American Rivers, Inc., and the State of Vermont v. Federal Energy Regulatory Commission, Green Mountain Power and Trout Unlimited, IntervenorsAmerican Rivers, Inc., and the State of Vermont v. Federal Energy Regulatory Commission, Green Mountain Power and Trout Unlimited, Intervenors
Petitioners, the State of Vermont and American Rivers, Inc., seek review of several orders issued by the Federal Energy Regulatory Commission (“FERC” or “Commission”) licensing six hydropower projects located on rivers within the State of Vermont. The dispute surrounds (1) the authority of the State under § 401 of the Clean Water Act
I. BACKGROUND
A. The Licensing Proceedings and the Statutory Scheme
The principal order under review in this proceeding arises from the efforts of the Tunbridge Mill Corporation (“Tunbridge”) to obtain a license from FERC for the operation of a small hydroelectric facility on the First Branch of the White River in Orange County, Vermont, restoring an historic mill site in Tunbridge Village. Pursuant to § 401(a)(1) of the CWA,
set forth any effluent limitations and other limitations, and monitoring requirements necessary to assure that any applicant for a Federal license or permit will comply with any applicable effluent limitations and other limitations, under section 1311 or 1312 of this title, standard of performance under section 1316 of this title, or prohibition, effluent standard, or pretreatment standard under section 1317 of this title, and with any other appropriate requirement of State law set forth in such certification ....
The CWA further provides that the state certification “shall become a condition on any Federal license or permit subject to the provisions of this section.” Id.
On October 15, 1990, Tunbridge petitioned the responsiblе state agency, Vermont’s Agency of Natural Resources (‘VANR”), for certification of the project.
See
As issued, the certification contained eighteen conditions (designated by letters “A” through “R”), three of which, P, J, and L, are relevant for our purposes. Condition P reserves the right in Vermont to amend (or “reopen”) the certification when appropriate.
1
Condition J requires Tunbridge to submit to the state for review and approval any plans for significant changes to the project.
2
Finally, condition L requires Tunbridge to seek clearance from the state before commencing
Certificate in hand, Tunbridge sought a license from FERC, which is vested with authority under § 4(e) of the Federal Power Act (“FPA”),
On July 15, 1994, FERC entered its Order Issuing License in which the Commission granted Tunbridge a 40-year license “to construct, operate, and maintain the Tunbridge Mill Project.” However, reversing the Commission’s longstanding policy that review of the appropriateness of § 401 conditions is solely within the purview of state courts, see, e.g., Town of Summersville, 60 Fed. Energy Reg. Comm’n Rep. (CCH) ¶ 61,291, at 61,990 (1992), Carex Hydro, 52 Fed. Energy Reg. Comm’n Rep. (CCH) ¶ 61,216 at 61,769 (1990), Central Maine Power Co., 52 Fed. Energy Reg. Comm’n Rep. (CCH) ¶ 61,033 at 61,172 (1990), FERC found that conditions P, J, and L were beyond the scope of Vermont’s authority under the CWA. Accordingly, FERC refused to incorporate them into the Tunbridge license.
The State of Vermont and American Rivers filed motions to intervene and petitions for rehearing in mid-August 1994, challenging the authority of FERC to review and reject state-imposed § 401 conditions. 4 By ordеr of May 17, 1996, the Commission granted the motions to intervene and denied the motions for rehearing, elaborating on the rationale for its decision to reject the conditions. Vermont and American Rivers now seek review in this court of the Commission’s determination in appeals numbered 96-4110 and 96-4112.
During the period Tunbridge was seeking certification and licensure, on November 13, 1992, intervenor, Green Mountain Power Corporation (“GMP”), sought Vermont’s certification of its Essex No. 19 project, a 7.2-megawatt facility on the Winooski River, a tributary of Lake Champlain, located in the townships of Essex Junction and Williston, Vermont. VANR issued a draft certification for notice and comment on September 3, 1993. After holding a hearing and obtaining written comments, VANR issued a final § 401 certificate on November 8, 1993, which was later amended on January 1, 1995. GMP did not seek review of the certification decision, аnd the decision became final on January 15, 1995.
As issued, the § 401 certificate contained twenty conditions (denominated letters “A” through “T”), several of which, B, E, H, K, M, N, S, and T, are relevant to this case.. In condition T, Vermont reserves the right to reopen the certification when appropriate, in language somewhat different from the reo-pener condition included in the Tunbridge certification.
