting that they had relied on a three-year term in purchasing equip-
ment. They claimed unspecified damages, but requested jury findings only on lost profits and attorney fees“.39 They did not claim that the City failed to pay for work actually performed; rather, they sought recovery only for lost profits they would have made had the contract continued—“consequential damages excluded from recovery under [Section 271.153].”40 Even though the Tookes’ contract claim fell within Section 271.152,41 we concluded—because they did not “claim damages within [Section 271.153‘s] limitations“—that “the City‘s immunity from suit on the Tookes’ claim has not been waived.”42 This was true even though the Tookes might have proved that the City breached the contract.
The text of Section 271.152 and our decision in Tooke ought to have settled the matter, but courts of appeals have read our decision in Kirby Lake Development, Ltd. v. Clear Lake City Water Authority43 to retreat from Tooke. There, developers sued an area water authority for reimbursement of part of their costs of building water and sewer facilities, which the authority had agreed to pay out of voter-approved bond funds.44 No bonds had been approved, but the developers claimed that the water authority had breached the contract by campaigning against approval, thereby forestalling its reimbursement obligation.45 The water authority argued in
sis without acknowledging the conflict with our opinion in Tooke.50
The Austin Court of Appeals has laid out the case for confining the scope of the Act‘s waiver to Section 271.152 in its opinion in City of San Antonio v. Lower Colorado River Authority.51 LCRA reasons that immunity from suit and immunity from liability are distinct concepts, that the former may be waived for a claim on which a governmental entity is not liable, and that the Act serves this very purpose.52 We agree with all but the conclusion. As we have explained, Section 271.153‘s limitations on recovery are incorporated into Section 271.152 by its last “subject to” clause and are thereby conditions on the Act‘s waiver of immunity. We disagree with LCRA that this reading of the Act makes its waiver of immunity dependent on ultimate liability. The Act waives immunity for contract claims that meet certain conditions: the existence of a specific type of contract, a demand for certain kinds of damages, a state forum, etc. The waiver does not depend on the outcome, though it does require a showing of a substantial claim that meets the Act‘s conditions. LCRA argues that this view of the Act makes Section 271.153 a grant of immunity, a construction precluded by
By “substantial” claim we mean, as we held in Texas Department of Parks and Wildlife v. Miranda, that the claimant must plead facts with some evidentiary support that constitute a claim for which immunity is waived, not that the claimant will prevail.53 In Tooke, the only damages claimed were precluded by Section 271.153, and therefore immunity was not waived. Had the Tookes claimed payment for work done, immunity would have been waived, regardless of whether the Tookes
could prevail, as long as the Tookes had some supporting evidence.
We conclude that the Act does not waive immunity from suit on a claim for damages not recoverable under Section 271.153.54
B
Under Section 271.153(a)(1), the “amount of money awarded ... for breach of contract” includes “the balance due and owed ... under the contract” as amended, “including any amount owed as compensation for the increased cost to perform the work as a direct result of owner-caused delays“.55 Section 271.153(b) precludes recovery of consequential damages, “except as expressly allowed under Subsection
No such requirement can be found in the statute‘s text. The phrase, “balance due and owed/owing“, is not defined in the Act, and the Legislature has not used it except in three other statutes waiving governmental immunity, where it is also undefined: the State Contract Claims Act,57 the County Contract Claims Act,58 and the State Agency Contract Claims Act.59 The word “due” simply means “owing or payable”60 and “owing” means “unpaid“.61 A
“balance due and owed ... under the contract” is simply the amount of damages for breach of contract payable and unpaid. Direct damages for breach—“the necessary and usual result of the defendant‘s wrongful act”62—certainly qualify.
