*1 IV. assis- provide substantial did Smith government’s claims that tance. Smith reasons, we affirm the foregoing For “clearly sentencing was his during position of the district court. judgment in the Octo- position with its inconsistent” it to brief submitted 16, appellate ber sen- Vasquez’s co-conspirator
this court brief, govern- In that
tencing appeal. had district court “that the argued
ment relying upon no error
committed a three- testimony] imposing [Smith’s CONSTRUCTION CORPO FRU-CON at Vas- sentencing enhancement” level RATION; Maintenance & Austin disagree hearing. We sentencing quez’s Corpo Construction, Delaware with Smith. ration, doing as Fru- business JV, Con/Austin, Appellants, equita estoppel is Judicial protect integ remedy fashioned “to ble by prohibiting judicial process rity of the AIR, INC., a Kansas CONTROLLED posi deliberately changing from Corporation, Appellee. exigencies according to tions Maine, 532 Hampshire v. No. New 08-1712. moment.” 1808, 749-50, Appeals, United States Court (2001) (internal citations L.Ed.2d Eighth Circuit. omitted). prevail In order to quotations must judicial estoppel, Smith a claim of Sept. 2008. Submitted: posi government’s first establish July Filed: 2009. “ ‘clearly incon sentencing was at his tion ” En Banc Rehearing Rehearing during position’ its earlier with sistent Sept. Denied Stallings v. Huss appeal. See Vasquez’s 1041, 1047 Cir. Corp., 447 F.3d mann
2006) Hampshire, 532 U.S. (quoting New 1808). has failed Smith S.Ct. There is requirement. this basic
to meet gov with the “clearly inconsistent”
nothing did not war position that Smith
ernment’s 3553(e) position § and its motion
rant that Smith’s Vasquez appeal
during serve as enough reliable to
testimony was enhancement. sentencing of a
the basis of wheth determination government’s
The assistance substantial provided
er Smith based on “the the motion was
and merited assistance” of the defendant’s
significance trials. Vasquez and Islas-Bravo
in both govern highlighted, previously
As includes consider to move
ment’s decision factors in addition Smith’s many
ation of fails. claim thus
credibility. Smith’s *3 BYE, BEAM, SHEPHERD,
Before Judges. Circuit BEAM, Judge. Circuit Corporation Fru-Con Construction Construction, Austin Maintenance and Inc. (the Venture) appeal Joint application court’s of Colorado River1 ab- stention to dismiss the Joint Venture’s *4 breach of against contract action Con- Air, trolled Inc. We reverse.
I. BACKGROUND Ravenna, L.L.C., Nordic Biofuels of hired the Joint Venture through a real improvement estate contract as defined § Nebraska Revised Statute 52-130 to construct an production facility ethanol Ravenna, Nebraska. The Joint Venture engaged Air Controlled to construct grain receiving, storage, milling sys- and tem for facility. agreement Their con- tained law and forum selection clauses re- quiring disputes all between the governed by be brought Missouri law and in Missouri state court or the federal dis- trict court for the Eastern District of Mis- souri. Additionally, the contract allowed the Joint Venture to terminate Controlled Air specified for reasons and to take over being performed the work giving after sev- enty-two hours written notice. dispute A between Air Controlled and the Joint Venture arose and work ceased on the project. Air supplied Controlled John Roger Edgar, argued, Christopher 14, and through January labor materials Daus, Sr., J. Timothy Thornton, R. on 2007, and the Joint Venture assumed re- brief, MO, St. Louis appellant. for sponsibility 17, for January the work on Hiotis, Stephen C. argued, Daniel J. 2007. Pursuant to the Nebraska Con- Welsh, Eggmann, and Robert E. (NCLA), on the struction Lien Act Controlled Air brief, Louis, MO, St. appellee. for recorded a construction lien on March (1976). 1. Colorado River Water Conservation Dist. L.Ed.2d 483 States, United 424 U.S. company labor and ma- authorized to do business Ne- unpaid purportedly braska, alleged that recording longer The the action was no rem
