History
  • No items yet
midpage
Skanska USA Building, Inc. v. Zurich American Insurance Company
1:24-cv-12607
D. Mass.
May 19, 2025
Read the full case

Background

  • Skanska USA Building, Inc. was the construction manager for a new high school and middle school in Belmont, Massachusetts, under a contract with the Town of Belmont.
  • Skanska constructed a geothermal HVAC system for the project; during the project, a coupling failed in July 2021, leading to the release of water-glycol and air entrapment in the system, resulting in ongoing repairs and damages.
  • Zurich American Insurance Company issued a Completed Value Builders Risk Policy for the project, naming the Town of Belmont as insured, that included various deductibles and limitations for defective work claims.
  • Skanska (or the Town, on its behalf) submitted a $600,735 claim to Zurich for repair and remediation of the HVAC system breakdown and related issues.
  • Zurich partially denied coverage, citing deductibles and exclusions, and argued the claim was untimely based on the policy’s suit limitations clause.
  • Skanska filed suit for declaratory judgment, breach of contract, and breach as third-party beneficiary; Zurich removed the case to federal court and moved to dismiss based on purported untimeliness of the suit.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Applicability of Mass. Gen. Laws ch. 175, § 99 to policy § 99 does not apply because the policy is a builder’s risk policy, not a standard fire policy § 99 applies, making the policy’s two-year limitation provision enforceable § 99 does not apply to this builder's risk policy
Validity of suit limitation clause under Mass. Gen. Laws ch. 175, § 22 The policy’s limitation clause is void under § 22 because it starts the clock at loss, not denial of claim The suit is time-barred because it was filed more than two years after the loss commenced, as the policy requires The limitations clause is void and unenforceable under § 22; clock runs from denial of claim
Timeliness of Skanska’s action Claim accrues at time of Zurich’s denial (Feb 13, 2024); suit filed timely Claim accrues at time of loss (July 7, 2021); suit filed too late Suit is timely, claim accrual is at denial of claim
Reasonableness of policy’s shortened limitations period Shortening statute of limitations to less than two years from accrual violates public policy and is barred Shortened limitations period is permissible and contractually agreed The limitations period is not reasonable or valid; policy provision unenforceable

Key Cases Cited

  • Bell Atl. Corp. v. Twombly, 550 U.S. 544 (plausibility pleading standard for motions to dismiss)
  • Ashcroft v. Iqbal, 556 U.S. 662 (plausibility pleading and factual content required to state a claim)
  • Riverdale Mills Corp. v. Fireman's Fund Ins. Co., 123 F. Supp. 2d 37 (property insurance in Massachusetts must adhere to § 99 standard form)
  • Gabelli v. S.E.C., 568 U.S. 442 (claims generally accrue when the plaintiff has a complete and present cause of action)
  • Foisy v. Royal Maccabees Life Ins. Co., 356 F.3d 141 (under Massachusetts law, contract claims generally accrue at breach)
  • Goldsmith v. Reliance Ins. Co., 353 Mass. 99 (limitations selected by parties to insurance policy must comply with statutes and public policy)
Read the full case

Case Details

Case Name: Skanska USA Building, Inc. v. Zurich American Insurance Company
Court Name: District Court, D. Massachusetts
Date Published: May 19, 2025
Docket Number: 1:24-cv-12607
Court Abbreviation: D. Mass.