midpage
Projects
Sign in to see your projects.
170 So. 3d 186
La. Ct. App.
2015
Read the full case

Background

  • City contracted with F.G. Sullivan, Jr., Contractor in 2001 to widen Tiger Bend Road and install an underground drainage system; Sullivan subcontracted drainage to RCS.
  • Contract and DOTD directive provided for reimbursement of idle/standby equipment under a formula tied to Blue Book rates.
  • City represented utilities would be removed by April 1, 2001; undisclosed utilities remained in the ROW and caused repeated delays.
  • Sullivan claimed idle-equipment and increased-overhead damages (and sought RCS’s claimed losses); City paid principal contract but denied these additional sums.
  • At bench trial the court awarded Sullivan ~$957,736 (idle equipment + overhead) but denied RCS’s claimed costs; on appeal the court affirmed in part, reversed/calculated idle-equipment de novo, and modified the award to $187,432.04.

Issues

Issue Sullivan's Argument City of Baton Rouge's Argument Held
Trial continuance denial City needed more time because its damages expert (Daigle) was unavailable for health reasons Court erred by refusing continuance under La. C.C.P. art. 1602 Denial affirmed: City failed to show due diligence or provide medical proof; no abuse of discretion
Use of opposing expert's deposition at trial Deposition admissible because witness unavailable on cardiologist's advice and parties had stipulation Objection: no proof of unavailability, no subpoena, deposition was for discovery not trial Sustained: trial court did not abuse discretion; deposition excluded (no sufficient proof of unavailability; exceptional-circumstances argument fails)
Quantum of damages for idle equipment and overhead Sullivan relied on expert Myers calculating 303-day delay and detailed equipment list leading to large idle-equipment award; overhead computed pro rata City challenged Myers’s timing, methodology, and assumptions about which equipment was idle and when Court found Myers’s timing methodology unsound for idle equipment (de novo review): awarded idle-equipment for 54 items on 49 documented utility-delay days ($124,741.64); overhead award ($62,690.40) upheld as within trial court discretion
Recovery of subcontractor (RCS) costs via general contractor Sullivan sought to recover RCS’s claimed increased costs as part of Sullivan’s damages City argued RCS is not a party and Sullivan had no judicially imposed liability to RCS Denied: general contractor cannot recover subcontractor pass-through losses absent judicially imposed liability or other proof of obligation; trial court did not err

Key Cases Cited

  • Keller Construction Corporation v. George W. McCoy & Co., Inc., 119 So.2d 450 (La. 1960) (general contractor may recover subcontractor expenses only where contractor is judicially held liable or otherwise sustains the loss)
  • Hanks v. Entergy Corp., 944 So.2d 564 (La. 2006) (expert testimony credibility respected unless reasons are patently unsound)
  • Wooley v. Lucksinger, 61 So.3d 507 (La. 2011) (appellate de novo review appropriate where trial court relied on unsound expert opinion)
  • McCarty Corp. v. Industrial Scaffolding, Inc., 413 So.2d 1322 (La. App. 1 Cir. 1982) (overhead/indirect expenses need not be proved item-by-item; pro rata allocation accepted)
Read the full case

Case Details

Case Name: Sullivan v. City of Baton Rouge
Court Name: Louisiana Court of Appeal
Date Published: Jan 27, 2015
Citations: 170 So. 3d 186; 2015 La. App. LEXIS 87; 2015 WL 363439; No. 2014 CA 0964
Docket Number: No. 2014 CA 0964
Court Abbreviation: La. Ct. App.
Log In