terials. Air owed Controlled applied, Venture the forum selection clause Joint $1,496,636 provided and materials for labor mandating jurisdiction in Missouri. Dur- Air filed January Controlled through matter, ing hearing first on this the construction lien in to foreclose suit court held that was bond County, Ne- of Buffalo the District Court only person having because ineffective braska, Ven- May 2007. The Joint in the real estate file a bond interest ture, however, previously had filed 52-142, § under Nebraska Revised Statute against of contract action Con- breach did not have an Joint Venture District Air in the United States trolled property.2 interest the lien After the for the Eastern District Missouri. Court bond, Venture amended the the Ne- Joint that the Ven- complaint alleged The Joint again braska court held bond ineffec- $1,500,000 damages of after ture incurred identify it tive because failed to where and 17, 2007, as a result of Controlled January Fi- upon whom service should be made. agreement. Air’s breach nally, after the Joint corrected all Venture *5 mistakes, the court purported Nebraska lien fore- Believing that its ruled on the motion to dismiss. litigate to the action could serve closure parties, the dispute between Con- entire The Nebraska court first noted that the asking a motion the fed- trolled Air filed lien,3 discharged bond the real estate but from or dismiss the eral court to abstain that action then concluded the foreclosure of contract claim breach Joint Venture’s was still in existence “in so much as the of Missouri. Be- in the Eastern District surety lien is transferred to the submitted court forum could lieving that the federal basis, bond.” On this the court held that purpose, same the Joint Ven- serve the validity original the of the construction lien in a lien relief bond Buffalo ture filed might the amounts that be owed on it and Nebraska, in accordance with the County, Thus, question. in still the court were NCLA, releasing the construction lien remedy that an appropriate decided was clearing the lien from the title to the in not available the federal forum and de- A to question. real estate in motion dis- the motion to dismiss. nied stay Air’s lien foreclo- miss or Controlled contract action not Although had by was then filed proceeding sure Nebraska, court, in been asserted the state in the District Court of Joint Venture Thus, making ruling, applied a fo- its Nebraska Re- County. Buffalo federal-state dispose § of the fight rum came to life. vised Statute 25-415 forum clause. That sec- contract’s selection Proceedings A. Nebraska recognition fo- tion codifies Nebraska’s clauses, provides rum selection but five motion to The Joint Venture’s dismiss originally proceeding alleged exceptions. While the the lien foreclosure by surety by exceptions poten- bond a viewed three of the as filing that a issued price. Tilt-Up payment of his or her contract was error. Pursuant to Nebraska Re- This 52-131(1), (includ- Concrete, any person § City/Fed., vised Statute Inc. v. 255 Neb. Star Venture, ing prime (1998) Joint contractor as (quoting 582 N.W.2d § Statute 52- defined in Nebraska Revised 52-131(1)). § Neb.Rev.Stat. " 127(8)), or materials 'who furnishes services improvement pursuant to a real estate con- analysis. 3. This was a correct " lien[,]' tract has a construction to secure Clearly tially applicable, ultimately believing it determined that the federal con- tract action and the state lien foreclosure that the Joint Venture’s bond was ineffec- proceeding were matters5 —un- releasing from real tive the lien Venture, fact that aware the Joint estate, creating an in rem action that had protest under and out of an abundance of disputé- to be resolved at the situs of the caution, had later asserted its contract ac- However, stated, isebraska. as earlier Air in against tion Controlled the Nebras- recognized Nebraska court later its error court, Air, ka Abengoa Controlled Inc. v. efficacy releasing to the bond Neb., LLC, (D. Bioenergy No. CI07319 thereafter, upon the real estate lien and 2007) County, Ct. Buffalo Neb. Oct. reconsideration, made its dismissal deci- (answer counterclaim) —the upon purported sion based district court first referenced the six ab- “unique[ness of the lien to the Ne- action] stention factors created Colorado River jurisdiction” making remedy braska — proceeded and then to discuss each in in the federal forum. available As men- turn. The court following found below, tioned the federal district court (1) factors favored abstention: while the error, found this to be a matter with which Nebraska action is not in rem and the agree greater we discuss detail juris- state court does not have exclusive Section IIA. diction, the state court has an interest (2)
