midpage
Projects
Sign in to see your projects.
370 Or. 792
Or.
2023
Read the full case

Background

  • Idaho Power sought a site certificate from the Oregon Energy Facility Siting Council (EFSC) to build a ~300-mile Boardman-to-Hemingway high-voltage transmission line; ODOE managed the project order and EFSC held a contested case with public comment and hearings.
  • BLM completed an EIS and identified a Glass Hill route in Union County as the NEPA “environmentally preferable” alternative; Idaho Power removed Glass Hill from its final application for reasons including landowner and tribal concerns.
  • Over 50 commenters sought party status in the contested case; EFSC (via the hearing officer) granted many requestors only limited party status (including Stop B2H and Gilbert); Idaho Power remained the applicant-party of right.
  • The project’s corona noise was predicted to exceed DEQ noise rules under certain foul-weather conditions; Idaho Power requested an exception and a variance, which EFSC granted after finding EQC/DEQ had suspended processing such requests.
  • EFSC approved the site certificate subject to detailed mitigation, historic-properties management (HPMP) to be approved later by ODOE, visual-impact mitigation, and a General Condition about construction rights; petitioners Stop B2H, McAllister, and Gilbert sought judicial review.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Party status (Stop B2H, Gilbert) Agency had no authority to deny full party status on request; petitioners should be full parties. APA and EFSC rules authorize agency to limit participation and treat party requests as limited parties to keep proceedings manageable. EFSC lawfully granted limited-party status and considered required factors; no abuse of discretion.
Noise exception / variance (Stop B2H) EFSC lacked authority to grant exceptions/variances (only DEQ/EQC can); even if it had authority, criteria ("unusual or infrequent") not met. EFSC may act under the siting act when other agencies have suspended processing; evidence shows exceedances are infrequent (<2% of hours) and weather is beyond applicant control. EFSC had authority here and substantial evidence supports both the exception and variance.
Project-order modification of noise‑sensitive landowner radius (Stop B2H) ODOE could not change the rule’s one‑mile requirement to one‑half‑mile without rulemaking. Existing rule expressly permits project-order modifications or waivers for a specific facility. ODOE lawfully modified that requirement for this facility; no rulemaking required.
Visual‑impact methodology (Stop B2H) Idaho Power’s method failed to account for viewers’ subjective perceptions of significance. Methodology incorporated BLM and USFS subjective sensitivity/concern criteria; no particular method mandated by rule. EFSC permissibly used Idaho Power’s methodology; no legal error shown.
Inclusion of BLM’s Glass Hill alternative (McAllister) ORS 469.370(13) required EFSC/Idaho Power to include the NEPA “environmentally preferable” Glass Hill route in the application or order amendment. ORS 469.370(13) requires coordination and non‑duplication with federal review but does not mandate choosing federal NEPA-preferred alternatives. EFSC/Idaho Power were not required to include or adopt the NEPA-preferred Glass Hill route; coordination duty does not compel that result.
Historic properties mitigation and HPMP delegation (Gilbert) EFSC failed to document impacts/mitigation; improperly delegated future approval of HPMP to ODOE; improperly relied on federal standards. EFSC may delegate future review to ODOE under ORS 469.402; final order requires mitigation meeting state standards and ties federal Section 106 mitigation to state requirements. Delegation authorized; final order specifies impacted resources and mitigation and requires demonstration that any federal mitigation satisfies state standards.
General Condition 7 vs. mandatory rule (Gilbert) EFSC altered a mandatory site‑certificate condition without rulemaking. EFSC trimmed language to apply to transmission lines but did not substantively change the rule; typographical redline error was harmless. No substantive change; condition is consistent with the rule and rulemaking was not required.

Key Cases Cited

  • Marbet v. Portland Gen. Elec., 277 Or 447 (Or. 1977) (describing legislature’s centralization of siting authority in EFSC)
  • Friends of Columbia Gorge v. Energy Fac. Siting Coun., 368 Or 123 (Or. 2021) (interpreting agency limits on participatory rights in contested cases)
  • Don’t Waste Oregon Com. v. Energy Facility Siting, 320 Or 132 (Or. 1994) (review standard for agency rule interpretation)
  • Teledyne Wah Chang v. Energy Fac. Siting Council, 298 Or 240 (Or. 1984) (limits on EFSC altering the site proposed in the application)
  • Save Our Rural Oregon v. Energy Facility Siting, 339 Or 353 (Or. 2005) (standard of review for EFSC final orders)
  • Robertson v. Methow Valley Citizens Council, 490 U.S. 332 (U.S. 1989) (NEPA requires process, not particular substantive outcomes)
Read the full case

Case Details

Case Name: Stop B2H Coalition v. Dept. of Energy
Court Name: Oregon Supreme Court
Date Published: Mar 9, 2023
Citations: 370 Or. 792; S069919
Docket Number: S069919
Court Abbreviation: Or.
Log In