5
Condition S requires GMP, in
On December 26, 1991, while awaiting state certification, GMP' applied for a license from FERC to operate the Essex No. 19 hydroelectric project. On March 30, 1995, the Commission, by “Order Issuing New License,” granted GMP a 30-year license. Relying largely on its reasoning in Tunbridge Mill, 68 Fed. Energy Reg. Comm’n Rep. (CCH) ¶ 61,078 (1994), the Commission found that several conditions — conditions T and S and aspects of conditions B, E, H, K, M, and N, discussed earlier — were beyond the scope of Vermont’s authority under the CWA. See Green Mountain Power Corp., 70 Fed. Energy Reg. Comm’n Rep. (CCH) ¶ 62,205 at 64,435-38 (1995). Accordingly, FERC refused to incorporate the suspect provisions into the license. The State of Vermont, already having intervеned in the proceeding, petitioned for rehearing on April 27, 1995, again challenging the authority of FERC to review and reject state-imposed § 401 conditions. By order of June 3, 1996, the Commission denied the state’s motion for rehearing, elaborating on the rationale for its decision to reject the conditions. Green Mountain Power Corp., 75 Fed. Energy Reg. Comm’n Rep. (CCH) ¶ 61,250 (1996). Vermont seeks review of the Commission’s determination in appeal number 96-4116.
Finally, during a similar time frame, the Central Vermont Public Service Corp. (“CVPS”), also sought certification in connection with their efforts to relicense four small hydroelectric facilities on the Passumpsic River near the town of St. Johnsbury, Vermont: the 0.7 megawatt Passumpsic Hydroelectric Project; the 0.25 megawatt Pierce
The certifications for the four projects contained between sixteen and nineteen conditions. As with the other certifications at issue in this case, VANR imposed conditions with which FERC took exception. Although FERC granted 40-year licenses for each of CVPS’s projects by orders issued December 8,1994, the Commission rejected three conditions and a portion of a fourth contained in each of the four licenses, relying on the rationale of Tunbridge Mill, 68 Fed. Energy Reg. Comm’n Rep. (CCH) ¶ 61,078 (1994). See Central Vermont Pub. Serv. Corp., 69 Fed. Energy Reg. Comm’n Rep. (CCH) ¶¶ 62,197; 62,198; 62,199; 62,200 (1994), reh’g denied, 75 Fed. Energy Reg. Comm’n Rep. (CCH) ¶ 61,263 (1996). One such condition required CVPS to seek approval from the state for any proposal for maintenance or repair of the project involving the river. 14 Another required CVPS to seek approval from the state for any proposed changes in the operation of the project. 15 A third reserved to the state the right to request FERC to reopen the license to consider any modification necessary for compliance with state water quality standards. 16 Finally, the Commission rejected a portion of a condition that required CVPS to construct facilities for upstream fish passage within two years of being ordered to do so by the state. 17
Already having intervened in the licensing proceedings, the State of Vermont moved for rehearing, again contesting the authority of FERC to reject states’ § 401 conditions. By order of June 4, 1996, the Commission denied Vermont’s motion for rehearing. See Central Vermont Pub. Serv. Corp., 75 Fed. Energy Reg. Comm’n Rep. (CCH) ¶ 61,263 (1996). The state seeks review of the Commission’s determination in appeal number 96-4118.
B. The Commission’s Decisions
Prior to
Tunbridge Mill,
68 Fed. Energy Reg. Comm’n Rep. (CCH) ¶ 61,078 (1994), FERC had held that it was required by § 401 to include in its licenses all conditions imposed by a state in its certifications notwithstanding the Commission’s view that the
We believe that these conditions are beyond the scope of Section 401, and that states should not use their water quality certification authority to impose conditions that are unrelated to water quality. However, since pursuant to Section 401(d) of the Clean Water Act all of the conditions in the water quality certification must become conditions in the license, review of the appropriateness of the conditions is within the purview of state courts and not the Commission. The only alternatives available to the Commission are either to issue a license with the conditions included or to deny [the] application, and we do not believe it is in the public interest to deny the application.
60 Fed. Energy Reg. Comm’n Rep. (CCH) ¶ 61,291 at 61,990. The Environmental Protection Agency (“EPA”), the Federal agency vested with the authority to administer and implement the CWA, continues to share this view.