adjudicating the dispute; al- lowing the federal action to continue would Proceedings B. Federal (3) in piecemeal litigation; result the Ne- The District Court for the Eastern Dis- forum; braska court ais more convenient *6 trict of recognized subject Missouri its (4) (5) controls; state law and the state jurisdiction matter but granted Controlled adequately court can protect the Joint Air’s motion to abstain from and dismiss rights. Venture’s The sixth and final fac- the Joint Venture’s breach of contract ac- (of regarding priority tor filing the fed- tion, but after the Nebraska court eral contract action and the state lien fore- jurisdiction retained over the action) lien foreclo- Then, closure was held neutral. proceeding.4 sure The Joint Venture dis- the district court abstained from and dis- puted Controlled Air’s motion to in missed the abstain federal case. grounds
the federal case on
that the con-
clause,
Turning to the forum selection
struction lien property
longer
was no
un-
considered,
separately
which it
der the exclusive control of the Nebraska
that “any questions
concluded
of fo-
court and because the forum selection
validly
rum were
by
decided
the Nebraska
jurisdiction
clause
that
mandated
over its
court.” The district court concluded that
contract action
in
properly
was
the federal
a question
abstention was
for it to decide
court.
while enforcement of the forum selection
respective
Controlled Air's motion
parties
plan
to dismiss for lack
on the ethanol
located
personal jurisdiction
improper
factor,
venue
although
in Nebraska. This
it does not
was
appeal
denied. As Controlled Air did not
abstention, weighs
mandate
in favor of ab-
ruling
today.
that
it is not before us
Appellants' App.
stention.”
at 125-26.
currently pending
"There is
before the Ne-
5. The
formulating
federal district court in
its
involving
braska state court an action
states,
abstention and dismissal order
for in-
property
same Parties and the same
at issue
stance,
dispute
"both the contract
before this
in the suit before this Court.” Id. Court, and the collection actions in the Ne-
N.W.2d 604.
court,
performed by
braska
involve work
judgments
satisfy
a realization on
to
left “to
question
best
clause was
Concrete,
Tilt-Up
Nebraska state
judgment of the
NCLA-based claim.
sound
timely
Inc.,
filed a
Venture
City/Fed.,
court.” The Joint
Inc. v.
261 Neb.
Star
(2001).
court im-
that the district
alleging
And,
appeal
any
621 N.W.2d
and dismissed.
abstained
properly
in
grounded
equity. Tilt-Up
action is
Concrete,
City/Fed.,
Inc. v.
Star
II. DISCUSSION
(1998).
It
Neb.
582 N.W.2d
availability of a federal
Because the
appeal
is reviewed on
de novo on the rec-
claim has
for the lien foreclosure
forum
in
limits an
Nothing
ord.
Id.
the statute
the Colorado River
an issue
both
been
courts and it
NCLA action
Nebraska
enforceability of
ruling and the
already
correctly
by
has
been
determined
clause,
that
selection
we discuss
the forum
judge
the federal
the United States
at the outset.
matter
for the
District of
District Court
Eastern
subject
juris-
Missouri would have
matter
Jurisdiction
A. Lien Foreclosure
dispute
diction over the lien
as well as
over the lien dis-
jurisdiction
Nebraska
jurisdiction
over the
personal
only in the sense that the
“unique”
pute
proper venue. See n. 4.
statute,
NCLA, gov-
here
damages
amount of
erns the nature and
NCLA, “[a]ny person
Under
may
claimant
recover
its con-
the lien
having
may
an interest
real estate
re
more.
dispute, nothing
lien
Of
struction
estate
...
lease the real
from liens
course,
routinely interpret
federal courts
[depositing
the office of the clerk of the
Frequently,
law.
apply
state
district court ... a
[appropriate Nebraska]
than one
statutes from more
appeal,
§
surety
Neb.Rev.Stat.
