History
  • No items yet
midpage
270 F. Supp. 3d 1088
D.S.D.
2017
Read the full case

Background

  • BHSU contracted with GSE to install an artificial turf system over an 8-inch, 8% by volume cement‑stabilized deck at Lyle Hare Field; GSE’s proposal and contract contemplated cement stabilization as the base.
  • GSE directed soil testing; FMG performed limited tests and reported results, but did not perform a mix design or extensive geotechnical analysis for cement stabilization. FMG had no prior cement‑stabilization experience.
  • GSE subcontracted Midstate to broadcast and mix cement into the soil (Midstate performed the broadcast/mix but did not perform mix‑design, coring, or geotechnical testing). GSE instructed Midstate to use the 8"/8% specification.
  • Soft spots/divots developed after installation. GSE attempted multiple repairs and entered an Amendment in May 2014 to regrade and repair the field in exchange for final payments; BHSU paid after a grading consultant (not a geotechnical engineer) approved the regrade.
  • Experts retained by BHSU (Rettner and Smith) concluded the cement stabilization failed due to unsuitable/plastic/organic soils and insufficient cement mix; they recommended removal and replacement with granular base. Court found recurring divots, extensive repairs over years, and continued field limitations.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Breach of contract (Count I) BHSU: GSE failed to provide the contract‑specified cement‑stabilized deck, a field meeting specs, and a functioning drainage system; damages to be determined. GSE: Denies breach; contends Amendment and subsequent work satisfied obligations; warranty governs repairs. Court: Grant summary judgment for BHSU — GSE breached the contract.
Accord and satisfaction / Amendment effect BHSU: Amendment was to cure GSE’s prior nonperformance, not to accept something different; no accord. GSE: Amendment was an accord extinguishing prior obligations once satisfied (grading approval, payments). Court: No accord; Amendment required performance to original specs and did not extinguish prior claim.
Express warranty / warranty as exclusive remedy BHSU: Warranty never became effective because BHSU never accepted a finished field; warranty does not bar other claims. GSE: Warranty (upon acceptance/first use) was BHSU’s exclusive remedy; BHSU failed to follow warranty claims. Court: Warranty never took effect; GSE cannot rely on it as exclusive remedy.
Implied covenant of good faith (Count II) BHSU: GSE’s failures and failure to disclose testing concerns prevented BHSU from receiving contract benefits. GSE: South Dakota doesn’t recognize independent tort; seeks summary judgment. Court: Claim allowed as contract‑based (not independent tort); factual issues remain — summary judgment denied to GSE.
Implied warranty of fitness for a particular purpose (Count III) BHSU: GSE held itself out as expert; implied warranty that work would be fit for intended purpose; warranty disclaimer inapplicable because express warranty never triggered. GSE: Contract is a services/ construction contract (not UCC goods); express warranty disclaimer precludes implied warranty. Court: Denied GSE summary judgment; implied warranty claim may proceed.
Rescission (Count IV) BHSU: Defective base defeats contract’s objective; seeks rescission due to substantial failure. GSE: BHSU derived benefit (used field for seasons); adequate remedy at law; rescission inequitable. Court: Grant summary judgment for GSE — rescission denied with prejudice.
Third‑party claims against Midstate (indemnity/contribution) GSE: Midstate negligently failed to advise unsuitability; agent noticed problems and should have warned GSE. Midstate: Duties limited to subcontract terms; no independent duty beyond contract; excluded mix design/testing. Court: Midstate owed no independent legal duty; grant summary judgment for Midstate (third‑party claims dismissed).
Third‑party claims against FMG (professional negligence/contribution) GSE: FMG should have warned that additional testing/mix design was needed; FMG’s proposal expressly tied tests to cement‑stabilization decision. FMG: Performed limited testing as contracted; methodology/results are unchallenged; no duty beyond tests. Court: Genuine factual dispute whether FMG owed broader professional advice; FMG’s motion denied.

Key Cases Cited

  • Anderson v. Liberty Lobby, 477 U.S. 242 (summary judgment standard and genuine issue inquiry)
  • Celotex Corp. v. Catrett, 477 U.S. 317 (summary judgment burden allocation)
  • Matsushita Elec. Indus. Co. v. Zenith Radio Corp., 475 U.S. 574 (view facts in light most favorable to nonmoving party)
  • Shady Grove Orthopedic Assocs. v. Allstate Ins. Co., 559 U.S. 393 (choice‑of‑law: federal courts apply state substantive law in diversity)
  • Mid‑Western Elec., Inc. v. DeWild Grant Reckert & Assocs. Co., 500 N.W.2d 250 (S.D. 1993) (professional negligence duty assessed by foreseeability beyond privity)
  • Fisher Sand & Gravel Co. v. State, 558 N.W.2d 864 (S.D. 1997) (duties arising from contract normally govern; tort duty must be independent of contract)
  • Waggoner v. Midwestern Dev., Inc., 154 N.W.2d 803 (S.D. 1967) (implied warranty of workmanship/fitness in construction contracts)
Read the full case

Case Details

Case Name: South Dakota Board of Regents ex rel. Black Hills State University v. Global Synthetics Environmental, LLC
Court Name: District Court, D. South Dakota
Date Published: Sep 15, 2017
Citations: 270 F. Supp. 3d 1088; CIV. 15-5003-JLV
Docket Number: CIV. 15-5003-JLV
Court Abbreviation: D.S.D.
Log In
    South Dakota Board of Regents ex rel. Black Hills State University v. Global Synthetics Environmental, LLC, 270 F. Supp. 3d 1088