History
  • No items yet
midpage
Sloan Construction Company, Inc. v. Southco Grassing, Inc.
395 S.C. 164
S.C.
2011
Read the full case

Background

  • SCDOT contracted in 2000 with Southco Grassing for highway maintenance in Greenville, SC, with a performance bond and a payment bond issued by Amwest Insurance Company as surety, totaling 100% of the contract value.
  • Sloan Construction entered into a subcontract with Southco on July 28, 2001, and performed all work; Amwest was later adjudged insolvent and its bonds were cancelled.
  • A Nebraska court approved a distribution plan allocating about 40% of each claim to bond claimants; Amwest bond claims were curtailed by liquidation proceedings begun in 2001 and approved in 2009.
  • Southco failed to replace the cancelled Amwest bond after being notified by SCDOT in July 2001; Sloan submitted its final bill on October 31, 2001, which Southco did not pay.
  • Sloan notified SCDOT in 2002 of the payment failure; Southco’s principal Wanda Surrett claimed all payments were made in March 2003, while SCDOT later verified contract completion and dispersed final retainage to Southco.
  • Sloan sued Southco, Surrett, SCDOT, and Greer State Bank; Amwest was not named as a defendant; the circuit court dismissed claims against SCDOT for lack of private right of action under SPPA, an outcome reversed on Sloan I remand for liability assessment.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Duty to maintain bond under SPPA Sloan argues SPPA creates a continuing duty to maintain a valid bond and a private right against the government for failure to do so. SCDOT contends there is no continuing duty to maintain the bond once issued. No continuing duty to maintain bond by government entities.
Mitigation of damages Sloan contends Sloan acted in a manner consistent with mitigating damages and should not be offset by reliance on Amwest liquidation. SCDOT argues Sloan failed to mitigate by not pursuing Amwest claims to collect against the liquidator. SCDOT did not meet its burden to show Sloan failed to mitigate; circuit court affirmed.

Key Cases Cited

  • Sloan Construction Co. v. Southco Grassing, Inc., 377 S.C. 108 (2008) (held SPPA creates a private right of action against a governmental entity for failure to ensure proper bonding; law of the case)
  • Barnes & Sweeney Enters., Inc. v. City of Hazel Park, 169 Mich.App. 422 (1988) (no duty on city to maintain bond validity for subcontractors)
  • Flori Corp. v. Yellow Rose Development & Construction, Inc., 911 P.2d 546 (Ariz.App.1995) (no duty on city to continuously ensure a viable bond)
  • DeKalb County v. J & A Pipeline Co., 263 Ga. 645 (1993) (no continuing duty on governmental entity to maintain bond)
  • Med. Clinic Bd. of the City of Birmingham-Crestwood v. E.E. Smelley, 408 So.2d 1203 (Ala.1981) (liability for failing to require a bond varies by statute)
Read the full case

Case Details

Case Name: Sloan Construction Company, Inc. v. Southco Grassing, Inc.
Court Name: Supreme Court of South Carolina
Date Published: Oct 31, 2011
Citation: 395 S.C. 164
Docket Number: 27061
Court Abbreviation: S.C.