Section 271.153(a)(1) does not require the “balance due and owed ... under the contract” to be ascertainable from the contract because, for one thing, this Section expressly includes “any amount owed as compensation ... for owner-caused delays“, an amount which cannot be determined in advance, when the contract is executed. To “include” means “[t]o contain as a part of something.”63 “[A]mount[s] owed as compensation for ... owner-caused delays“, allowed by Subsection (a)(1), are consequential damages that are recoverable by law, not merely contractual right.64 Delay damages can be a “balance due and owed” only if that phrase is not limited to amounts stated in the contract.65
We conclude that the Local Government Contract Claims Act waives immunity for a contract claim for delay damages not expressly provided for in the contract.73 We now turn to whether Zachry‘s claim is barred by the no-damages-for-delay provision of the contract.
III
We held in Green International, Inc. v. Solis that a contractor may generally agree to assume the risk of construction delays and not seek damages.74 But we noted that the court of appeals in City of Houston v. R.F. Ball Construction Co.75
when the delay: (1) was not intended or contemplated by the parties to be within the purview of the provision; (2) resulted from fraud, misrepresentation, or other bad faith on the part of one seeking the benefit of the provision; (3) has extended for such an unreasonable length of time that the party delayed would have been justified in abandoning the contract; or (4) is not within the specifically enumerated delays to which the clause applies.76
And we also noted77 that the court of appeals in Green had identified a fifth exception “based upon active interference” with the contractor “or other wrongful conduct“, including “arbitrary and capricious acts“—” ‘willful and unreasoning actions,’ ‘without due consideration’ and ‘in disregard of the rights of other parties.’ ”78 The issues in Green did not require us to determine whether the courts of appeals in that case and Ball were correct in their statement of the law. Zachry contends that the second and fifth exceptions apply here.
The jury found that Zachry‘s delay damages resulted from the Port‘s “arbitrary and capricious conduct, active interference, bad faith and/or fraud” as those terms were defined in the charge.79 The court of appeals concluded that, assuming such conduct fell within the second exception, the exception could not apply if the parties intended the no-damages-for-delay provision to cover the Port‘s conduct.80 The provision stated that Zachry could not recover from the Port “any damages arising out of or associated with any delay or hindrance” to its work, even if due to the Port‘s “negligence, breach of contract or other fault“, and that its “sole remedy in any such case” would be “an extension of time.” By “other fault“, the court concluded, the parties intended to include the kind of misconduct by the Port found by the jury in awarding damages.81 “As harsh as this result seems,” the court explained, the parties must be bound by their agreement.82 Rejecting Zachry‘s argument that enforcing the no-damages-for-delay provision made the contract illusory, allowing the Port to delay performance in perpetuity with impunity, the court responded simply that it would not deprive the Port of its bargain.83
As a matter of textual interpretation, it is doubtful whether the rule of ejusdem generis would allow “other fault“, following “negligence” and “breach of contract“, to include the kind of deliberate, wrongful conduct the Port was found by the jury to have engaged in.84 That interpretation is
Based on their years of experience, education, and training, [contractors] can assess potential delaying events when estimating and bidding public works. For example, they can make a judgment on the quality and completeness of the plans and specifications, determine potential delays resulting from material shortages, analyze historical weather data for potential delays, and assess possible delays from soil conditions by studying soil testing reports furnished by most owners. However, they cannot assess potential delays that may arise due to an owner‘s direct interference, willful acts, negligence, bad faith fraudulent acts, and/or omissions.85
Regardless, the purpose of the second Ball exception is to preclude a party from insulating himself from liability for his own deliberate, wrongful conduct.
We have indicated that pre-injury waivers of future liability for gross negligence are void as against public policy.86 Generally, a contractual provision “exempting a party from tort liability for harm caused intentionally or recklessly is unenforceable on grounds of public policy.”87 We think the same may be said of contract liability. To conclude otherwise would incentivize wrongful conduct and damage contractual relations. This conclusion is supported by lower court decisions in Texas88 and court decisions in at least 28 American jurisdictions.89 We join this overwhelming consensus. The Port
Accordingly, we conclude that the no-damages-for-delay provision, Section 5.07 of the parties’ contract, was unenforceable.
IV
Several issues remain.