52-
bond.”
piece
litiga-
play
single
are
in a
142(l)(a).
bond,
deposit
of a
Upon
tion.
rights
“the claimant’s
are transferred from
the real estate to
bond and the
[that]
specify
does not
The NCLA
claim
claimant
establish his or her
that must be used to
procedure
forum or
*7
52-142(3). Upon
§
under the
Id.
[Act].”6
remedies under the
rights and
determine
validity
amount
determination of the
§
A
Neb.Rev.Stat.
52-155.
legislation.
claim, the
shall render
applicable to
of a lien
court
may
any procedure
use
NCLA,
may
extent that it
be consid-
vendor such as
is limited to the
6. Under the
a contract
actually
part
compensation for services
ren-
unpaid
to the
ered
Controlled Air “is entitled
dered,
distinguished from the amount of
price when the
[ ]
[ven-
of his or her contract
substantially performed
the contractor's loss because of
owner's
the con-
dor] has
Thus,
tract,”
incorporated
at
Con-
profits
breach of contract.” Id.
615.
which includes
Concrete,
damages
Tilt-Up
trolled Air is limited in
to the rea-
the contract.
into
provided
value of labor and materials
When a vendor has not sub-
sonable
N.W.2d
prevent-
stantially performed
because Controlled Air claims it was
the contract or has been
work, however,
project.
completing
the
completing
it
ed from
work on
prevented from
And,
sure,
only
asked for
only
to be
Controlled Air
"entitled to a lien for the reasonable
is
unpaid
performed
[]
amount
for the services
“[t]he
value of the labor he or she has
furnished,
may,
furnished.” Controlled Air
or she has
materials
[]
and the material he
however,
separate
file a
action for breach of
have a lien for the dam-
the
cannot
[vendor]
profits
the lost
on the contract.
ages
contract.”
contract for
sustained from the breach of
Concrete,
Yet,
Supreme
Tilt-Up
the amount of
unflagging obligation ...
to
exercise
by the
company is dictated
NCLA. Recov-
jurisdiction
them,
given
even when there is
ery
requires proof
under the bond first
pending
involving
state court action
improvement contract”
that a “real estate
(internal
subject
same
matter.”
Id.
cita-
§
actually been entered into.
Id.
52-
has
omitted). Thus,
may
tions
a federal court
131(1).
case,
question
In
jurisdiction by abstaining
divest itself of
whether such a contract exists between
parallel
when
state and federal ac-
Air
and Controlled
is an-
Joint Venture
exceptional
tions exist and
circumstances
law—the law
by
swered Missouri
selected
warrant abstention. Colorado River Wa-
if
agreement.
under their
And even
States,
ter
Conservation Dist.
United
by
law
applicable
governed
is
800, 817-18,
424 U.S.
statute,
the federal court can make that
(1976).7
L.Ed.2d 483
So,
determination.
once it is established
improvement
that a valid real estate
con-
Six non-exhaustive factors have been de-
whether,
veloped
tract exists and that
the Joint Venture
to
determine
the case
by receiving
that contract
and of
state and
proceedings,
breached
federal
failing
pay
exceptional
pro-
for labor and materials
circumstances warrant absten-
Air,
tion.
by
recovery
vided
Controlled
under
These six factors are:
through
(1)
is
judgment
bond
had
whether there is a res over which
against
surety company.
§
Id.
52-
jurisdiction,
one court has established
142(3).
(2) the inconvenience of the
fo-
(3)
rum,
maintaining separate
whether
In the event
judgment
that such a
piecemeal litiga-
actions
result
rendered
the federal
court for
district
tion, unless the relevant law would re-
Missouri, may
the Eastern District of
it
be
quire piecemeal litigation and the feder-
transferred,
necessary,
if
to the District
(4)
severed,
al court
easily
issue is
which
Nebraska,
County,
Court of Buffalo
priority
necessarily
case has
which
—not
through the Uniform Enforcement of For-
was
greater empha-
case
filed first but a
eign Judgments
long ago
Act
enacted
progress
sis on the relative
made
§§
Nebraska.
