Citizens of the State of Florida, etc. v. Florida Public Service CommissionCitizens of the State of Florida, etc. v. Florida Public Service Commission
This case is before the Court on appeal from a decision of the Florida Public Service Commission (the Commission) relating to the rates of a public utility providing electric service. See In re Petition of Fla. Power & Light Co., Docket No. 120015-EI, Order No. PSC-13-0023-S-EI, 2013 WL 209584 (F.P.S.C. Jan. 14, 2013). We have jurisdiction. See
FACTUAL AND PROCEDURAL BACKGROUND
On March 19, 2012, FPL filed an application with the Commission for a permanent increase of base rates of $516.5 million to satisfy revenue requirements and a proposed return on equity (ROE) of 11.5% beginning in January 2013, and a generation base revenue adjustment (GBRA) of $173.9 million for the Cape Canaveral modernization project beginning in the summer of 2013. With its petition, FPL filed its minimum filing requirements (MFR) and the prefiled testimony and exhibits of fifteen witnesses who addressed FPL‘s request.
Citizens, represented by the Office of Public Counsel (OPC),1 filed its notice of intervention on March 19, 2012. Other affected parties also filed petitions for leave to intervene, which were granted in separate orders. On July 2, 2012, Citizens filed the testimony of seven expert witnesses. These witnesses opined that no rate increase was warranted and that the Commission should require FPL to reduce its rates. Other intervenors, including FIPUG, SFHHA, and FEA, submitted testimony opposing FPL‘s request. Between the March filing and July 2012, FPL began negotiating a settlement with FEA, FIPUG, and SFHHA.2 In July, FPL first presented Citizens with the negotiated settlement. Shortly thereafter, FPL filed the testimony of seventeen rebuttal witnesses.
On August 14, 2012, a prehearing conference was conducted and 193 disputed issues of fact were identified in FPL‘s petition. On August 15, 2012, the signatories to the settlement agreement—FEA, FIPUG, SFHHA, and FPL—filed joint motions to suspend the procedural schedule and approve the settlement agreement. The proposed settlement agreement set an ROE of 10.7% and an initial rate base increase of $378 million annually, scheduled to take effect in January 2013. Further, although not part of FPL‘s initial petition, FPL would receive a GBRA for the Cape Canaveral modernization project and receive GBRAs of $236 million and $217.9 million, respectively, for its Riviera Beach and Port Everglades modernization projects upon entering commercial operations in 2014 and 2016.
The agreement also gave FPL the ability to amortize up to $209 million of its accumulated fossil plant dismantlement reserve during its four-year term and postpone the periodic analysis of the status of the fossil dismantlement reserve balance that otherwise would be required by the Commission‘s rule, unless the Commission ordered otherwise. Although Citizens and the signatories each requested a suspension of the hearing schedule to consider the settlement agreement
A full evidentiary hearing was held on the rate case on August 20-24 and August 27-31, 2012. Prior to the hearing, the parties filed direct and rebuttal testimony of all witnesses, along with the exhibits they intended to sponsor. They also engaged in extensive discovery and filed prehearing statements. A prehearing conference was held on August 14, 2012, and a prehearing order was issued on August 17, 2012. On August 30, 2012, during the rate case hearing, the Commission announced on the record, in conformity with an order establishing procedure on August 27, 2012, that the hearing would reconvene on September 27, 2012, to discuss the proposed settlement agreement.
At the September 27, 2012, hearing, the Commission determined that the proposed settlement agreement raised five new disputed issues of material fact supplemental to the disputed issues presented in the initial petition. The issues were: (1) whether the GBRAs for the Cape Canaveral, Riviera Beach, and Port Everglades modernization projects were in the public interest; (2) whether the amortization of a portion of FPL‘s fossil dismantlement reserve was in the public interest; (3) whether the postponement of filing depreciation or dismantlement studies by FPL was in the public interest; (4) whether the incentive mechanism for gain sharing between customers and FPL was in the public interest; and (5) whether the settlement agreement was in the public interest. As a result, the Commission elected to schedule a hearing to take additional testimony limited to the five new disputed issues of fact. In an order issued on October 3, 2012, the hearing was scheduled for November 19-21, 2012. The parties filed direct and rebuttal testimony of all witnesses as to the settlement issues, along with the exhibits they intended to sponsor. The parties also engaged in discovery. The formal hearing reconvened on November 19, 2012, and concluded on November 20, 2012. Post-hearing briefs were filed on November 30, 2012.
