MARBET, Petitioner, v. PORTLAND GENERAL ELECTRIC COMPANY et al, Respondents.
(CA 4727, SC 24630)
Supreme Court of Oregon
Argued October 6, 1976, reargued January 6, reversed and remanded March 3, 1977
petition for rehearing denied March 29, 1977
561 P2d 154
Argued October 6, 1976, reargued January 6, reversed and remanded March 3, petition for rehearing denied March 29, 1977
W. Michael Gillette, Solicitor General, Salem, argued the cause for respondent Energy Facility Siting Council. With him on the brief were Lee Johnson, Attorney General, and Richard M. Sandvik, Assistant Attorney General, Salem.
David N. Hobson of Phillips, Coughlin, Buell, Stoloff & Black, Portland, argued the cause for respondent Portland General Electric Company.
Before Denecke, Chief Justice, Holman, Tongue, Bryson, Lent, Linde, and Bradshaw, Justices.
Bryson, J., dissenting opinion.
LINDE, J.
Since 1971, construction of facilities for the production and transmission of energy has required a site certificate from the state. This case is the first contested proceeding under the energy facility siting act, now
The statutory scheme
After enactment of the original statute, Oregon Laws 1971, ch 609, no facilities covered by the act could be constructed or expanded without a certificate executed by the Governor upon the recommendation of a Nuclear and Thermal Energy Council composed of the Public Utility Commissioner, the State Engineer, the State Health Officer, the Director of the Department of Environmental Quality, and five “public members” appointed by the Governor. In 1975, in legislation revising the state‘s energy laws and creating a Department of Energy, the terms and coverage of the facility siting law were amended in some respects, and the Nuclear and Thermal Energy Council was replaced by a new Energy Facility Siting Council composed only of seven public members. Oregon Laws 1975, ch 606.
The statute expressly directs the council to exercise some of its functions by rules or regulations.
A central question concerns the standards to be used by the council in reaching a certification decision. The key section on the site certification process,
The proceedings
PGE filed its statutory notice of intent to apply for a site certificate in December 1972 and its application in December 1973, followed by amendments in May and July of 1974. The notice of intent and the application were circulated to other agencies for their comments, as required by
After prehearing conferences to identify contested issues, a hearing examiner held hearings on PGE‘s application in November, 1974, in Arlington and Portland. Thereafter the parties were invited to submit findings, conclusions, and proposed terms for the site certificate, and to reply to such submissions. On April 11, 1975, the council adopted its order, accompanied by findings and conclusions, recommending to the Governor approval of a site certificate for PGE‘s Pebble Springs project under the terms, warranties, and conditions of a site certificate agreement accompanying the order. One member of the council dissented on the ground that serious problems of the disposal of spent nuclear fuel remain unresolved.
The intervenors, Marbet and Christiansen, obtained review of the order in the Court of Appeals. In a cross-petition, PGE raised objections to the council‘s admission of intervenors as parties to the proceedings. While the case was before the Court of Appeals but after the statutory deadline for agency withdrawal of an order for reconsideration,
Status of the parties
Since the council‘s order resulted from a contested case,
“(1) Any person adversely affected or aggrieved by any order or any party to an agency proceeding is entitled to judicial review of a final order, ...”
The statute provides two distinct bases of standing entitling one to judicial review of an agency decision. Any party to the agency proceeding, which includes any person in fact named or admitted as such by the agency,
Neither the issue of standing under the administrative procedure act nor the issue of intervention under the energy facility siting act depends on generalizations of administrative law. Both issues have been resolved by the legislature.
As to intervention,
“(2) The council may, by proper order, permit any person to become a party complainant or defendant by intervention who appears to have an interest in the results of the hearing or who represents a public interest in such results....”
The statute thus gives no greater procedural weight to an intervenor‘s personal self-interest than to an inter-
The text does not support PGE‘s contention that by “a public interest,” the legislature meant only an organized interest group. The difficulties with such a restriction appear in this case. Mr. Marbet in fact stated that he represented an “organization” consisting of himself and one other person, which he calls “Forelaws on Board,” and also Coalition for Safe Power, which he described as a group of people who meet to discuss energy questions. Inquiry into how and how far these groups authorized his testimony proved unenlightening. But nothing of legal importance hinges on the widespread practice of presenting viewpoints on public policy under some banner embroidered for the occasion.