First: Zachry‘s contends that it is entitled to recover the $2.36 million that the Port withheld as liquidated damages for Zachry‘s failure to meet deadlines. For each progress payment, Zachry executed a document entitled “Affidavit and Partial Release of Lien“, which contained the following language:
[Zachry] hereby acknowledges and certifies that [the Port Authority] has made partial payment to [Zachry] on all sums owing on Payment Estimate Number [—] and that it has no further claims against [the Port Authority] for the portion of the Work completed and listed on the Schedule of Costs in Payment Estimate Number [—].
Zachry contends that the releases covered only liens. The Port counters that the releases covered all claims for payment. The trial court concluded that the release language was ambiguous on the issue and charged the jury to determine its effect.
The jury failed to find that the release language covered Zachry‘s claims for liquidated damages withheld by the Port. The court of appeals held that the releases unambiguously covered Zachry‘s claim for liquidated damages and reversed.92 We agree that the releases are unambiguous, but we conclude that they do not cover Zachry‘s claim.
Section 6.07 of the contract conditioned the Port‘s obligation to make progress payments on Zachry‘s execution of “waivers and releases of liens” providing “that all amounts due and payable” to Zachry and all subcontractors and suppliers “have been paid in full” and that Zachry “waives, releases and relinquishes any lien ..., security interest and claim for payment“. The Port argues that the releases must be construed in light of this requirement because the contract and releases are related contracts and must be read together.93 While Section 6.07 could be read to require Zachry to release its claims for liquidated damages withheld by the Port in order to obtain progress payments, that is not the issue. Had the Port insisted on express language to that effect, and had Zachry refused, the interpretation of Section 6.07 would be important. Now, however, the issue is not what releases Zachry was contractually required to execute, but the effect of the releases Zachry actually did execute.
The release forms were captioned “Affidavit and Partial Release of Lien“. In the form language, Zachry acknowledged “partial payment ... on all sums owing” on a specified invoice and stated that it had “no further claims against [the Port] for the portion of the Work completed and listed on” the invoice. The release plainly refers only to claims for work completed, not for
Second: The trial court did not award Zachry the entirety of the $2.36 million in withheld payments because the jury found that the Port was entitled to an offset of $970,000 as damages for Zachry‘s use of defective wharf fenders. Zachry contends that the evidence is legally insufficient to support the jury‘s finding.
To prove its claim for the offset, the Port submitted evidence that the wharf fenders, which protect vessels from damage during the mooring process, were supposed to last for 30 years but became corroded after only 90 days. The Port‘s expert witness testified that this occurred because the fenders were improperly sealed and, as a result, “the aluminum pores [] remain[ed] open [and] filled with sea water.” A lab analysis and tests that a structural fabrication company conducted supported the expert‘s conclusion. Zachry contends that the evidence does not establish that it breached the contract because the sealing or coating on the fenders was “thinned” at 25% in accordance with the contract specifications, and if more thinning was required then the blame lies with the specifications and not with Zachry. Even if there were a breach of contract, Zachry argues that the evidence does not establish that the fenders were in fact defective or that the breach caused the damages that the jury awarded.
Viewing the evidence in the light most favorable to the verdict, we cannot agree that the evidence was legally insufficient to support the jury‘s verdict. Although Zachry submitted evidence that tended to contradict the Port‘s evidence, we conclude that there was “more than a mere scintilla” of evidence on which a reasonable jury could find that Zachry breached its obligation to provide fenders that were supposed to last for 30 years by providing fenders that began corroding within 90 days, and that the Port sustained damages in the amount of $970,000 as a result, entitling it to an offset against the damages recovered by Zachry.
Third: The contract provided that “[i]f [Zachry] brings any claim against the Port Authority and [Zachry] does not prevail with respect to such claim, [Zachry] shall be liable for all attorney‘s fees incurred by the Port Authority as a result of such claim.” The jury found that the Port incurred $10.5 million in attorney fees as a result of Zachry‘s claim for delay damages, plus additional fees on appeal. Separately, the jury found that the Port incurred $80,250 in attorney fees as a result of Zachry‘s claim to recover the payments that the Port withheld as liquidated damages, plus additional fees on appeal. In light of our holdings that Zachry prevails on both its claims for delay damages and to recover part of the withheld payments, we reverse the court of appeals’ judgment awarding the Port attorney fees.