See id.
25-1587.01 to
(5)
cases,
whether state or federal law
however,
likely,
1587.09. It is
any
controls, especially favoring the exercise
bonding company authorized to do busi-
jurisdiction
where federal
law con-
*8
ness in
directly subject
Nebraska is also
(6)
trols,
adequacy
of the state
process
service of
in the federal courts of
forum to protect
plaintiffs
the federal
Missouri.
rights.
Pure,
Mountain
535
separately,
viability
pendency
of the forum selec-
The
of a state claim based on
tion clause. Because the federal district
general
subject
the same
or
facts
matter
compared
court
the federal contract
as a federal claim
involving
the same
action and the state lien foreclosure ac- parties is not alone sufficient. Federated
tion, clearly non-parallel proceedings, the
Corp.
Rural Elec. Ins.
v. Ark.
Coop.,
Elec.
provide
Inc.,
(8th
River doctrine did not
294,
Cir.1995).
Colorado
48 F.3d
297
Thus,
judgment.
actually Rather,
basis for its
we
similarity
a substantial
must exist
need not consider whether
between the state and federal proceedings,
properly weighed
factors.
above
similarity
which
occurs when there is a
Nonetheless,
note,
for a reason we later
substantial
likelihood that
pro
the state
carefully analyze
application
we
of
fully
ceeding
dispose
will
of the claims
components
these
the federal district
presented in the federal court. TruServ
court in
IIB2.
Section
Corp.
Flegles,
584,
v.
419 F.3d
592
(7th Cir.2005).
analysis
This
focuses on
Proceedings
a. Parallel
they
exist,
matters as
currently
not as
matter,
As a threshold
as above indicat
they
Baskin,
could be modified.
15 F.3d
ed,
pending parallel
there must be
Moreover,
at 572.
in keeping with the
proceedings
and federal court
before Colo
Supreme Court’s charge to abstain in lim
implicated.
rado River is
In re
&
Burns
only, jurisdiction
ited instances
must be
Wilcox,
(8th
Ltd.,
475,
54
477
F.3d
Cir.
if
any
exercised
there is
doubt as to the
1995) (citing
Twp.
Baskin v. Bath
Bd. of parallel nature of the state and federal
(6th
569,
Zoning
Appeals,
F.3d
571-72
Int’l,
AAR
proceedings.
Inc. v. Nimelias
Cir.1994)), limited
grounds by
on other
S.A.,
(7th
510,
Enter.
250 F.3d
Cir.
Co.,
Quackenbush v. Allstate Ins.
517 U.S.
2001).
710-11,
706,
1712,
state Lancaster, 585, Air breached the sub v. 260 Neb. whether Controlled Co. 618 676, (2000); Mahan, and whether Joint Venture contract v. N.W.2d 679 C.F.S. According a damages as result. incurred 615, (Mo.Ct.App.1996); 934 S.W.2d 618 foreclosure action will not ly, the state lien Heibel, 511, 178 351, Old v. 352 Mo. S.W.2d in the contract dispose of all issues federal (1944). 352 See, e.g., George v. Stratum action. Weis Co. by Almost were identical facts addressed Inc., 486, 227 sign-Build, De S.W.3d Co., the Fourth Inc. v. Circuit Gannett (Mo.2007) (holding a lien is a claim 489-90 Group, Clark Construction 286 F.3d a against surety bond— property —here hired Gannett Clark to against is a claim a and of contract breach Today headquarters, build a new a USA thus, person; the lien proceeding did arose, dispute work ceased. and Id. at action). of dispose of the breach contract 740. a Gannett filed federal action for judgment in the any Neither will rendered breach of and filed contract Clark a lien judicata lien action be foreclosure res dispute. Virginia the contract foreclosure action court. a subsequently Id. Clark filed motion to law, required evidentiary of The sources stay dismiss or the federal proceedings damages, measures of and treat showings, action, pending the outcome of the state appeal ment on are also distinct for each stay Gannett filed a motion to abate or is, at part, claim. lien amount least in The proceedings. the state Id. The federal statute limited based on Nebraska and is district court Clark’s granted motion to The breach contract the NCLA. of stay the proceedings pursuant to the Colo- claim, hand, is on the other based on Mis rado River doctrine. abstention Id. at souri common law and entails the satisfac 740-41. tion five different Berra v. of elements. Builders, Inc.,