Nor does the statute support PGE‘s contention that the “public interest” is restricted geographically. Communities in immediate proximity to a proposed site have economic and other reasons to desire or to oppose a project that differ from the interests of a wider public, as the hearing in this case shows.1 Representation of these interests is hardly limited to residency in Gilliam County. To the contrary, the statute calls for consideration of some local factors in setting construction and operating standards, e.g. the uses of “adjacent areas,”
What matters under the quoted statute is that the interest the intervenor proposes to represent, if not a merely personal one, be an interest shared by a significant part of the public or one to be considered an element in the over-all public interest. The statute leaves the agency discretion to determine whether an intervenor is qualified to represent such a public interest. It does not assume expertise or organizational backing, but neither does it open a contested case hearing to all comers. Much depends on the nature of the issues and on the presence of other qualified parties representing the same public interest. To avoid redundancy, the agency may choose to require intervenors to join in one presentation or to address separate aspects of the public interest as long as the effect is not to exclude an asserted public interest altogether. Something like this was done in the interventions of Marbet and Christiansen in these proceedings. They accepted the restrictions on their testimony and cross-examination, and we find here no abuse of discretion by imposing conditions over an intervenor‘s protests.
It does not follow that each intervenor has standing to seek judicial review only of issues arising from his individual intervention. Such a rule could preclude a person who intervenes from securing review of the legality of the final order2 on issues that the agency in fact decided on someone else‘s initiative. No rule compels that result. See, e.g., Hennesey v. SEC, 285 F2d 511, 515 (3d Cir 1961).
An invariable requirement that judicial review must be limited to objections first made to the agency is foreclosed in any event by the present text of
The council‘s duty to “establish standards”
The most important issue is whether the council failed to establish the standards required by
Unlike other administrative law decisions discussing the issue, this case does not present the question whether an agency has been empowered to reach individual decisions directly under the terms of its authorizing statute without articulating any intermediate standards.6 The energy facility siting act expressly directs the council to set its own standards refining the statutory policies.
“(3) Establish standards and promulgate rules that applicants for site certificates must meet including, but not limited to, standards of financial ability and qualifications as to ability to construct and operate the energy facility to which the site certificate applies and prescribe the form.”
Similarly,
Miles v. City of Eugene, 252 Or 528, 451 P2d 59 (1969), and a port, Carruthers v. Port of Astoria, 249 Or 329, 438 P2d 725 (1968), without questioning whether the party entitled to review had first presented its objections to the agencies.
In Oregon Newspaper Publishers Assoc. v. Peterson, 244 Or 116, 415 P2d 21 (1966), plaintiffs were allowed to challenge a regulation of the Board of Pharmacy addressed not to them but to pharmacists. The court was concerned about plaintiffs’ standing and the “ripeness” of the issue for judicial review, but nothing in the opinion turns on whether plaintiffs’ arguments were first made to the Pharmacy Board. This decision was cited as a prominent source of the 1971 revision of
There is thus no doubt that the council is directed to exercise its own judgment in setting standards beyond the policies stated in the statute itself, though of course consistent with those policies. It is less clear that the statute directs the council invariably to set these standards by rulemaking in advance of a specific site certification proceeding. When compared with another section of the same statute that unambiguously directs the council to “adopt safety standards promulgated as rules for the operation of all thermal power plants and nuclear installations . . .,”
However, the directive to the council gains meaning from the functions served by agency-formulated
If the council chooses in this fashion to move from general over-all standards to more specific ones bearing on the proposed facility and site, it must be able to do so after the initiation of the proceeding. The procedure for adopting a standard to be applied in a few complex, large-scale decisions such as the site certifications entrusted to the council is not necessarily the same as that chosen to state precise rules for numerous or frequently recurring situations. The Oregon Administrative Procedure Act (APA), like most, is
The choice of one or the other procedure has important consequences. In adopting a policy or standard as an agency “rule,” the agency is not bound to facts or arguments in the record of the rulemaking proceeding.
This sharp division between procedures for setting standards and procedures for applying them creates widely-recognized difficulties in contemporary administrative law. On the one hand, regulatory standards often rest on scientific, technical, or economic assumptions and probabilities that escape testing in a rulemaking proceeding.8 On the other hand, the adjudication procedure of a contested case offers neither prior notice nor a familiar form of participation to persons who wish to address the policy premises of a decision apart from the facts of a concrete case.9 The difficulty of separating the standards of decision from the specific facts is exacerbated when the standards are to govern relatively few, complex, and factually diverse cases. However, we think they can be managed within the energy facility siting act.