See
In Tunbridge Mill, however, the Commission reversed field, finding that “[t]o the extent that states include conditions that are unrelated to water quality, these conditions are beyond the scope of Section 401 and are thus unlawful.” 68 Fed. Energy Reg. Comm’n Rep. (CCH) ¶ 61,078 at 61,387. The Cоmmission continued, “We conclude that we have the authority to determine that such conditions do not become terms and conditions of the licenses we issue.” Id. The Commission reasoned, in part: “We believe that, in light of Congress’ determination that the Commission should have the paramount role in hydropower licensing process, whether certain state conditions are outside the scope of Section 401(d) is a federal question to be answered by the Commission.” Id. In its decision denying petitioners’ motion for rehearing, the Commission elaborated on its prior ruling. See Tunbridge Mill, 75 Fed. Energy Reg. Comm’n Rep. (CCH) ¶ 61,175 (1996).
In the other licensing decisions, the Commission relied on its reasoning in Tunbridge Mill in finding that “states may, under Section 401(d) of the CWA, impose conditions related solely to water quality.” Green Mountain Power Corp., 70 Fed. Energy Reg. Comm’n Rep. (CCH) ¶ 62,205 at 64,435 (1995), reh’g denied, 75 Fed. Energy Reg. Comm’n Rep. (CCH) ¶ 61,250 (1996); Central Vermont Pub. Serv. Corp., 69 Fed. Energy Reg. Comm’n Rep. (CCH) ¶¶ 62,197; 62,198; 62,199; 62,200 (1994), reh’g denied, 75 Fed. Energy Reg. Comm’n Rep. (CCH) ¶ 61,263 (1996). Petitioners contest the Commission’s expansion of its authority.
II. DISCUSSION
The principal dispute between petitioners and the Commission in this case surrounds the relative scope of authority of the states and the Commission under the CWA and the FPA. Petitioners’ contention is straightforward, resting on statutory language. In their view, the plain language of § 401(d) indicates that FERC has no authority to review and reject the substance of a state certification or the conditions contained therein and must incorporate into its licenses the conditions as they appear in state certifications. FERC disagrees, arguing that the language of § 401(d) is not as clear as petitioners would have it. Rather, FERC contends, it is bound to accede only to those conditions that are within a state’s authority under § 401, that is, conditions that are rea
A. The Clean Water Act
Before considering the Commission’s contentions regarding the CWA, we note that FERC’s interpretation of § 401, or any other provision of the CWA, receives no judicial deference under the doctrine of
Chevron USA, Inc. v. Natural Resources Defense Council,
We begin, as we must, with the statute itself. In this case, the statutory language is clear. Section 401(a), which is directed both to prospective licensees and to the federal licensing agency (in this ease, the Commission), provides, in relevant part:
Any applicant for a Federal license or permit to conduct any activity ... which may result in any discharge into the navigable waters, shall provide the licensing or permitting agency a certification from the State in which the discharge originates or will originate.... No license or permit shall be granted until the certification required by this section has been obtained or has been waived.... No license or permit shall be granted if certification has been denied by the State....
Any certification provided under this section ... shall become a condition on any Federal license or permit subject to the provisions of-this section.
The Commission argues that, notwithstanding the mandatory language of the provision, § 401(d) itself restricts the substantive authority of states to impose conditions: “Section 401 authorizes states to impose only conditions that relate to water quality.”
Tunbridge Mill,
68 Fed. Energy’ Reg. Comm’n (CCH) ¶ 61,078 at 61,387. This is plainly true. Section 401(d), reasonably read in light of its purpose, restricts conditions that states can impose to those affecting water quality in one manner or another.
See P.U.D. No. 1 of Jefferson County,
In addition to § 401(d), the Commission relies on several other provisions of the CWA in arguing that it has the authority to review and reject state-imposed conditions that are deemed by the Commission to exceed a
Section 401(a)(3) establishes a presumption that a state’s § 401 certification obtained in order to procure a federal construction permit — for instance, a dredge-and-fill permit issued by the Army Corps of Engineers pursuant to § 404 of the CWA,
Beyond the statutory language of § 401, the Commission relies primarily on the decision of the Court of Appeals for the District of Columbia Circuit in
Keating v. Federal Energy Regulatory Comm’n,
In Keating an individual obtained a permit from the Army Corps of Engineers to build a dam. Because the project’s construction would result in a discharge into navigable waters within the State of California, Keating sought and received from California a § 401 certification permitting construction to go forward. Id. at 619. Following the construction of a dam — but prior to its licensure for operation — the state purported to withdraw its certification without paying heed to the requirements of § 401(a)(3), and FERC withheld its license to operate the completed facility on this basis. The prospective licensee sought review.
