midpage
Projects
Sign in to see your projects.
2020 Ohio 184
Ohio Ct. App.
2020
Read the full case

Background

  • Main Event contracted with Omni to build an entertainment facility; Omni subcontracted work to Sterling (concrete) and Western Reserve (cleaning/finishing).
  • Contracts between Omni and Sterling and between Omni and Western Reserve contained identical Article 21 arbitration clauses requiring binding arbitration for disputes between those contracting parties.
  • Omni abandoned the project, ceased operations, could not be located, and defaulted in related litigation; Main Event obtained a default judgment against Omni.
  • Sterling and Western Reserve sued Main Event (unjust enrichment/quantum meruit) and Omni (breach). Main Event moved to stay those proceedings pending arbitration under the subcontract arbitration clauses.
  • The trial court denied Main Event’s motion to stay; the appellate court consolidated Main Event’s appeals and affirmed.
  • The court reasoned Omni waived arbitration by defaulting and Main Event—being a non-party to the subcontract arbitration clauses—lacked standing to compel or enforce those arbitration agreements; the request for frivolous-conduct sanctions was denied without a trial-court hearing.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Whether proceedings must be stayed pending arbitration under Omni–subcontractor agreements Sterling/Western Reserve: arbitration clause applies only to disputes between them and Omni; Main Event not a party Main Event: arbitration clause should stay all claims related to the project Denied stay: arbitration clause binds Omni and its subcontractors, not Main Event; Main Event lacks standing to enforce it
Whether Omni’s default waived its right to arbitrate Sterling/Western Reserve: Omni could still demand arbitration if it chose Main Event: Omni’s default and failure to participate do not preclude arbitration enforcement by Main Event Court: Omni’s default equates to waiver of proceeding with arbitration (Omni failed to assert arbitration)
Whether a non-party (Main Event) may compel arbitration between other contracting parties Sterling/Western Reserve: only an aggrieved party to the arbitration agreement may demand arbitration Main Event: as a current litigation party, it can seek stay/enforcement Court: a third party generally cannot be bound by or enforce an arbitration agreement to which it is not a party; Main Event lacks standing
Whether Main Event’s motion and appeal constituted frivolous conduct warranting sanctions Sterling/Western Reserve: Main Event knew Omni had defaulted/dissolved and thus motions/appeal were frivolous Main Event: pursued a legitimate procedural remedy Court: denied sanctions on appeal; required trial-court motion and statutorily mandated hearing before sanctions could be imposed

Key Cases Cited

  • Taylor Bldg. Corp. of Am. v. Benfield, 884 N.E.2d 12 (Ohio 2008) (strong presumption favoring arbitration; resolve doubts for arbitration)
  • Hayes v. Oakridge Home, 908 N.E.2d 408 (Ohio 2009) (doubts about arbitrability resolved in favor of arbitration)
  • Maestle v. Best Buy Co., 800 N.E.2d 7 (Ohio 2003) (distinguishing motions to compel arbitration and motions to stay proceedings)
  • Blakemore v. Blakemore, 450 N.E.2d 1140 (Ohio 1983) (abuse-of-discretion standard defined)
  • Featherstone v. Merrill Lynch, Pierce, Fenner & Smith, Inc., 822 N.E.2d 841 (Ohio App. 2004) (if a dispute arguably falls within arbitration clause, trial court must stay proceedings)
Read the full case

Case Details

Case Name: Sterling Contracting, L.L.C. v. Main Event Entertainment, L.P.
Court Name: Ohio Court of Appeals
Date Published: Jan 23, 2020
Citations: 2020 Ohio 184; 108186 & 108187
Docket Number: 108186 & 108187
Court Abbreviation: Ohio Ct. App.
Log In
    Sterling Contracting, L.L.C. v. Main Event Entertainment, L.P., 2020 Ohio 184