* * * * *
We hold that Zachry‘s claim for delay damages is not barred by immunity or by the no-damages-for-delay provision of the contract. We also hold that Zachry is entitled to recover the liquidated damages
Justice BOYD filed a dissenting opinion, in which Justice JOHNSON, Justice WILLETT, and Justice LEHRMANN joined.
Justice BOYD, joined by Justice JOHNSON, Justice WILLETT, and Justice LEHRMANN, dissenting in part.
Chapter 271 of the Texas Local Government Code waives a local governmental entity‘s immunity against suits for breach of written contracts for goods and services, but it does so only to allow contractors to recover “the balance due and owed by the local governmental entity under the contract.”
I.
Governmental Immunity Against Contract Actions
As a local governmental entity, the Port Authority “enjoy[s] governmental immunity from suit, unless immunity is expressly waived.” Kirby Lake Dev., Ltd. v. Clear Lake City Water Auth., 320 S.W.3d 829, 836 (Tex.2010). Governmental immunity
While most damages awards justly impose the financial consequences of a party‘s wrongdoing on the wrongdoer, a damages award against a governmental entity imposes the financial consequences on innocent third parties: taxpayers. Thus, although “[t]he doctrine of governmental immunity arose hundreds of years ago from the idea that ‘the king can do no wrong,’ ... it remains a fundamental principle of Texas law, intended ‘to shield the public from the costs and consequences of improvident actions of their governments.‘” Lubbock Cnty. Water Control & Improvement Dist. v. Church & Akin, L.L.C., 442 S.W.3d 297, 300 (Tex.2014) (quoting Tooke, 197 S.W.3d at 331-32). In some circumstances, however, justice may demand that the government compensate innocent injured parties even though innocent taxpayers must pay the bill. The challenge is in deciding which circumstances justify a waiver of immunity to allow for such compensation.
Because this decision “requires balancing numerous policy considerations, we have consistently deferred to the Legislature, as the public‘s elected representative body, to decide whether and when to waive the government‘s immunity.” Lubbock Cnty., 442 S.W.3d at 301. The Legislature may waive the government‘s immunity, and thereby “consent to suit[,] by statute or by legislative resolution.” Fed. Sign v. Tex. S. Univ., 951 S.W.2d 401, 405 (Tex. 1997). The Legislature has declared that we cannot construe a statute to waive immunity “unless the waiver is effected by clear and unambiguous language.”
For the first 154 years of Texas’ existence, parties who contracted with the government could not recover for the government‘s breach unless they first convinced the Legislature to pass a special resolution waiving immunity for their specific claim. See Fed. Sign, 951 S.W.2d at 408 (reaffirming previous holdings that “the State is immune from suit arising from breach of contract suits“);
Although Chapter 2260 provides a limited avenue of relief for those who contract with State agencies and departments,3 it provides no remedy at all for those who contract with a local governmental entity. The Legislature first addressed local governmental entities in 2003, when it enacted a limited waiver of immunity for certain breach of contract suits against Texas counties. See
As it had done in Chapter 2260, the Legislature strictly limited the immunity waivers in Chapters 262, 271, and 114, not only in terms of the types of contracts under which a party can sue, but also in terms of the types and amounts of damages the party can recover. See
II.
Section 271.153
Section 271.153 is entitled ”LIMITATIONS ON ADJUDICATION AWARDS.”
- the balance due and owed by the local governmental entity under the contract as it may have been amended, including any amount owed as compensation for the increased cost to perform the work as a direct result of owner-caused delays or acceleration;
- the amount owed for change orders or additional work the contractor is directed to perform by a local governmental entity in connection with the contract; and
- interest as allowed by law.
- consequential damages, except as expressly allowed under Subsection (a)(1);
- exemplary damages; or
- damages for unabsorbed home office overhead.