On December 13, 2012, the Commission held a special agenda conference to rule upon the merits of the proposed settlement agreement. After the Commission voiced its concern with a few items, the Commission recessed to give all the parties an opportunity to engage in further settlement negotiations.
When presented with the modified settlement agreement, the Commission found that it satisfied all of the Commission‘s concerns and that it established fair, just, and reasonable rates and that it was in the public interest. The final order memorialized this finding on January 14, 2013, and incorporated the approved settlement. The final order also listed the major differences between the proposed agreement and the modified agreement. However, the 193 disputed issues of fact identified in FPL‘s petition were not entirely addressed by the Commission in its final order. The details of the procedures followed by the Commission, testimony and evidence introduced at the hearings, and the Commission‘s final order that are relevant to the issues raised on appeal will be discussed below.
Citizens now appeals the Commission‘s decision and contends that: (1) the Commission erred by approving a non-unanimous negotiated settlement agreement over Citizens’ objection; (2) the Commission violated Citizens’ due process rights by creating a rushed hearing track to consider the settlement agreement; and (3) the Commission‘s decision that the settlement agreement and its terms result in rates that are fair, just, reasonable, and in
ANALYSIS
Standard of Review
As we have consistently held, when reviewing an order of the Commission, this Court affords great deference to the Commission‘s findings. S. Alliance for Clean Energy v. Graham, 113 So. 3d 742, 752 (Fla. 2013) (noting that this Court has repeatedly held that “[the Commission‘s] orders, and concomitant interpretations of statutes and legislative policies that it is charged with enforcing, are entitled to great deference.“). “Commission orders come to this Court clothed with the presumption that they are reasonable and just.” W. Fla. Elec. Coop. Ass‘n, Inc. v. Jacobs, 887 So. 2d 1200, 1204 (Fla. 2004) (citing Gulf Coast Elec. Coop., Inc. v. Johnson, 727 So. 2d 259, 262 (Fla. 1999)); see also BellSouth Telecomm., Inc. v. Johnson, 708 So. 2d 594, 596 (Fla. 1998) (noting that Commission orders carry a presumption of validity). Moreover, “[t]o overcome these presumptions, a party challenging an order of the Commission on appeal has the burden of showing a departure from the essential requirements of law and the legislation controlling the issue, or that the findings of the Commission are not supported by competent, substantial evidence.” S. Alliance for Clean Energy, 113 So. 3d at 752 (quoting Crist v. Jaber, 908 So. 2d 426, 430 (Fla. 2005) (citing Jacobs, 887 So. 2d at 1204)). We now turn to Citizens’ first claim on appeal.
I. Whether the Commission is Authorized to Approve a Non-unanimous Settlement Agreement over Citizens’ Objection
Citizens’ first issue presented for review is whether the Commission erred in approving the revised stipulation and settlement between FPL, FIPUG, SFHHA, and FEA over Citizens’ continued objections and without its involvement.3 Specifically, Citizens claims that the Commission‘s approval of the settlement agreement was akin to the procedural violations present in Citizens v. Mayo, 333 So. 2d 1 (Fla. 1976), where the OPC was denied from participating fully in a public hearing that the Commission conducted on an aspect of a utility‘s rate increase request. In support, Citizens cites to
As more fully explained below, Citizens’ argument regarding the Commission‘s authority to approve a settlement agreement objected to by the OPC is without merit because the Commission independently determines rates for utilities, the Commission is authorized by statute to resolve rate-making proceedings by approving negotiated settlements, and nothing in the language of
Pursuant to
Second, pursuant to
(1) To recommend to the commission or the counties, by petition, the commencement of any proceeding or action or to appear, in the name of the state or its citizens, in any proceeding or action before the commission or the counties and urge therein any position which he or she deems to be in the public interest, whether consistent or inconsistent with positions previously adopted by the commission or the counties, and utilize
therein all forms of discovery available to attorneys in civil actions generally, subject to protective orders of the commission or the counties which shall be reviewable by summary procedure in the circuit courts of this state; (2) To have access to and use of all files, records, and data of the commission or the counties available to any other attorney representing parties in a proceeding before the commission or the counties;
(3) In any proceeding in which he or she has participated as a party, to seek review of any determination, finding, or order of the commission or the counties, or of any hearing examiner designated by the commission or the counties, in the name of the state or its citizens;
(4) To prepare and issue reports, recommendations, and proposed orders to the commission, the Governor, and the Legislature on any matter or subject within the jurisdiction of the commission, and to make such recommendations as he or she deems appropriate for legislation relative to commission procedures, rules, jurisdiction, personnel, and functions; and
(5) To appear before other state agencies, federal agencies, and state and federal courts in connection with matters under the jurisdiction of the commission, in the name of the state or its citizens.