The act gives the council wide discretion over many facets of the construction of energy facilities. Like
much agency discretion, it includes judgments of two kinds: judgments about technological feasibility, economic projections, costs, safety, environmental consequences, and similar probabilities that will call for factual information and agency expertise, and judgments about the relative importance of conflicting goals, about values and priorities, in short, policy judgments. With respect to matters on which the statute itself expresses a policy, its directive to the council to adopt standards calls for the factual kind of judgment and procedures appropriate thereto. But where the statute entrusts choices between alternate policies to the agency, its directive to adopt standards calls for agency articulation of these choices, and the procedures for public participation take the place of the legislative forum.It is these latter, policymaking choices that particularly demand procedures open to the assertion of viewpoints beyond those of the applicant and the agency staff. We may take notice, for purposes of illustration only, that since this case was argued the council has been holding widely-publicized and widely-attended rulemaking hearings on the relationship between nuclear waste disposal and future construction of nuclear power plants. Under the APA, as we have said, this is the normal way to set policy standards in advance of their application in a concrete case. But it is not the only way. It is not indispensable that every standard under
The council‘s standards and findings
The council did purport to adopt some standards as rules in advance of its Pebble Springs proceeding. But it phrased these rules mostly as demands for information that an applicant must supply. OAR 345-25-001 to 345-25-049. In 1975, the council issued rules addressed to holders of site certificates. OAR 345-26-005 to 345-26-200. These rules are stated to carry out
1. Financial ability. This is one of the standards for applicants mandated by
“345-25-047 APPLICANT‘S FINANCIAL ABILITY. The application shall provide information sufficient to demonstrate the financial qualifications of the applicant to construct and operate the plant. Such information
shall show that the applicant possesses or has reasonable assurance of obtaining the funds necessary to cover estimated construction costs, operating costs for the design lifetime of the plant, including related fuel cycle costs, and the estimated costs of permanently shutting the facility down and maintaining it in a safe condition.”
The rule is stated as a demand for information to be included in the application. Respondents also rely on additional such requirements as further “standards” bearing on financial ability.11 But a demand for information does not tell an applicant, the staff representing the agency, any other party, or the hearing officer what conclusion the information is required to prove. It provides no verbal yardstick against which the evidence is to be measured. A demand for information standing alone is not a “standard.”
In the council‘s quoted rule 345-25-047, however, the demand does not stand alone. The rule requires an applicant to show access to funds necessary to build the proposed plant, to operate it over its useful life, and to shut it down and maintain it in a safe condition. As a “standard,” it is minimal and could well be made more informative.12 But although the reference to
Petitioner further challenges the absence of a finding that the applicant has the requisite financial ability. If the rule quoted above states a standard “that applicants for site certificates must meet,” then an order in a contested case requires a finding of ultimate fact that the applicant has (or has not) demonstrated the financial ability to do everything required by the standard and a “statement of the underlying facts supporting the findings.”
2. Qualifications to construct and operate. A second standard mandated by
PGE argues that a standard of operating qualifications can be deduced from another council rule, OAR 345-26-015(4), which requires site certificate holders to comply with federal requirements for operating a nuclear facility. From this PGE would apparently infer a council decision to establish ability to comply with the regulations of the federal Nuclear Regulatory Commission as the council‘s only standard of qualifications under
3. Power needs. Under
The council found as an ultimate fact that PGE‘S customers will need the power from the project by 1984-86. When the council determines that a factual predicate is important to its conclusion on one of the issues entrusted to it, as the council apparently did with respect to power needs, the issue must be identifiable and the finding of ultimate fact supported by underlying facts. It is not clear whether the council equated “need” with “demand.” The statement of underlying facts refers to PGE forecasts of demand for its power and certain studies made by its staff and by the Public Utility Commissioner. These procedural recitals are not proper findings of fact by the council itself and do not elucidate the ultimate finding. In the 1975 energy legislation which reorganized the council and created the Department of Energy, the legislature did not equate “need” and “demand.” See
4. Other findings. Petitioner contends that many of the commission‘s “findings” are only recitals of evidence and not proper findings as required by law. The criticism is well taken.18 This court has repeatedly emphasized the importance of clear findings both of “ultimate facts” and of “underlying facts” as required by
Conclusion
The council acted within its powers in admitting petitioner as a party to its proceeding. Under
The order reflects an erroneous reading of the energy facility siting act in important respects. The council has established only a minimal standard on financial ability and none on ability to construct and operate the proposed facility. Instead it misread the eight statutory factors which
Because of our disposition of this case, we do not reach other issues raised by the parties. We are persuaded that the energy facility siting act is not per se preempted by federal regulation of nuclear power plants, and indeed, PGE here is defending a decision under the act, not attacking it. If and when an applicant claims that a particular denial or condition imposed by the council is preempted will be soon enough to examine that claim. Nor do we anticipate what the council may do about petitioner‘s additional objections upon further consideration of such standards as it may establish in the light of this decision.
