OPINION
Defendant City of Tucson contracted with defendant Yellow Rose Development & Construction, Inc., for certain improvements on Speedway Boulevard. Yellow Rose posted payment and performance bonds, obtained from Pacific States Casualty Co., pursuant to A.R.S. § 34-222. In mid-April 1993, one of Yellow Rose’s subcontractors notified Tucson that it had not been paid, and also reported that another subcontractor might not have been paid. Shortly thereafter, the inquiring subcontractor learned that Pacific States was in a court-ordered conservatorship in California. The city was informed of this development. After learning of these facts the city made two progress payments to Yellow Rose, the last being on May 10, 1993. Thereafter Pacific States went into liquidation and the City terminated its contract with Yellow Rose. Its contract with another to complete the project cost it substantially more than the original contract price with Yellow Rose. This suit was brought by a number of sub
Both the plaintiffs and the City had their expectations defeated in this case. Plaintiffs expected Yellow Rose to pay its bills. The City expected Yellow Rose to complete its contract. Yellow Rose’s failures caused both plaintiffs and the City damages. Normally, those damages could be recovered from the company issuing performance and payment bonds. Again, expectations were defeated by the financial insolvency of the bonding company. This is undoubtedly an unhappy situation for all involved. We do not believe, however, that plaintiffs’ unhappiness permits a shift of their losses to the City.
It is argued that the City owed a duty to subcontractors to insure that a payment bond was always in effect from a financially secure surety. We join most other courts in rejecting that claim. The provision of A.R.S. § 34-222 that a contractor “shall furnish” a payment bond imposes a duty on the contractor, not on the city employing the contractor. See Hardaway Co. v. United States Army Corps of Engineers,
Pointing to the provision of the contract between the City and Yellow Rose that permits the City to require additional security for paying subcontractors if the initial bond becomes unacceptable, plaintiffs contend that they may sue as third-party beneficiaries of that provision. Because the provision is permissive, it can hardly be construed as imposing a contractual duty on the City to require such additional security. There being no breach of contract by the City, no action against it lies. Moreover, there is no evidence that had such security been requested it would have been forthcoming.
Finally, it is argued that plaintiffs should have an “equitable lien” on those sums of money that were the subject of two progress payments after the City had knowledge of some nonpayment of subcontractors by Yellow Rose and the financial insolvency of Pacific States, those sums that were owed Yellow Rose but not paid, and that sum representing contract retention to insure full performance. Permitting a recovery on this theory is supported by Kennedy Electric Co. v. United States Postal Service,
Affirmed.