Keating
addresses the narrow question of the Commission’s authority to determine whether a valid § 401 certificate exists prior to issuing its license.
Escondido Mut. Water Co. v. La Jolla, Rincon, San Pasqual, Pauma & Pala Band of Mission Indians,
Although
Escondido
arose in a different context, it is instructive in this case for several reasons. In both contexts, FERC is required in clear statutory language to incorporate conditions imposed by an independent governmental agency with special expertise, in
Escondido,
the Department of the Interior,
Finally, and most persuasively, in both cases the Commission argued that without the authority to review conditions imposed by the certifying agency its ability to carry out its statutory mission would be compromised. In
Escondido,
notwithstanding this contention, the Supreme Court found that absent a challenge by the applicant-licensee, the Interior Secretary’s conditions must either be incorporated'in full into any license that it issues or the Commission must deny the license altogether.
We note that in the unlikely event that none of the parties to the licensing proceeding seeks review, the conditions will go into effect notwithstanding the Commission’s objection to them since the Commission is not аuthorized to seek review of its own decisions. The possibility that this might occur does not, however, dissuade us from interpreting the statute in accordance with its plain meaning. Congress apparently decided that if no party was interested in the differences between the Commission and the Secretary, the dispute would best be resolved in a nonjudicial forum.
Id.
The Commission’s efforts to distinguish
Escondido
are unavailing. FERC’s principal contention relies on a portion of
Escondido
that has no bearing on this case. The Supreme Court — in addition to concluding that the Commission has no authority to reject conditions imposed by the Secretary under § 4(e) of the FPA,
This rather unremarkable holding does not support the Commission’s contention that it may review and reject
any
state-imposed condition that it finds to be violative of
B. The Federal Power Act
Independent of FERC’s concerns that Vermont’s
We have no quarrel with the Commission’s assertion that the FPA represents a congressional intention to establish “a broad federal role in the development and licensing of hydroelectric power.”
California v. Federal Energy Regulatory Comm’n,
The Commission fails to acknowledge appropriately its ability to protect its mandate from incursion by exercising the authority to refuse to issue a hydropower license altogether if the Commission concludes that a license, as conditioned, sufficiently impairs its authority under the FPA.
See, e.g., Escondido,
The Commission, however, has chosen to forgo this route, arguing that refusing to issue a license is not a “practical option” in relicensing cases, such as CVPS.
Id.
at 20 n. 10. Although we understand that refusing to relicense a hydroelectric project would result in the disassembly of the project, presenting “serious practical and economic problems” and affecting all manner of local interests, id, the Commission’s dissatisfaction with the remedy, of license denial is not reason enough to turn a blind eye to FERC’s assumption of authority to review and reject a state’s
Finally, with respect to the ECPA amendments to the FPA, the Commission is mistaken. Under these provisions, the Commission
The Commission’s claim that the CWA — as we construe it — and the ECPA amendments are incompatible must be rejected. The Commission’s concern that states will hold the Commission hostage through the
III. CONCLUSION
We have considered the Commission’s remaining arguments and find them to be without merit. For the foregoing reasons, we grant the petition for review, vacate the orders of the Commission, and remand for proceedings consistent with this opinion.
Notes
. Condition P reads, in full: “The Department is reserving the right to add and alter terms and conditions as appropriate to'carry out its responsibilities during the life of the project with respect to water quality.”
. Condition J reads, in full: "Any significant changes to the project, including project operation, must be submitted to the Department for prior review and written approval.”
.Condition L reads, in full:
No construction may commence until after the Department has issued written approval under Conditions B, C, D, and J and until Fish and Wildlife has issued written approval undеr Condition E. Operation changes made after project completion are subject to Condition I and must be approved prior to effecting the change.
Conditions B and C address minimum water flow and plans for monitoring water flow; condition D addresses erosion control; condition E addresses plans for a downstream fish passage; and condition I addresses procedures for desilt-ing the dam's impoundment area.
. Any review of a FERC order before a court of appeals must be preceded by a rehearing petition before the agency.
See,
. Condition T reads, in full: “The Department may request, at any time, that FERC reopen the license to considеr modifications to the license necessary to assure compliance with Vermont Water Quality Standards.”
. Condition S reads, in full: "Any change to the project that would have a significant or material effect .on the findings, conclusions, or conditions of this certification, including project operation, must be submitted to the Department for prior review and written approval.”
. Condition M provides, in full: "Any proposals for project maintenance or repair work involving the river, including desilting of the dam impoundment, impoundment drawdowns to facilitate repair/maintenance work, and tailrace dredging, shall be filed with the Department for prior review and approval.”