In addition, this Court‘s holding in Mayo was not intended to extend to the factual circumstances present here. In Mayo, Gulf Power filed a petition for a permanent rate increase and the OPC intervened on behalf of Citizens. Mayo, 333 So. 2d at 2-3. The Commission scheduled and held hearings over two days. The evidence presented to the Commission included direct testimony from Gulf Power in support of its rate increase requests; clarifying questions from the Commission‘s staff, from the OPC, public counsel, and from other intervenors with respect to Gulf Power‘s testimony and evidence; and testimony and evidence from public witnesses both for and against the proposed rate increases. The OPC, however, did not cross-examine Gulf Power witnesses or present any direct evidence contradictory to the data supplied by Gulf Power because it indicated it was not prepared due to the Commission‘s notice of hearing specifying such facets of the hearing would be held at a later date. Shortly thereafter,
special conditions pertain in cases where public counsel has intervened. This is a consequence of the statutory nexus between the file and suspend procedures and the role prescribed for public counsel in rate regulation. Public counsel was authorized to represent the citizens of the State of Florida in rate proceedings of this type. That office was created with the realization that the citizens of the state cannot adequately represent themselves in utility matters, and that the rate-setting function of the Commission is best performed when those who will pay utility rates are represented in an adversary proceeding by counsel at least as skilled as counsel for the utility company. The
office of public counsel was created by the same enactment which brought the utilities accelerated rate relief. Under these circumstances, the Commission cannot schedule a “public hearing” and preclude public counsel, the public‘s advocate, from acting to protect the public‘s interest.
Id. at 6-7 (footnote omitted). Accordingly, this Court held that “[b]y foreclosing public counsel‘s effective participation in the interim rate process after having assured it, the procedures used by the Commission to grant interim rate relief in this case were plainly improper.” Id. at 7. This Court‘s use of this language was intended to ensure that the OPC is fully involved (i.e., not precluded from participation in a hearing) when the public‘s interest is at issue in an adversary proceeding—it is not a broad-based proclamation that the OPC is a “special intervenor” deserving of additional authority in a rate-setting context. Moreover, the factual circumstances here satisfy this Court‘s reasoning in Mayo.
Here, as discussed more at length below, the OPC fully represented Citizens in ten days of hearings regarding FPL‘s petition for a rate increase and also fully participated in hearings regarding the proposed settlement agreement by submitting prefiled testimony, participating in discovery, presenting evidence in opposition to the settlement agreement, and filing post-hearing briefs. Thus, the OPC was not precluded from zealously representing Citizens, but was provided multiple opportunities to urge the public‘s position on FPL‘s petition and subsequent settlement agreement.
Likewise, this Court‘s holding in Jaber does not support Citizens’ argument. In Jaber, this Court found that the Commission
Third, the OPC‘s argument that “[u]nless the Court reverses the Final Order, the effect will be to marginalize the participation of ‘the public‘s advocate . . .’ as the petitioning utility could bypass [the] OPC‘s opposition through the expedient of offering a revenue concession . . . to a willing intervenor . . .” is without merit. Ultimately, the Commission‘s actions are conditioned by statute (rates set must be fair, just, and reasonable) and its actions are subject to judicial review—the Commission cannot simply accept any settlement agreement devoid of record support as in the public interest. Moreover, none of the actions taken by the Commission in this case will preclude the OPC from fully representing the public‘s interest in future cases because the OPC was able to “urge therein any position which he or she deem[ed] to be in the public interest” in this rate-making proceeding.
Citizens also argues that the factual findings in the final order were insufficient because the Commission did not explain why it overruled the OPC‘s objections to consideration of the settlement and did not resolve every disputed issue of fact. Further, amicus curiae AARP argues that approval of the settlement without staff review is an improper abdication of the Commission‘s obligations. These arguments are without merit.
