243 So. 3d 903
Fla.2018Background
- Florida Power & Light (FPL) filed consolidated rate dockets in 2016 seeking large base-rate increases and cost recovery for capital projects, including a $725.6 million Peaker Replacement Project that replaced 44 aging gas-turbine peaking units with seven newer combustion turbines.
- The Peaker Project accounted for about $92 million of FPL’s 2017 revenue request but was estimated to produce net customer savings over time and improve reliability; peaker units provide fast-start, emergency, and peak-hour capacity that solar cannot reliably supply.
- FPL and three intervenors (Office of Public Counsel, South Florida Hospital & Healthcare Assn., Florida Retail Federation) executed a nonunanimous “black box” settlement resolving all 167 issues in the consolidated dockets; Sierra Club, AARP, and two individual intervenors opposed.
- The Florida Public Service Commission reopened the record, held a hearing on whether the settlement was in the public interest, and unanimously approved the settlement, adopting findings about rate reductions, service quality, rate stability, and participation by broad customer representatives.
- Sierra Club appealed, arguing the Commission should have applied the statutory prudence standard to the Peaker Project individually rather than approving the settlement under the Commission’s public interest standard.
Issues
| Issue | Plaintiff's Argument | Defendant's Argument | Held |
|---|---|---|---|
| Whether the PSC was required to perform an independent prudence determination of FPL’s Peaker Project before approving a nonunanimous settlement that included cost recovery for that project | Sierra Club: statute §366.06(1) requires prudence review of utility investments; Commission must decide prudence of the Peaker Project separately rather than rely only on a holistic public-interest settlement review | Commission/FPL: when presented with a settlement, the Commission properly applies a case-specific public-interest standard to the settlement as a whole and need not make discrete prudence findings on every resolved issue | The Court affirmed that the Commission may review settlements under the public-interest standard and is not required to make independent prudence findings for the Peaker Project when approving a settlement |
| Whether the Commission’s Final Order provided sufficient findings and was supported by competent, substantial evidence | Sierra Club: Final Order failed to adequately explain the basis for approving cost recovery relating to the Peaker Project | Commission/FPL: the Final Order described major settlement terms, procedural history, participant support, rate impacts, reliability and service findings, and factual record; competent, substantial evidence supports the public-interest determination | The Court held the Final Order was sufficient and that competent, substantial evidence supported the Commission’s finding that the settlement was in the public interest |
Key Cases Cited
- Citizens of State v. Fla. Pub. Serv. Comm’n, 146 So. 3d 1143 (Fla. 2014) (approving Commission’s use of public-interest standard to review settlement agreements)
- Citizens of State v. Fla. Pub. Serv. Comm’n, 191 So. 3d 897 (Fla. 2016) (de novo review of Commission authority; interpretations of statute reviewed for clear error)
- Citizens of State v. Fla. Pub. Serv. Comm’n (FPUC), 213 So. 3d 703 (Fla. 2017) (Commission must explain reasoning when allowing cost recovery precluded by prior settlement)
- S. All. for Clean Energy v. Graham, 113 So. 3d 742 (Fla. 2013) (prudence standard arises under §366.06 and governs cost recovery for investments)
- Crist v. Jaber, 908 So. 2d 426 (Fla. 2005) (appellant bears burden to show departure from essential requirements of law or lack of competent, substantial evidence)
- Gulf Power Co. v. Fla. Pub. Serv. Comm’n, 453 So. 2d 799 (Fla. 1984) (appellate court will not reweigh evidence or substitute its judgment for Commission)
- W. Fla. Elec. Coop. Ass’n v. Jacobs, 887 So. 2d 1200 (Fla. 2004) (Commission orders presumed reasonable and just)
- United Tel. Co. of Fla. v. Fla. Pub. Serv. Comm’n, 496 So. 2d 116 (Fla. 1986) (Commission derives authority solely from Legislature; authority-to-act questions reviewed de novo)
- AmeriSteel Corp. v. Clark, 691 So. 2d 473 (Fla. 1997) (public-interest inquiry guides Commission review of settlement/territorial agreements)
- Fla. Power & Light v. Beard, 626 So. 2d 660 (Fla. 1993) (prudence standard applied to individual investment projects in rate cases)