The Court holds that subsection (a)(1) authorizes Zachry to recover its delay damages. While I agree that delay damages can be part of “the balance due and owed by [a] local governmental entity under [some] contract[s],” I do not agree that they are part of “the balance due and owed by [the Port Authority] under [this] contract.” To the contrary, this contract expressly provided that the Port Authority would have no liability for any delay damages. And while I agree that “the balance due and owed ... under the contract” can include “compensation for ... owner-caused delays,” compensation for owner-caused delays are not part of the balance due and owed under this contract, which stated that the contractor “shall receive no financial compensation for delay or hindrance to the Work ... EVEN IF SUCH DELAY OR HINDRANCE RESULTS FROM, ARISES OUT OF OR IS DUE, IN WHOLE OR IN PART, TO THE NEGLIGENCE, BREACH OF THE CONTRACT OR OTHER FAULT OF THE PORT AUTHORITY.”
A. The Balance Due and Owed Under the Contract
Chapter 271 does not define or describe what constitutes “the balance due and owed ... under the contract.” When a statute does not give words a specific definition or technical meaning, we use their common, ordinary meaning. City of Rockwall v. Hughes, 246 S.W.3d 621, 625-26 (Tex.2008). Typically, we look to dictionaries to determine the common meaning of words.5 See Epps v. Fowler, 351 S.W.3d 862, 873 (Tex.2011) (Hecht, J., dissenting) (“The place to look for the ordinary meaning of words is ... a dictionary.“). When a word has multiple common meanings, we give it the meaning most consistent with the statutory context
In the context of payment obligations, the term “balance” means “the difference between the debits and credits of (an account).” BLACK‘S LAW DICTIONARY 170 (10th Ed.). The term “due” means (1) “payable; owing; constituting a debt,” when used in relation to a “fact of indebtedness,” or (2) “immediately enforceable,” when used in relation to “the time of payment.” Bryan A. Garner, A DICTIONARY OF MODERN LEGAL USAGE, 298-99 (2nd ed.); see also Black‘s Law Dictionary 609 (10th Ed.). The Dictionary of Modern Legal Usage notes that the second definition, “immediately enforceable,” is “almost invariably the applicable one” today. DICTIONARY OF MODERN LEGAL USAGE at 299. And the term “owing” means “[t]hat is yet to be paid; owed; due.” BLACK‘S LAW DICTIONARY 1279 (10th Ed.); see also DICTIONARY OF MODERN LEGAL USAGE at 633 (noting that “owed” is the preferred modern usage, over “owing“). The difference between the terms “due” and “owed” is reflected in the fact that something can be owed but not yet due because the date for payment or the contingency on which payment is conditioned has not yet come to pass. See DICTIONARY OF MODERN LEGAL USAGE at 299. A “balance” that is both “due” and “owed” is thus an amount by which an account‘s debits exceed its credits that is yet to be paid and immediately enforceable. Stated another way, a balance due and owed is a mature debt. This understanding of the phrase is consistent with both the statutory context, which relates to recoverable monetary obligations under a contract, and with our prior use of the phrase “due and owed” or “due and owing,” both in our construction of this statute and more generally.6
Importantly,
The Court, by contrast, concludes that “[a] ‘balance due and owed ... under the contract’ is simply the amount of damages for breach of contract payable and unpaid.” Ante at 111. I do not agree that a “balance due and owed ... under a contract” includes all common law damages regardless of whether they are contemplated in the parties’ contract. When a payment is not provided for under the contract, but instead arises under the common law, that payment may later be due and owed under the court‘s judgment, but is not part of “the balance due and owed ... under the contract.” See
The Court‘s construction of the statute is contrary to the statute‘s language and its structure. First, the Court‘s construction separates the phrase “balance due and owed” from the phrase “under the contract,” and then alternatively reads each of them out of the statute. On the one hand, the Court equates the phrase “the balance due and owed” with the phrase “damages ... payable and unpaid,” ante at 111, and by doing so ignores the statute‘s actual words. On the other hand, the Court treats the phrase “under the contract” as if it said “under a court‘s judgment,” but does so only by relying on court opinions that address damages under a contract, not a “balance due and owed ... under a contract.” Ante at 111 n. 62, 64. We must read the two phrases together, just as they appear in the statute, and the Court‘s alternatives for each simply are not equivalents. By equating “the balance due and owed ... under the contract” with “the amount of damages for breach of contract payable and unpaid,” the Court shifts the focus from the mature debt that exists “under the contract” when suit is filed to prospective liability that a Court may impose in a breach of contract action.