II. Whether the Commission Violated Citizens’ Due Process Rights by Considering FPL‘s Proposed Settlement Agreement Containing Major Elements not Present in FPL‘s Petition for Base Rate Increases
Citizens claims that the Commission failed to afford due process to the opponents of the settlement agreement by creating a rushed hearing schedule to discuss settlement issues that were not present in FPL‘s rate increase petition and not accompanied by a test-year notification letter, MFRs, testimony, or exhibits. Specifically, Citizens argues that FPL‘s settlement agreement included new rate base increases, $209 million of earnings enhancements, and FPL-favoring policy initiatives. Thus, this Court must determine whether the fairness of the proceedings or the correctness of the Commission‘s action was impaired by a material error in procedure or a failure to follow prescribed procedure, or whether the Commission‘s exercise of discretion was outside the range of discretion delegated to it.
A. Due Process Requirements
As this Court has noted in the past, “[t]he extent of procedural due process protections varies with the character of the interest and nature of the proceeding involved.” Hadley v. Dep‘t of Admin., 411 So. 2d 184, 187 (Fla. 1982) (citing In Interest of D.B., 385 So. 2d 83, 89 (Fla. 1980)). Although this Court has stated that there is no single test to determine whether the requirements of due process have been met, see Hadley, 411 So. 2d at 187, “[t]he fundamental requirements of due process are satisfied by reasonable notice and a reasonable opportunity to be heard.” Fla. Pub. Serv. Comm‘n v. Triple “A” Enter., Inc., 387 So. 2d 940, 943 (Fla. 1980) (citing Ryan v. Ryan, 277 So. 2d 266 (Fla. 1973); Powell v. State of Ala., 287 U.S. 45 (1932); Dohany v. Rogers, 281 U.S. 362 (1930)). Further, due process cannot be compromised “on the footing of convenience or expediency.” United Tel. Co. of Fla. v. Beard, 611 So. 2d 1240, 1243 (Fla. 1993) (quoting Fla. Gas Co. v. Hawkins, 372 So. 2d 1118, 1121 (Fla. 1979)).
Ultimately, however, “[t]he legislature may determine by what process and procedure legal rights may be asserted and determined provided that the procedure adopted affords reasonable notice and a fair opportunity to be heard before rights are decided.” Peoples Bank of Indian River Cnty. v. State, Dep‘t of Banking & Fin., 395 So. 2d 521, 524 (Fla. 1981). In the administrative arena, due process requirements are found in chapter 120, Florida Statutes, the Florida Administrative Procedure Act (“APA“).6 Further, additional procedural requirements specific to the Commission and public utilities are provided in chapter 366, Florida Statutes, and the Florida Administrative Code.
The provisions of
All parties shall have an opportunity to respond, to present evidence and argument on all issues involved, to conduct cross-examination and submit rebuttal evidence, to submit proposed findings of facts and orders, to file exceptions to the presiding officer‘s recommended order, and to be represented by counsel or other qualified representative. When appropriate, the general public may be given an opportunity to present oral or written communications. If the agency proposes to consider such material, then all parties shall be given an opportunity to cross-examine or challenge or rebut the material.
Chapter 366 also provides procedures for fixing and changing rates of public utilities.
The Florida Administrative Code also contains procedural rules for rate-making proceedings. Specifically, rules 25-6.140 and 25-6.043 set forth the initial requirements for a utility‘s application for a
- (1) At least 60 days prior to filing a petition for a general rate increase, a company shall notify the Commission in writing of its selected test year and filing date. This notification shall include:
- (a) An explanation for requesting the particular test period. If a historical test year is selected, there shall be an explanation of why the historical period is more representative of the company‘s operations than a projected period. If a projected test year is selected, there shall be an explanation of why the projected period is more representative than a historical period;
- (b) An explanation, including an estimate of the impact on revenue requirements, of the major factors which necessitate a rate increase;
- (c) A statement describing the actions and measures implemented by the company for the specific purpose of avoiding a rate increase; and
- (d) A statement that the utility either is or is not requesting that the Commission process its petition for rate increase using the proposed agency action process authorized in Section 366.06(4), F.S.
- (2) In the event that a test year other than one based on a calendar year or the company‘s normal fiscal year is selected, the notification shall include an explanation of why the chosen test year period is more appropriate.