Papin 706 S.W.2d 73-74 reversed, The holding Fourth Circuit (outlining (Mo.Ct.App.1986) the five breach proceeding the state lien and the fed- elements). The contract difference in eral breach of contract action were not these claims highlighted recoveries for was parallel. at The court Id. 741-43. found Refrigeration in Preston Co. v. Omaha the federal contract action and the state Terminals, Storage Cold where the court lien action involved different with issues unpaid a “the said lien is cost of materials requisites proof. different Id. at 742. actually expended,” a labor while Further, the remedies were different as breach of contract action concerns the sought the state lien action foreclosure on a damages incurred as result of incomplete (here, property proceeds) the bond and the performance. Neb.App. 228, sought compensato- federal contract action (2007); see Sys. N.W.2d also Info. Thus, ry damages. Id. Corp. City City, & v. Networks Kansas contract action and the state lien action (8th Cir.1998) (address 147 F.3d parallel proceedings were not and Colora- ing damages). Finally, breach of Id.; apply. do River did not grounded equity, lien foreclosure is Beckley Mining Corp. see also New v. appeal tried to the court is re UMW, (4th Cir.1991) 1072, 1074 record, viewed de novo on the while the (holding federal actions not par- state and claim an breach of contract action at law purposes allel for Colorado River because presented jury which be and is eq- different —one was factually reviewed for clear error. Par remedies were Livingston, compensatory Inc. uitable Neb. and the other —and
537
Air,
the sources of law came from different
abundance of caution.” Controlled
states).
CI07319,
No.
answer and counterclaim at
So,
time,
point
2.
at that
in
the contract
sum,
In
lien
pro-
the state
foreclosure
action asserted
the Joint Venture
dispose
not
of the federal con-
ceeding will
was,
against Controlled Air
ostensibly,
law,
tract action and the sources of
reme-
pending
both the Nebraska court and
sought,
proof,
dies
elements of
review on
the federal district court for the Eastern
appeal,
giving
and events
rise to each
District of Missouri.8
Additionally,
cause of action are different.
event, however,
Air
Controlled
has never asserted the lien
This
did
trigger par-
claim in
foreclosure
the federal district
allelism between the proceedings pending
So,
foreclosure,
court.
as to the lien
there
principle
the two courts. The
cases
is neither similar claims nor similar
this circuit defining when actions become
parallel
purposes
both state and federal courts as re-
for abstention
are Scotts-
Thus,
quired
parallelism.
Industries,
for
Colorado dale Insurance Co. v. Detco
Inc.,
Cir.2005),
River was not available to the federal
the Joint Venture’s motion to dismiss the
L.Ed.2d
v.
Brillhart
Excess
claim,
America,
lien
the Joint Venture answered
Insurance Co.
316 U.S.
of
(1942),
Controlled Air’s lien foreclosure action in S.Ct.
539
erroneously
ka substantive law as
indi-
ment in the federal court will require
Also,
by the
court.
application
cated
federal
of federal
law. Otherwise
federal district court has little or no
though, state law will
in
apply
the feder
ignore
and,
discretion to
the Joint Venture’s
al court
in
the Nebraska forum
filing
claim,
choice of the federal forum for the
toas
the contract
it will be Mis
claim,
law,
of
its
even
the absence
souri
not that of Nebraska. And
presence
of a forum selection clause.
“the
of state law issues [in
weigh
will
court]
favor of ab
Finding Two:
only
stention
in rare circumstances.”