Second, by holding that “a ‘balance due and owed ... under the contract’ is simply the amount of damages for breach of contract payable and unpaid,” the Court renders subsection (a)(1) a tautology. Under the Court‘s construction, the amount of damages that is recoverable for a breach of contract is “limit[ed]” to the amount of damages that is recoverable for a breach of contract. Under that construction, the amount of damages is not “limited” at all.7
Third, the Court‘s construction of subsection (a)(1) renders subsection (a)(2) superfluous. Subsection (a)(2) expressly authorizes the recovery of “the amount owed
Finally, under the Court‘s construction of subsection (a)(1), the exception to the exclusion of consequential damages in subsection (b)(1) would completely swallow the rule. Subsection (b)(1) provides that recoverable damages may not include “consequential damages, except as expressly allowed under Subsection (a)(1).”
In short, under the Court‘s construction, subsection (a), which says recoverable amounts are “limited” to those specified in subsections (a)(1) through (a)(4), does not in fact “limit” anything; and subsection (b), which says recoverable amounts “may not include” those listed in subsection (b)(1), does not in fact exclude anything.
In addition to the language of the statute, the Court‘s holding contradicts our precedent on this very point. We have addressed
In Tooke, the Court held that the claimants could not recover after the City of Mexia prematurely terminated their service contract because they “claim[ed] only lost profits on additional work they should have been given,” which “are consequential
Similarly, in Sharyland, the contractor, the Sharyland Water Supply Corporation, sought to recover its “increased cost to perform” its contractual duty to repair and maintain a water system, which allegedly resulted from the City of Alton‘s breach of its own contractual duties. 354 S.W.3d at 413. We held that
In Kirby Lake, by contrast, we held that the damages the claimant sought were recoverable as “the balance due and owed ... under the contract” because “the Agreements do stipulate the amount of reimbursement owed upon approval of bond funds.” 320 S.W.3d at 840 (emphasis added). Consistent with the language of the statute and our precedent, I would hold that
B. “Including Any Amount Owed as Compensation for the Increased Cost to Perform....”
Relying on the language at the end of
The Court misconstrues the language at the end subsection (a)(1) to independently authorize recovery of “any amount owed as compensation ... for owner-caused delays,” even if that amount is not part of “the balance due and owed ... under the contract.” Ante at 111. In doing so, the Court overlooks the key word that connects these two phrases: “including.” The word “including” in this subsection does not expand the meaning of the words that come before it (“the balance due and owed“); rather, it limits the meaning of the words that come after it (“any [owner-caused delay damages]“) to “include” only those owner-caused delay damages that are in fact “due and owed.” See BLACK‘S LAW DICTIONARY at 766 (defining “include” to mean “contain as part of something“). The Court thus reads subsection (a)(1) as authorizing recovery of the balance due and owed under the contract and (or plus) any delay damages, when in fact the statute authorizes recovery of “the balance due and owed ... under the contract ..., including any amount owed” as damages for owner-caused delays.
For example, if a franchise agreement authorized a franchisee to operate “in any Texas city, including Athens,” the agreement would permit operations in Athens, Texas, but not in Athens, Greece, or Athens, Georgia. The word “including” is not a synonym for the word “and.” It does not expand the meaning of “any Texas city” to include Athens, Greece, or Athens, Georgia, merely because those cities are also named “Athens.” Instead, it limits the scope of the reference to “Athens” to the “Texas city” by that name.10 In the
The language the Legislature used in its most recent statutory waiver of immunity for breach of contract suits further confirms this point. See
the balance due and owed by the state agency under the contract as it may have been amended, including any amount owed as compensation for the increased cost to perform the work as a direct result of owner-caused delays or acceleration if the contract expressly provides for that compensation....