- (3) If the company cannot meet its filing date, it shall notify the Commission in writing before the due date and include an explanation of why it will not meet the filing date. The company shall include a revised filing date.
- (1) General Filing Instructions.
- (a) The petition under Sections 366.06 and 366.071, F.S., for adjustment of rates must include or be accompanied by:
- 1. The information required by Commission Form PSC/ECR/011-E (2/04), entitled “Minimum Filing Requirements for Investor-Owned Electric Utilities” which is incorporated into this rule by reference. The form may be obtained from the Commission‘s Division of Economic Regulation.
- 2. The exact name of the applicant and the address of the applicant‘s principal place of business.
- 3. Copies of prepared direct testimony and exhibits for each witness testifying on behalf of the Company.
- (b) In compiling the required schedules, a company shall follow the policies, procedures and guidelines prescribed by the Commission in relevant rules and in the company‘s last rate case or in a more recent rate case involving a comparable utility. These schedules shall be identified appropriately (e.g., Schedule B-1 would be designated Company Schedule B-1 – Company basis).
- (c) Each schedule shall be cross-referenced to identify related schedules as either supporting schedules or recap schedules.
- (d) Each page of the filing shall be numbered on 8 1/2” × 11” inch paper. Each witness’ prefiled testimony and exhibits shall be on numbered pages and all exhibits shall be attached to the proponent‘s testimony.
- (e) Except for handwritten official company records, all data in the petition, testimony, exhibits and minimum filing requirements shall be typed.
- (f) Each schedule shall indicate the name of the witness responsible for its presentation.
(g) All schedules involving investment data shall be completed on an average investment basis. Unless a specific schedule requests otherwise, average is defined as the average of 13 monthly balances. - (h) Twenty-one copies of the filing, consisting of the petition and its supporting attachments, testimony, and exhibits, shall be filed with the Office of Commission Clerk.
- (i) Whenever the company proposes any corrections, updates or other changes to the originally filed data, 21 copies shall be filed with the Office of Commission Clerk with copies also served on all parties at the same time.
- (2) Commission Designee: The Director of the Division of Economic Regulation shall be the designee of the Commission for purposes of determining whether the utility has met the minimum filing requirements imposed by this rule. In making this determination, the Director shall consider whether information that would have been provided in a particular schedule required by this rule has been provided to the same degree of detail in another required schedule that the utility incorporates by reference.
The Florida Administrative Code also contains a rule governing the procedures for disposition of a motion. Under
As noted in the discussion below, the Commission followed the procedures outlined in the statutes and rules, and provided Citizens with adequate notice and the opportunity to be heard. Accordingly, we affirm the Commission‘s final order.
B. Relevant Procedure Followed Below
1. Initial Filing
FPL filed its application for a change in rates on March 19, 2012, more than sixty days after January 17, 2012, when FPL notified the Commission of its intent to submit such application. FPL‘s filing indicated that the projected test year for the petition was 2013 and requested authority to increase its base rates and charges to generate an additional $516.5 million of revenues annually with an 11.5% ROE. FPL also asked for authority to increase its base rates by an additional $173.9 million annually when its Cape Canaveral generation project enters commercial service in the summer of 2013. With its petition, FPL submitted the MFRs as well as the prefiled testimony and exhibits of fifteen witnesses.
2. Order Establishing Procedure
Shortly thereafter on March 26, 2012, the Commission issued an order establishing the procedure for the rate-making proceedings. The deadline for discovery was set for August 13, 2012, the prehearing conference was scheduled for August 14, 2012, and the evidentiary hearing on the petition was scheduled for a two-week period beginning August 20, 2012. Thus, in regard to the evidentiary hearing for the petition, Citizens received adequate notice of the hearing pursuant to
From March to mid-August 2012, Citizens served fourteen sets of interrogatories and thirteen requests to produce documents on FPL and participated in numerous depositions. On July 2, 2012, Citizens filed the testimony of seven expert witnesses, who addressed various aspects of FPL‘s March filing, and argued that FPL should actually reduce its existing rates. FPL presented Citizens with a completed and signed settlement agreement in the middle of July.