Allowing the federal action to continue
Corp.
Federated Rural Elec. Ins.
Ar
v.
piecemeal litigation.
would result in
kansas
Coops.,
Elec.
48 F.3d
Analysis:
piecemeal litigation
There will be no
in-
Finding Five:
volving
Litigating
the contract claim.
The state court can adequately protect
claim,
the hen foreclosure
if that is the
rights.
the Joint Venture’s
comparison being
made
the federal
finding,
require sepa-
will
Analysis:
rate,
piecemeal, litigation
and thus
it is true that
While
the Nebraska
jurisdiction, although joinder
either
of
adequately
court can
protect
the Joint
separate
possible
claims
un-
be
rights,
Venture’s
it can do so no more
der
of
Rule 18 the Federal Rules of Civil
efficiently than the federal district court.
Likewise,
Procedure.
there is no cer-
And, this factor
against
counts for or
court,
tainty that
the Nebraska
even
abstention
and dismissal
where
correctly applying
forum
se-
“one of the
inadequate
forums is
to pro
precedent,
lection
or
could would fail to
tect a party’s rights.”
Employees
Gov’t
enforce the contract’s Missouri forum
Simon,
Ins. Co. v.
917 F.2d
selection clause when faced with the is-
(8th Cir.1990) (emphasis in original)
sue
the contract claim.
S.,
(quoting Noonan
Inc.
County
v.
of
Finding Three:
Volusia,
(11th
Cir.
1988)). Thus,
The Nebraska court is a more conve-
this reason is no better
nient forum.
than an
push
even
for each forum and
certainly
provide
does not
an “exception
Analysis:
al
required by
circumstance” as
Colora
agreement
Given the contract
do River.
law,
apply Missouri
the Nebraska forum
Finding Six:
is at
incrementally
least
less convenient
And,
than the Missouri forum.
“mere
Priority
filing
the cases is neutral.
party
inconvenience to a
is an insuffi
Analysis:
cient basis to defeat an otherwise en
It may be true that “time of
forceable
forum selection
clause.”
filing” of the contract claim and the lien
Plumbing,
Servewell
tiffs choice
reasons, we reverse
foregoing
For the
Corp.,
Chem.
Mississippi
v.
for pro-
the district court
and remand to
Cir.1997).
Accordingly,
688, 695
opinion.
this
ceedings consistent with
the
retention of
clearly favors
this factor
court, the
by the federal
claim
contract
BYE,
concurring in the
Judge,
Circuit
the Joint Venture
which
chosen forum
part.
joining
result and
the dissent
contract claim.
first filed its
there has
summary, although
court’s decision to
In
I
the district
conclude
analysis
River
jurisdiction
Colorado
under
purported
exercising
been
from
abstain
by the
filings
of the
non-parallel
of
Dis-
Conservation
Colorado River Water
court,
under
court has never
the
States,
800,
district
v.
trict
United
pleadings
a review of the contract
taken
(1976),
was an
the district court’s decision to abstain un-
view the state and federal proceedings as
der the broad Wilton standard.
Id. at 797.
they
Thus,
originally
existed when
Royal
filed was
Indemnity,
es
the amended
complaint,
reasoning
state-court
sential to our
judgment
filed two months af-
and
ter
Royal
the federal
lawsuit
Indemnity
commenced and
binding
and is
on this
nine months
Passmore,
after the state lawsuit
panel.