. Condition K provides, in pertinent part:
The applicant shall submit a plan for downstream fish passage to the Department of Fish and Wildlife for review. Downstream passage shall be provided 24 hours per day, April 1— June 15 and September 15 — December 15 and shall be functional at all operating impoundment levels, with the period subject to adjustment based on knowledge gained about migration periods for migratory salmonoids. Downstream fish passage facilities shall be installed so as to be operational in the spring of 1996....
. Condition N requires, in relevant part, that "[t]he applicant :.. provide a canoe portage on the right (north) side of the impoundment and river at Essex No. 19 Dam by. May 1, 1995.”
. Condition E, as amended, permits exceptions to peak flow limits in certain circumstances, including times of local power emergencies, and after having "provided notice and an opportunity for hearing, the Secretary of the. Agency may modify th[e] exception[s] as appropriate.”
. Condition H, as amended, allows GMP to let the water level in the impoundment area to recede beneath a minimum level in certain emergency conditions and provides, as well, that "this exception may be modified by the Secretary of the Agency ... as appropriate after consultation with GMP and an opportunity for hearing.”
. Although condition B (relating to minimum water flow) differs from condition E and condition H in that it does not contain explicit exceptions to ordained water or flow levels, the report accompanying the certification indicates that the GMP has discretion to alter the levels. At the same time, however, the report states that Vermont may restrict such discretion at some later date. To the extent that the report may be considered to permit the state to alter the terms of the condition at some later date, FERC rejected the reservation of authority by the state.
. CVPS did not seek review of the certificates; however, on July 1, 1994, a local environmental group did so, and the appeal is currently pending before the Vermont Water Resources Board. The certifications are stayed pending appeal.
See
. The language of this condition reads, in full: "Any proposals for project maintenance or repair work involving the river, including desilting of the dam impoundment, impoundment draw-downs to facilitate repair/maintenance work, and tailrace dredging, shall be filed with the Department for prior review and approval.” Condition L in the Passumpsic certificate, condition J in the Pierce Mills and Arnold Falls certificates, and condition M in the Gage certificate.
. This condition reads, in full: “Any change to the project that would have a significant or material effect on the findings, conclusions, or conditions of this certification, including project operation, must be submitted to the Department for prior review and written approval.” Condition O in the Passumpsic, Pierce Mills and Arnold Falls certificates and condition R in the Gage certificate.
. The condition reads, in full: "The Department may request, at any time, that FERC reopen the license to consider modifications to the license necessary to assure compliance with Vermont Water Quality Standards.” Condition P in the Pаssumpsic, Pierce Mills and Arnold Falls certificates and condition S in the Gage certificate.
. The condition reads, in relevant part:
Within two years of a written request by the Agency, the applicant shall provide for upstream fish passage, subject to plan approval by the Department of Fish and Wildlife. The U.S. Fish and Wildlife Service and the Department of Fish and Wildlife shall be consulted during plan development....
Condition G in the Passumpsic, Pierce Mills and Arnold Falls certificates and condition J in the Gage certificate.
. In particular,
. Contrary to the Commission’s contention,
see
Brief of the Fed. Energy Regulatory Comm’n at 11 (stating that
.
[a]ny Federal license or permit with respect to which a certification has been obtained ... may be suspended or revoked by the Federal agency issuing such license or permit upon the entering of a judgment under this chapter that such facility or activity has been operated in violation of the applicable provisions of section 1311, 1312, 1313, 1316, or 1317 of this title.
. Section 4(e) of the FPA,
The Commission is authorized and empowered — (e) To issue licenses ... to any corporation organized under the laws' of the United States or any State thereof .,.. for the purpose of constructing, operating, and maintaining dams, water conduits, reservoirs, pоwer houses, transmission lines, or other project works necessary or convenient ... for the development, transmission, and utilization of power across, along, from or in any of the streams or other bodies of water over which Congress has jurisdiction under its authority to regulate commerce with foreign nations and among the several States, or upon any part of the public lands and reservations of the United Slates (including the Territories), or for the purpose of utilizing the surplus water or water power from any Government dam, except as herein provided: Provided, That licenses' shall be issued within any reservation only after a finding by the Commission that the license will not interfere or be inconsistent with the purpose for which such reservation was created or acquired, and shall be subject to and contain such conditions as the Secretary of the department under whose supervision such reservation falls shall deem necessary for the adequate protection and utilization of such reservátion....