History
  • No items yet
midpage
888 F.3d 906
8th Cir.
2018
Read the full case

Background

  • Merlyn Drake built a road across land adjacent to Enemy Swim Lake (1998–2009), obtaining multiple Corps CWA verifications: farm-road exemptions and nationwide-permit determinations.
  • The Sisseton‑Wahpeton Oyate Tribe owns most of the lake shoreline, uses the lake for cultural/ceremonial purposes, and asserted Drake misrepresented his intent (development vs. agriculture).
  • The Tribe repeatedly protested to the Corps (meetings in 2005, calls in 2004 and 2007, meeting in 2009) and sent a March 2010 letter asking the Corps to recapture the exemptions, require removal of the road, and impose penalties.
  • The Corps responded in August 2010, affirming its earlier exemption/permit decisions and declining enforcement action; the Tribe sued (2011) under the APA, CWA, and NHPA.
  • The district court dismissed most claims on grounds including finality/timeliness, non‑justiciability of enforcement decisions, and lack of entitlement to equitable tolling; it remanded only the NHPA issue as to the 2009 nationwide permit.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Whether the Corps' Aug. 30, 2010 letter was a final agency action for challenging prior permit/exemption determinations The 2010 letter consummated and finalized earlier decisions, so the Tribe’s challenges are timely against that final action The underlying verification letters issued earlier were the final agency actions; the 2010 letter merely restated earlier positions and caused no new legal consequences 2010 letter is not a final agency action; earlier verification letters were final when issued (Tribe’s attempt to reset the limitations clock fails)
Whether the recapture claim (forcing Corps to treat project as no longer exempt) is justiciable Corps lawfully misapplied recapture and the Corps must be ordered to enforce the CWA against Drake Corps has prosecutorial/enforcement discretion; decisions not to enforce are committed to agency discretion and not reviewable Recapture claim is a nonjusticiable enforcement action; dismissal affirmed
Whether Tribe’s challenges to 1998–2003 permits were time‑barred and whether equitable tolling applies Tribe argued accrual occurred later (e.g., 2008) and equitable tolling should apply (or §2401(a) is nonjurisdictional following Kwai Fun Wong) Tribe knew or should have known by Jan. 25, 2005; no extraordinary circumstances justify tolling; even if §2401(a) tollable, Tribe not entitled to equitable tolling Claims arising from permits discussed by Jan. 25, 2005 are time‑barred; Tribe not entitled to equitable tolling; those counts affirmed dismissed
Whether the Corps unlawfully "stacked" exemptions/permits (2009 Nationwide Permit 14 not a single and complete project) Drake’s multiple verifications made the 2009 Nationwide Permit part of a larger phased project and thus not a single and complete project Corps’ interpretation treats separate crossings of the same waterbody at separate/distant locations as separate single-and-complete projects; Corps’ linear-project rule allows phased separate crossings Court defers to Corps’ interpretation (Auer); the 2009 permit qualified as a single and complete project; stacking claim dismissed

Key Cases Cited

  • Bennett v. Spear, 520 U.S. 154 (agency action is final only when it marks consummation of decisionmaking and determines rights/obligations)
  • Heckler v. Chaney, 470 U.S. 821 (agency refusal to enforce is presumptively unreviewable prosecutorial discretion)
  • Auer v. Robbins, 519 U.S. 452 (deference to agency interpretations of its own regulations unless plainly erroneous)
  • Hawkes Co. v. U.S. Army Corps of Eng’rs, 782 F.3d 994 (8th Cir. 2015) (agency letters may be final if they inflict legal consequences; used here to analyze finality)
  • Irwin v. Department of Veterans Affairs, 498 U.S. 89 (presumption that statutes of limitations are subject to equitable tolling absent contrary congressional intent)
  • Dubois v. Thomas, 820 F.2d 943 (8th Cir. 1987) (discretionary enforcement under CWA not judicially compellable)
Read the full case

Case Details

Case Name: Sisseton-Wahpeton Oyate of the Lake Traverse Reservation v. U.S. Corps of Eng'rs
Court Name: Court of Appeals for the Eighth Circuit
Date Published: Apr 25, 2018
Citations: 888 F.3d 906; 16-4283
Docket Number: 16-4283
Court Abbreviation: 8th Cir.
Log In