3. Evidentiary Hearing and Joint Motions to Approve Settlement and Suspend Procedural Schedule
On August 15, 2012, the signatories to the negotiated settlement agreement filed a joint motion to approve settlement agreement and a joint motion to suspend procedural schedule. Anticipating that there would not be a need for a hearing if the Commission granted their motion, the signatories requested the Commission to suspend all remaining portions of the procedural schedule. Citizens opposed the joint motion to approve the settlement agreement, but not the joint motion to suspend the procedural schedule, arguing that the hearing could not proceed without the Commission conducting a full analysis of the settlement agreement. The joint motion to suspend the procedural schedule was denied in part based on the difficulty of rescheduling a complex hearing if the settlement agreement was not approved. The hearing commenced as scheduled on August 20, 2012.
At the start of the hearing, Citizens orally moved for reconsideration of the order denying the joint motion to suspend the procedural schedule and requested that the procedural schedule be suspended because Citizens wished to “rid the process of the undue influence of the FPL document . . . on the scheduled hearing.”8 Argument was heard on the motion from all parties, and the motion was denied. Citizens then moved to dismiss the proposed settlement agreement, set the motion to approve it for expedited oral argument in advance of the rate case hearing, or dismiss the petition for rate increase.9 The
On August 27, 2012, the Commission revised the order establishing procedure to set the procedural schedule for the Commission‘s consideration of the proposed settlement agreement. Although the order did not provide a specific date and time to consider the joint motion to approve the settlement agreement, the order provided that at the conclusion of the evidentiary portion of the rate case hearing, the Commission would recess until the date and time announced to reconvene the hearing to consider the motion to approve the settlement agreement. In short, the hearing to consider the settlement agreement was considered part of the hearing on the petition.
The order stressed that the hearing to consider the joint motion to approve the settlement agreement was not an evidentiary proceeding and that no evidence would be taken, but thirty minutes for comments per side would be provided. The order also permitted the parties and Commission staff to submit up to 100 data requests each, with responses due within five days from the requests. Various data requests were propounded by the parties and Commission staff in advance of the hearing on the proposed settlement agreement.
On August 30, 2012, during the rate case hearing, the Commission announced on the record that the hearing would reconvene on September 27, 2012, to take up the proposed settlement agreement. Post-hearing briefs for the evidentiary hearing were filed on September 21, 2012. Upon reconvening the hearing, oral argument commenced and the Commission determined that the proposed settlement agreement raised five new disputed issues of material fact. Therefore, the Commission voted to take additional testimony limited to those specific issues that were supplemental to the issues in the initial MFRs in an expedited manner that would comport with due process and all statutory requirements.
4. Evidentiary Hearing on Settlement Agreement
On October 3, 2012, the Chairman of the Commission issued a third order revising the order establishing procedure, continuing the hearing until November 19-21, 2012, to take evidence on the specific issues contained in the proposed settlement agreement that were supplemental to the issues of the rate case. Prior to the hearing, the parties filed the direct and rebuttal testimony of all witnesses on the settlement issues and the exhibits each witness would sponsor. The parties also engaged in discovery. The parties filed their prehearing statements, and a prehearing conference was held on November 15, 2012. The formal hearing reconvened on November 19, 2012, and concluded on November 20, 2012. Post-hearing briefs on the settlement issues were filed on November 30, 2012.
On December 13, 2012, pursuant to a notice issued on November 21, 2012, the Commission held a special agenda conference to rule upon the merits of the proposed settlement agreement. The Commission voiced public interest concerns about specific terms of the settlement agreement. The Commission then recessed to give all the parties an opportunity to engage in further settlement negotiations
C. Application of Law to the Procedures Followed Below
1. Whether the Inclusion of the Riviera Beach and Port Everglades GBRA Provisions Should Have Resulted in the Filing of a New Application for a Change in Rates
Citizens argues that the GBRA provisions in the settlement agreement exceeded the scope of FPL‘s initial petition and affect rates, which should have required a new application for changes in rates under rules 25-6.140 and 25-6.043 of the Florida Administrative Code.
First, as emphasized above, these rules apply to petitions for changes in rates, not proposed settlement agreements; FPL complied with those rules with its initial filing petition. Although it may be the better practice to require a new application for changes in rates, there is no such requirement. Second, the GBRAS for the Riviera Beach and Port Everglades modernization projects will be tied to the 10.5% midpoint of FPL‘s authorized ROE and calculated using the capital structure reflected in the MFRs filed for the Cape Canaveral project; and the revenue requirements will be based on the “cumulative present value of revenue requirement reflected in the respective need determinations.” And third, as discussed more fully below, the Commission provided ample opportunities for discovery and held hearings to consider the settlement agreement well after the joint motion for approval of the settlement was filed by FPL and the intervenor signatories, and well after Citizens claimed it was prepared to argue the joint motion for approval of the settlement agreement. Citizens, however, correctly notes that the Commission has not been consistent with its treatment of GBRAs in the past.