Similarly, we need not consider whether the Court of Appeals should have heeded the council‘s motion for a remand or whether the council could have initiated
We have no wish to impose unnecessary delay on proceedings that are inherently time-consuming. We are equally sensible that decisions on plans for constructing huge and costly physical installations, such as highways, dams, or power plants, create a momentum that is difficult to halt or reverse at later stages in the process. This is not a private lawsuit between petitioner and the applicant. It is a proceeding to review whether an agency has made a decision of great public importance in accordance with the directives of the people‘s representatives.
Our present remand does not require the council to stop and start over. We have indicated that the statute does not mandate all standards to be established before a site certification is initiated. They may be stated and refined in the course of the proceeding. The council has the choice of procedures suggested in the opinion. After refining its standards, the council can make such revised findings as may be pertinent under its standards and the statute, based upon the existing record and whatever additional evidence those criteria require. With these safeguards, the council‘s decision on recommending for or against a site certificate will come as close to being well-considered and reasonable as the statutory procedure can bring it.
Reversed and remanded.
BRYSON, J., dissenting.
It is reasonable to conclude that petitioner Marbet‘s right to challenge, through judicial review, the Energy Facility Siting Council‘s (Council) final order is limited to the scope of his intervention; that the Court of Appeals usurped the Council‘s function when it affirmatively appears that petitioner Marbet failed to present such contentions regarding standards to the Council, and the court nevertheless undertook to rule upon the sufficiency of the rules and standards pro-
The result of the majority opinion is that notwithstanding over four years of investigation and study by the Council, still more private and public money must be spent for additional administrative hearings and proceedings before ruling upon Portland General Electric Company‘s (PGE) request for a power plant site permit on the “Pebble Springs” project. These additional sums of money are eventually paid by the energy consumers in the rate structure and in additional taxes.
The majority concludes that this further expenditure of time and money is mandated by the Council‘s failure to promulgate standards sufficient to satisfy
Petitioner Marbet was an intervening party in the proceedings before the Council. The Council properly
“A. Conditions imposed upon Intervenor Marbet—
“(1) Intervenor Marbet may cross-examine and give testimony only on the following subject matters:
“(a) The long-handling and storage of the high level radioactive wastes generated by the proposed plans;
“(b) Possible dangers to the public health, safety and welfare associated with military attacks on nuclear power plants;
“(c) The environmental consequences of radioactive emissions from the plant;
“(d) The propriety of ‘banking’ sites for the construction of nuclear power plants at some indefinite date in the future.
“* * * * *”2
Basically, petitioner, in his appearance before the Council, addressed himself to issues of nuclear safety and nuclear waste disposal technology and made no attempt to concern himself with the administrative standards that the Council had or had not adopted. Petitioner Marbet expressly consented to the limitation placed upon his participation. He derives his standing to seek judicial review from
“(1) Any person may appear personally or by counsel to present testimony in any hearing before the council on any application for a site certificate.
“(2) The council may, by proper order, permit any person to become a party complainant or defendant by intervention who appears to have an interest in the results of the hearing or who represents a public interest in such results. However, the request for intervention must be made before the final taking of evidence in the hearing.
“(3) Any person authorized to intervene in the hearing on a site certificate may appeal the council‘s recom-
mendation in the manner prescribed in ORS chapter 183. Such recommendation shall be deemed a final order for purposes of such appeal. [Formerly 453.375]”
“(1) Any person adversely affected or aggrieved by an order or any party to an agency proceeding is entitled to judicial review of a final order * * * ”
The legislature has chosen to open participation in site licensing procedures to anyone who has an interest in the results of the hearing or who “represents a public interest in such results.” However, there is nothing to indicate any intent on the part of the legislature to permit a limited intervenor to judicially challenge the Council‘s final order on a ground which is neither related to that raised by petitioner‘s intervention nor made an issue before the Council.