Parties to construction contracts often allocate unquantified costs between themselves, just as Zachry and the Port Authority did with delay costs. Zachry and the Port Authority allocated all of Zachry‘s delay-related expenses and losses to Zachry, even if the Port Authority was at fault for the delay. But parties to construction contracts sometimes choose a different allocation, obligating an owner to reimburse the contractor for some or all owner-caused delay costs. See, e.g., MasTec N. Am., Inc. v. El Paso Field Servs., L.P., 317 S.W.3d 431, 452 (Tex.App.-Houston [1st Dist.] 2010) (involving construction contract in which owner agreed to compensate contractor for certain owner-caused delays) rev‘d, 389 S.W.3d 802 (Tex.2012) (holding that contract allocated all risk of unknown obstructions in construction path to contractor); Shintech Inc. v. Group Constructors, Inc., 688 S.W.2d 144, 148 (Tex.App.-Houston [14th Dist.] 1985, no writ) (involving contract that allocated to the owner‘s account undue expenses incurred by the contractor as a result of owner-caused delays). If this contract had
III.
Conclusion
I agree with the Court that Zachry‘s claim to recover installment payments that the Port Authority withheld as liquidated damages are recoverable under
TEXAS GENERAL LAND OFFICE and Texas Commission on Environmental Quality, Appellants,
v.
CRYSTAL CLEAR WATER SUPPLY CORPORATION, Appellee,
Texas General Land Office and Texas Commission on Environmental Quality, Cross-Appellees.
No. 03-13-00528-CV.
Court of Appeals of Texas, Austin.
Aug. 22, 2014.
Rehearing Overruled Oct. 28, 2014.
Notes
You are instructed that § 5.07 of the Contract precludes Zachry from recovering delay or hindrance damages, if any, unless you find that the delay or hindrance damages, if any, resulted from a delay or hindrance that was the result of the Port‘s actions, if any, that constituted arbitrary and capricious conduct, active interference, bad faith and/or fraud.
“Arbitrary and capricious” means willful and unreasoning action without due consideration and in disregard of the facts, circumstances, and rights of other parties involved.
“Active interference” means affirmative, willful action that unreasonably interferes with the other party‘s compliance with the contract. “Active interference” requires more than a simple mistake, error in judgment, lack of total effort, or lack of complete diligence.
“Bad faith” is conscious doing of a wrong for a dishonest purpose.
“Fraud” occurs when
1. a party makes a material misrepresentation,
2. the misrepresentation is made with knowledge of its falsity or made recklessly without any knowledge of the truth and as a positive assertion,
3. the misrepresentation is made with the intention that it should be acted on by the other party, and
4. the other party suffers injury as a result of its reliance on the misrepresentation.
“Misrepresentation” means a promise of future performance made with an intent, at the time the promise was made, not to perform as promised, and the promise of future performance is that the Port would comply with the terms of Change Order 4. In response, the Court contends that the statute does “limit[] recovery” because “damages are but one item in a list that includes attorney‘s fees and interest, even if not provided for in the contract.” Ante at 113 n. 66. But
- certain types of damages: “the balance due and owed ... under the contract” under
section 271.153(a)(1) and “the amount owed for change orders or additional work” under (a)(2); - certain types of attorney‘s fees: “reasonable and necessary attorney‘s fees that are equitable and just” under (a)(3); and
- all interest allowed by law under (a)(4).
Sharyland, 354 S.W.3d at 413. We thus addressed all provisions of subsections (a)(1) and (a)(2), demonstrating that there was no possible basis on which any of them could have authorized the recovery of the repair and maintenance costs that Sharyland sought. SeeThe kind of damages sought by Sharyland were not those provided for or contemplated in the Water Supply Agreement and are not a “balance due and owed” under that contract. Nor are these costs the “direct result of owner-caused delays or acceleration,” or the “amount owed for change orders or additional work the contractor [was] directed to perform by [the] local governmental entity in connection with the contract.”