In 2005, the Commission approved a settlement agreement that contained a provision allowing FPL to receive GBRAs for “any power plant that is approved pursuant to the Florida Power Plant Siting Act (PPSA) and achieves commercial operation within the term of this Stipulation and Settlement.” In re Fla. Power & Light Co., Docket Nos. 050045-EI, 050188-EI, Order No. PSC-05-0902-S-EI, 2005 WL 2276715, *7 (F.P.S.C. Sep. 14, 2005). The term was for four years with rates going into effect until new rates became effective by order of the Commission. Id. at *1. Notably, FPL‘s application for a change in rates only included MFRs for a GBRA for Turkey Point Unit 5. Id.
In 2010, in the rate case immediately following the 2005 rate case, the Commission rejected a similar request from FPL to receive GBRAs for revenue requirements associated with new generating additions at the time they enter commercial service. In re: Petition for Increase in Rates by Fla. Power & Light Co., Docket Nos. 080677-EI, 090130-EI, Order No. PSC-10-0153-FOF-EI, 2010 WL 1005321, *10 (F.P.S.C. Mar. 17, 2010). Instead, the Commission elected to allow the previous GBRAs to expire. The Commission specifically reasoned that:
[t]he existing ratemaking procedure provided by Florida Statutes and our rules provides for a more rigorous and thorough review of the costs and earnings associated with new generating units.
Section 366.06(2), F.S. , provides that when approved rates charged by a utility do not provide reasonable compensation for electrical service, the utility may request that we hold a public hearing and determine reasonable rates to be charged by the utility.Section 366.071, F.S. , provides expedited approval of interim rates until issuance of a final order for a rate change.Rule 25-0243, F.A.C. , establishes the minimum filing requirements for utilities in a rate case. These procedures have been sufficient in the past for FPL and other regulated utilities wishing to recover capital expenditures when a new generating facility begins commercial service.
Id. Further, the Commission noted that “[i]t is not possible for us or interested parties to examine projected costs at the same level of detail during a need determination proceeding as we would be able to do in a traditional rate case proceeding. A need determination . . . does not allow for a review of the full scope of costs and earnings, as a rate case does.” Id. at *12. Thus, based on the 2010 case, it would appear that the Commission believes that GBRA requests should entail the same requirements associated with an initial petition for a change in rates.
The Commission, however, explained why the GBRAs sought in the 2010 case merited treatment distinct from the GBRAs in the 2005 case. In a section titled “Differences From the 2005 Stipulation,” the Commission noted that FPL‘s 2010 request was to permanently establish GBRAs intended to cover the costs of all future power plants that receive need determination approval. Id. at *11. In the 2005 request, the GBRAs were also intended to cover the costs of all power plants, but the term of the agreement was for a minimum of four years and would remain in effect until new base rates and charges became effective by order of the Commission. Thus, the 2005 request was an interim measure and not a permanent measure. Further, acceptance of the 2005 GBRA provision of the settlement agreement was a result of the “give-and-take” in negotiating the agreement. Id. For instance, in the 2005 request, FPL‘s base rates could not change during the term of the settlement agreement whereas FPL‘s 2010 request to continue the GBRA specified no restriction on changes to base rates. The 2005 request also contained a revenue sharing plan between shareholders and customers whereas no such plan existed in the 2010 request. Id.
Here, the settlement contains terms that are similar or more proscriptive than the rate request of 2005. First, the GBRAs here are part of a settlement agreement with a fixed four-year term. In the 2005 rate case, the settlement had a term of a minimum of four years and the rates would remain in effect until the necessary steps were taken to adjust the established rates. Second, the disputed GBRAs in this case are intended to cover the costs of the Riviera Beach and Port Everglades projects, whereas the GBRA mechanism approved as part of the 2005 settlement was intended to cover the costs of any and all power plants that received need determination approval during the settlement term. Third, both the 2005 agreement and the agreement approved here contained provisions prohibiting FPL from changing its base rates during the term of the settlement. And fourth, the 2005 request contained a revenue sharing plan between shareholders and customers; here, the settlement agreement contains an incentive mechanism where revenues are shared on an incremental basis. Thus, this current case is most similar to the 2005 case, in which the Commission found that the GBRA mechanism was appropriate and did not require the filing of MFRs and test year notifications for each plant approved pursuant to the PPSA.