Contrary to the majority‘s contentions, there is nothing incongruous about the fact that persons “adversely affected or aggrieved” may challenge the Council‘s final order where that person has neither participated in the contested case nor raised its contentions before the agency while a limited intervenor cannot. Even if the APA did not provide such a right to persons adversely affected or aggrieved, these persons would still have the right to judicially challenge an administrative final order.3 However, it is apparent
It is logical to conclude that the legislature, in facilitating input by persons representing particular public interests and viewpoints, did not intend to grant those individuals the right to protest Council actions unrelated to the purpose of their intervention or to the special interest they represent. To hold otherwise would be to grant standing to contest every aspect of the Council‘s order to individuals not possessing the proximity of interests required to qualify for standing as a person adversely affected or aggrieved and whose only participation before the Council has been on a
Petitioner Marbet has made no showing of any interest which would qualify him as a person adversely affected or aggrieved. Regardless of any special competency he might possess to serve as a spokesman for the public interest on matters of health and safety, Marbet has no greater personal interest in the Council‘s final order than does any other resident of Oregon or, for that matter, of the Pacific Northwest.
The majority‘s argument that his limited participation before the Council makes him a person aggrieved is without basis. By the same rationale, any party to the administrative proceedings should be given the right to appeal issues to the court not raised previously before the administrative agency. This clearly is not the law.
As demonstrated by the above paragraph, this statutory construction issue concerning the scope of the right to appeal granted to limited intervenors is closely related to the policy considerations involved in the doctrine of exhaustion and the procedural rule that, with a few exceptions not relevant here,5 issues
In United States v. L. A. Tucker Truck Lines, 344 US 33, 37, 73 S Ct 67, 97 L Ed 54 (1952), the court noted that:
“* * * Simple fairness to those who are engaged in the tasks of administration, and to litigants, requires as a general rule that courts should not topple over administrative decisions unless the administrative body not only has erred but has erred against objection made at the time appropriate under its practice.”
Three policy rationales support the rule that parties air their objections first before the agency.
(1) Danger that the proceedings before the agency would be reduced to a preliminary bout, preparatory for the main event, the role of agencies might be reduced to that of takers of evidence.
(2) Presumption that if all arguments are fairly and fully presented before the agency, it will in most cases reach the correct result.
(3) Energies of the reviewing court should not be dissipated in considering points that might never be raised on appeal, if they had been properly presented to the agency.
See 2 Cooper, State Administrative Law at 597. See also Jaffe, Judicial Control of Administrative Action 452 (1965).
“* * * In addition, the [Council] staff served upon all parties, including petitioners, the proposed findings of fact, order and site certificate and an opportunity was given to the parties to file objections thereto. Petitioners did not avail themselves of the opportunity to object to the proposed findings of fact, order or site certificate.”
Having failed to take advantage of this opportunity to protest the proposed findings, it should follow from what has been discussed above that petititioner Marbet should be foreclosed to contest their adequacy before this court.
In his petition for review to this court, petitioner emphasizes, “We are not lawyers in this proceeding but laymen forced to represent our own interests.” He argues that it would do the public a great disservice to limit his appeal to the issues on which he intervened and to which he addressed himself before the Council. But there is more than one “public interest” to be preserved here.
The public also has an interest in efficient and
It must be admitted that this court is not schooled in the sciences of nuclear and thermal energy. We do know from common experience that learned scientists and engineers are still arguing their respective positions before the people competent to decide what will be the ultimate outcome on nuclear and thermal energy. With this in mind, the courts should exercise
The “standards” to be set by the Council will continue to fluctuate in this complex field of science. The courts, by necessity, must give way to the criteria set by the Council which in itself could fluctuate within a relative short span of time as more knowledge is gained in the field of energy production. The legislative scheme seems to have contemplated this very problem and placed an unusual amount of authority in the Council.
The legislature has adopted statutory safeguards to protect the public health and safety.
The Court of Appeals correctly held in Marbet that:
“It is a well-recognized rule of administrative law that a ‘reviewing court usurps the agency‘s function when it sets aside the administrative determination upon a ground not heretofore presented’ to the agency, thereby depriving the agency of an opportunity to consider the matter. Neeley v. Compensation Department, 246 Or 522, 524-25, 426 P2d 460 (1967); Stanbery v. Smith, 233 Or 24, 32-33, 377 P2d 8 (1962); see also 3 Davis, Administrative Law Treatise, § 20.06 (1958); Easton Utilities Commission v. Atomic Energy Commission, supra, 424 F2d at 851-52.” 25 Or App 469, 477 (1976).
However, the Court of Appeals chose to then ignore
The present state of the law on this subject, by whom and on what grounds the Council‘s orders may be attacked, is an open invitation to future delay and confusion. There is no finality on which the government or its governed may rely with any degree of security. With this in mind, the legislature may desire to reconsider the provisions of
