History
  • No items yet
midpage
187 F. Supp. 3d 893
M.D. Tenn.
2016
Read the full case

Background

  • Summit Contracting (licensed Tennessee general contractor) entered a construction contract with Ashland Heights, LP to build an assisted living facility for an initial lump-sum of $8,667,731; contract governed by Tennessee law and provided for retainage, progress payments, interest on late payments, and attorney fees to prevailing party.
  • Summit alleged substantial completion in May 2015 and that Ashland withheld 5% retainage from progress payments (total alleged withheld: $320,415.74) but failed to deposit retained funds into a third-party, interest-bearing escrow as required by Tennessee retainage statutes.
  • Summit sent a statutory demand in October 2014 and alleged entitlement to a $300/day statutory penalty for failure to escrow retainage; Ashland later produced evidence of a deposit at Max Credit Union but Summit disputed that it satisfied the statutory escrow requirement.
  • Summit also alleged unpaid change orders, untimely payments (contractual interest owed), extended general conditions for weather delays beyond 30 days, and other costs; it brought federal suit for breach of contract, retainage and Prompt Pay Act claims seeking > $1.5 million.
  • Separately, Summit filed a state-court mechanic’s lien/enforcement action seeking enforcement of a lien for $1,074,668.74; the state action named additional parties but those third parties were later dismissed.
  • Ashland moved to dismiss/abstain under the Colorado River doctrine, arguing parallel state and federal proceedings warranted dismissal without prejudice; the court denied the motion.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Whether federal court must abstain/dismiss under Colorado River because of a prior state mechanic’s lien action Summit: federal breach/retainage claims proceed; lien action is limited and won’t resolve all federal issues Ashland: actions are parallel; state lien adjudication will render federal case moot and conserve resources Denied—actions are not sufficiently parallel; state action will not resolve all federal claims
Whether state lien action is coextensive with federal breach/retainage claims Summit: lien action enforces lien amount only and cannot recover statutory penalties, contract interest, attorney fees or non-lien damages Ashland: overlap in parties/contract means issues are identical and duplicative Court agreed with Summit: lien action and breach action involve different issues and remedies
Whether Colorado River abstention requires exact parallelism Summit: substantial similarity insufficient if state suit won’t dispose of all federal claims Ashland: argued substantial similarity/overlap suffices Court applied Sixth Circuit precedent: exact parallelism not required but must be substantial likelihood state suit will resolve all federal claims; here it will not
Whether abstention would promote judicial economy/comity here Ashland: staying/dismissing promotes economy and comity Summit: state forum inadequate to decide all claims; abstention would likely leave federal claims unresolved Court found substantial doubt state action would be adequate vehicle; abstention inappropriate

Key Cases Cited

  • Colorado River Water Conservation Dist. v. United States, 424 U.S. 800 (discusses narrow circumstances permitting federal abstention in favor of parallel state proceedings)
  • Moses H. Cone Memorial Hospital v. Mercury Construction Corp., 460 U.S. 1 (federal courts have a strong obligation to exercise jurisdiction; stays only where state proceeding will resolve federal case fully)
  • Romine v. CompuServe Corp., 160 F.3d 337 (6th Cir.) (Colorado River analysis: determine parallelism then weigh factors)
  • Baskin v. Bath Township Board of Zoning Appeals, 15 F.3d 569 (6th Cir.) (compare issues actually raised in state action to those in federal action)
  • Nakash v. Marciano, 882 F.2d 1411 (9th Cir.) (exact parallelism not required; proceedings must be substantially similar)
  • Gannett Co. v. Clark Construction Group, Inc., 286 F.3d 737 (4th Cir.) (lien enforcement and breach-of-contract actions involve different issues and remedies)
  • Fru-Con Construction Corp. v. Controlled Air, Inc., 574 F.3d 527 (8th Cir.) (mechanic’s lien action determines unpaid labor/materials for property improvement and does not resolve breach/damages claims)
Read the full case

Case Details

Case Name: Summit Contracting Group, Inc. v. Ashland Heights, LP
Court Name: District Court, M.D. Tennessee
Date Published: May 6, 2016
Citations: 187 F. Supp. 3d 893; 2016 WL 2607056; 2016 U.S. Dist. LEXIS 60662; Civil No. 3:16-CV-17
Docket Number: Civil No. 3:16-CV-17
Court Abbreviation: M.D. Tenn.
Log In
    Summit Contracting Group, Inc. v. Ashland Heights, LP, 187 F. Supp. 3d 893