History
  • No items yet
midpage
898 F.3d 383
4th Cir.
2018
Read the full case

Background

  • Mountain Valley Pipeline (MVP) proposed a ~303-mile, 42-inch interstate natural gas pipeline crossing ~106 miles in Virginia, requiring 385 stream and 144 wetland crossings across steep, landslide-prone terrain.
  • MVP obtained a FERC certificate (Oct. 2017) and sought Corps authorization under CWA §404 (NWP 12). Virginia DEQ/State Water Control Board reviewed Section 401 certification under the Clean Water Act.
  • DEQ issued an initial April 2017 401 certification for Corps/NWP 12-covered crossings, then developed a 2017 Guidance Document to evaluate upland (non-jurisdictional) construction impacts and requested supplemental information from MVP.
  • After extensive information exchanges, public comment, site-specific plan requirements, and added monitoring/mitigation conditions, DEQ and the Board issued a December 2017 Section 401 certification imposing additional conditions addressing upland impacts and monitoring.
  • Environmental petitioners challenged the December 401 certification in this court, arguing DEQ’s reasonable-assurance determination was arbitrary and capricious and that DEQ failed to consider cumulative impacts of upland activities plus NWP 12-covered crossings.
  • The Fourth Circuit considered standing, standard of review, and whether DEQ’s reliance on existing regulatory frameworks, monitoring, and adaptive enforcement sufficed as ‘‘reasonable assurance’’ under §401.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Standing to challenge state §401 certification Petitioners: December 401 caused concrete injury to water/uses; vacatur would redress by enabling stricter conditions or denial Respondents/MVP: Injury caused by FERC authorization; vacatur may not lead to ultimate relief so redressability lacking Court: Petitioners have Article III standing; realistic possibility of redress exists (Townes framework)
Standard of review for state §401 action Petitioners: review under arbitrary-and-capricious standard (APA) Respondents: argue state-law/substantial-evidence standard might apply but concede outcome same Court: applied arbitrary-and-capricious review and deferred to agency expertise
Whether DEQ lacked basis for finding "reasonable assurance" (antidegradation/Tier 2/3) Petitioners: DEQ relied improperly on EPA/general permits and non-site-specific analyses; monitoring and future approvals insufficient DEQ/MVP: relied on AS&S, VESC/VSM equivalence to Construction General Permit, site-specific AS&S, monitoring, adaptive enforcement, and FERC/Corps conditions Court: DEQ's predictive, monitoring-based reasonable-assurance determination was not arbitrary or capricious; reliance on established programs and adaptive measures was reasonable
Whether DEQ improperly segmented review (separating NWP 12 impacts from upland impacts) Petitioners: DEQ failed to consider combined/cumulative effects of upland activities plus stream/wetland crossings Respondents: DEQ integrated prior NWP 12 analysis and intended April and December certificates to operate together; monitoring addresses cumulative risk Court: Segmentation was not arbitrary; DEQ considered NWP 12 impacts in its supplemental review and relied on combined conditions and monitoring

Key Cases Cited

  • PUD No. 1 of Jefferson Cty. v. Washington Dep’t of Ecology, 511 U.S. 700 (1994) (states’ §401 authority and role in conditioning federal permits)
  • Baltimore Gas & Elec. Co. v. NRDC, 462 U.S. 87 (1983) (deference to agencies on complex factual predictions)
  • AES Sparrows Point LNG, LLC v. Wilson, 589 F.3d 721 (4th Cir. 2009) (Clean Water Act §404 and Corps permitting context)
  • Crutchfield v. County of Hanover, Va., 325 F.3d 211 (4th Cir. 2003) (nationwide permits and Corps verification)
  • Townes v. Jarvis, 577 F.3d 543 (4th Cir. 2009) (standing/redressability framework where court relief is antecedent to agency action)
  • Spokeo, Inc. v. Robins, 136 S. Ct. 1540 (2016) (Article III injury-in-fact requirements)
  • American Rivers, Inc. v. FERC, 129 F.3d 99 (2d Cir. 1997) (Section 401 conditions become binding on federal licenses)
Read the full case

Case Details

Case Name: Sierra Club v. State Water Control Board
Court Name: Court of Appeals for the Fourth Circuit
Date Published: Aug 1, 2018
Citations: 898 F.3d 383; 17-2406; 17-2433
Docket Number: 17-2406; 17-2433
Court Abbreviation: 4th Cir.
Log In
    Sierra Club v. State Water Control Board, 898 F.3d 383