(we
com-
See
Under approach, Beam’s the case, and the present the proceedings were Eighth panel Circuit in Royal Indemnity they not as existed when originally necessarily erred. As the state and feder- filed, they but became parallel before al the they suits existed when originally were filed, district court issued its Apex Oil was abstention order. party the common actions, Therefore, Judge approach to both which Beam’s involved different the policies. present insurers and different impermissibly ignores Id. at 791. case our re Apex Because Oil’s state against lawsuit cent in Royal decision Indemnity.12 "[wjhile Judge Royal Beam states that parties.” In- tween (quota- the same Ante at demnity might omitted). provide be read to a different opines tion He further that "en- time, forcement, strictly not, upon filing result based a it or of the contractual forum pro- otherwise demands that the state court selection procedur- clause was a federal court ceeding present must the governed by [to federal the al court] matter federal law” ... issues, law, [and][t]his, course, governed by same parallelism be- of "defeats un- have decisis, district court would the [ ] [federal] issues of stare Moving beyond which to abstain.” nothing River in favor of underlying Colorado principles adopting against Zoning Ap- Twp. counsel Bd. also Baskin v. Bath of deter- to approach filed” “originally peals, actions and federal state mine whether Thus, parallel proceedings of the existence “rest principles Those parallel. are to discretion triggers the district court’s judicial administra- of wise considerations under Colorado River. Under abstain ju- of conservation tion, regard to giving Beam, by Judge to de- approach advanced comprehensive dis- and resources dicial to abstain is whether its discretion termine River litigation.” Colorado position take a the district court must triggered, States, 424 Dist. v. United Conservation federal suits as of the state and snapshot L.Ed.2d 800, 817, originally filed. they existed when omitted). (1976) an- Put (quotation case, or If, present parties as “[allowing litigation way, other have simultaneously proceedings in federal and in the issues involved proceed ultimate- originally because courts is wasteful the suits were changed since actu- jurisdictions will ly only filed, pro- one of taking snapshot a then the case. Once one ally decide says they past in the ceedings as existed will be ruling, a the other court renders abstention will con- nothing about whether give obliged proceedings to halt its judicial promote com- serve resources Er- judicata to the decision.” res effect disposition litigation of the prehensive Chemerinsky, Federal Jurisdiction win Scottsdale, If, the future. as (5th ed.2007). Thus, River Colorado changed, have never then there and issues asks, its if the district court exercises taking snapshot no between difference now, it con- to abstain will discretion they in the as existed proceedings of the promote judicial serve resources taking snapshot proceed- of the past and litiga- comprehensive disposition currently snap- exist. The ings they tion in future? same, and the answer to the look the shots the same. inquiry is parallel proceedings parallel pro presence
The
*17
Therefore,
principles under-
light
applica
a
for the
ceedings
prerequisite
is
abstention,
only
it
because,
River
lying Colorado
River abstention
tion of Colorado
exists,
court to view
makes sense for the district
action
parallel
unless “a
state-court
law,
procedural
by
or federal
Indemnity precedent.” Id. at 538.
state substantive
Royal
der
view,
(“Be-
interpretation
the
my
Plumbing,
In
such
F.3d at 789
see Servewell
Indemnity
language
Royal
would
cited
from
enforceability of a forum selection
cause the
meaning.
If a
give
words unwarranted
those
law of
clause concerns both the substantive
procedur-
and federal
difference between state
venue,
procedural
and the
law
contracts
necessarily
governing
actions
al law
the two
disagreement among
cir-
there is some
few, if
parallelism, then there will be
defeats
ap-
or federal law
cuits over whether state
any,
River ab-
situations in which Colorado
adopt
yet to
a definitive
plies, and we have
procedural
permissible
all
stention is
because
we do so here
position on the issue. Nor must
governed
fed-
court are
matters in federal
omitted)); Ra-
...(quotation
and citations
Tompkins,
law. See Erie R.R. Co.
eral
(“we indulge
Café,
tion. case, circumstances
the uncontested of. matter of as a unsupportable is than obvious “it is more
law” and that jus- or circumstances [exceptional]
no such anal- any acceptable exist under
tifications action.” Id. causes of any of the
ysis of id., least,” that, very “at the I believe
540. court will so the district remand
we should the Joint to consider opportunity
have an counterclaim
Venture’s deciding whether ab-
breach of appropriate.
stention America, STATES
UNITED
Appellee, JONES, Appellant.
Ortez
No. 08-2851. Appeals, States Court
United
Eighth Circuit. 10, 2009. Feb.
Submitted: July
Filed:
