History
  • No items yet
midpage
State of Ohio Dept. of Dev. v. Matrix Centennial, L.L.C.
2014 Ohio 3251
Ohio Ct. App.
2014
Read the full case

Background

  • Matrix Centennial, LLC received a $2.5 million Job Ready Site grant from the Ohio Department of Development (ODOD) to build a 90,000 sq ft office building at 1492 Rockwell Avenue; ODOD disbursed $755,920.22.
  • The Grant Agreement had a project completion date (amended) of December 18, 2010; Matrix missed the deadline and sought an additional extension in Nov. 2010 which ODOD did not approve.
  • ODOD sued (Feb. 2012) for breach of contract and unjust enrichment and sought return of the $755,920.22 already paid.
  • Both parties moved for summary judgment; the trial court denied Matrix’s motion, granted ODOD’s, and awarded repayment plus potential collection costs under R.C. 131.02; Matrix appealed.
  • The appellate court reviewed de novo and affirmed: it held the Grant Agreement was a valid contract, Matrix breached it, the repayment/liquidated-damages clause was enforceable, economic conditions did not excuse performance, and future collection costs may be assessed under R.C. 131.02.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Whether the grant instrument is an enforceable contract ODOD: instrument is a contract; ODOD performed by disbursing funds and secured statutory benefit Matrix: agreement was gratuitous; lack of consideration Held: Contract valid — consideration exists (ODOD obtained statutory program benefit)
Whether Matrix breached and is liable to repay funds ODOD: Matrix failed to complete project by deadline; clause permits repayment of all or part of funds Matrix: failure due to recession/financing made performance impossible Held: Breach established; economic downturn not a legal impossibility; repayment allowed
Enforceability/amount of repayment clause (liquidated damages) ODOD: paragraph 15 authorizes recovery up to full amount disbursed Matrix: ODOD’s decision to claw back full amount is unreasonable/ambiguous Held: Repayment provision is clear and enforceable; ODOD may recover up to $755,920.22
Award and specification of collection costs under R.C. 131.02 and timeliness of ODOD’s filing ODOD: statute allows attorney general to assess collection costs after certification; trial court need not quantify now; filing delay was excusable neglect Matrix: trial court failed to specify collection costs (no final order) and ODOD did not plead collection costs; ODOD’s summary-judgment filing was untimely Held: Final appealable order exists despite future assessable collection costs; R.C. 131.02 costs need not be pled as claim in court; trial court did not abuse discretion in allowing late filing (excusable neglect)

Key Cases Cited

  • Kostelnik v. Helper, 96 Ohio St.3d 1 (contract elements and consideration)
  • Samson Sales, Inc. v. Honeywell, Inc., 12 Ohio St.3d 27 (liquidated damages/enforceability)
  • Dresher v. Burt, 75 Ohio St.3d 280 (summary judgment burden-shifting)
  • Grafton v. Ohio Edison Co., 77 Ohio St.3d 102 (de novo review of summary judgment)
  • State ex rel. Lindenschmidt v. Butler Cty. Bd. of Commrs., 72 Ohio St.3d 464 (excusable neglect standard for late filings)
  • Blakemore v. Blakemore, 5 Ohio St.3d 217 (abuse of discretion standard)
Read the full case

Case Details

Case Name: State of Ohio Dept. of Dev. v. Matrix Centennial, L.L.C.
Court Name: Ohio Court of Appeals
Date Published: Jul 24, 2014
Citation: 2014 Ohio 3251
Docket Number: 14AP-47
Court Abbreviation: Ohio Ct. App.