Accordingly, despite the Commission‘s inconsistent approach and due to the deferential standard of review given to the Commission‘s decisions, we hold that FPL‘s request for GBRAs for the modernization projects did not necessitate the filing of a new petition.
2. Whether the Procedures Followed by the Commission in Consideration of the Proposed Settlement Violated Citizens’ Due Process Rights
Based on the above, the Commission did not violate Citizens’ due process rights. On March 26, 2012, the Commission provided notice of a hearing on August 20 that fully complied with
Moreover, two cases from this Court are instructive on this issue. In Jaber, as noted earlier, this Court held that the Commission‘s decision to approve a non-unanimous negotiated settlement without an evidentiary hearing did not violate due process or the statutory rights of SFHHA in a rate review proceeding initiated by the Commission. Jaber, 887 So. 2d at 1212.
In Jaber, the settlement at issue on appeal resulted from a proceeding initiated by the Commission in August 2000 to consider the effect on FPL‘s retail rates of the formation of Florida‘s regional transmission organization and FPL‘s then-planned merger with Entergy Corporation. The Commission then expanded the scope of the proceeding to provide for a more thorough rate review, and ordered FPL to submit MFRs pursuant to
On appeal to this Court, SFHHA argued that the Commission‘s order approving the settlement in the absence of an evidentiary hearing violated its due process and statutory rights. Id. According to SFHHA, Florida law required the Commission to hold an evidentiary hearing because determining a reasonable level for FPL‘s rates involved numerous disputed issues of material fact. Id. SFHHA further asserted that the Commission erred in approving a non-unanimous settlement agreement absent a hearing. Id. This Court rejected those arguments.
This Court held in Jaber that the Commission‘s decision to expand the scope of its review did not require it to conduct an evidentiary hearing. The Court reasoned that the Commission properly initiated the proceeding, expressly recognized the possibility of a negotiated settlement, and acted in accordance with the authority granted under
Here, there is no dispute that an evidentiary hearing was held more than fourteen days after notice was provided and after additional discovery was provided and sought. Further, like Jaber, Citizens presented arguments in opposition to the settlement and its assertions presented at the settlement agreement were similar to the assertions presented throughout the course of the proceedings below. Thus, although in a distinct procedural posture, this Court has found that there was no due process violation when the Commission approved a non-unanimous settlement agreement without conducting an evidentiary hearing.
In AmeriSteel Corp. v. Clark, this Court held that AmeriSteel‘s due process rights were not violated by the Commission‘s failure to require the Jacksonville Electric Authority (JEA) and FPL to provide public notice that its settlement discussions would encompass matters beyond the scope of JEA‘s initial complaint against FPL regarding a territorial dispute over service to certain customers. 691 So. 2d 473, 479 (Fla. 1997). Although AmeriSteel is distinct factually and
procedurally, this Court‘s reasoning and analysis is instructive on the issue presented here. In AmeriSteel, the appellant was a customer of FPL, but the Commission did not allow it to intervene because it did not have requisite standing. However, AmeriSteel received notice of the Commission‘s proposed agency action order approving the territorial agreement and exercised its rights to file a protest in response.
In concluding that AmeriSteel‘s due process rights had not been violated, this Court noted that there “is no requirement in chapter 366, the Administrative Procedure Act, or Florida‘s Administrative Code that two negotiating utilities publish notice of the substance and scope of their ongoing
D. Conclusion
Accordingly, we affirm the Commission‘s final order because the Commission complied with all of the procedural requirements listed in
III. Whether the Elements of the Settlement Agreement are Supported by Competent, Substantial Evidence and Whether the Commission Exceeded the Limits of its Discretion in Approving the Settlement Agreement
As stated above, this Court will affirm the Commission‘s “findings and conclusions if they are based upon competent, substantial evidence and are not clearly erroneous.” S. Alliance for Clean Energy, 113 So. 3d at 752. Further, this Court ” ‘will not overturn an order of the [Commission] because we would have arrived at a different result had we made the initial decision and we will not re-weigh the evidence.’ ” Id. at 753. For the following reasons, the Commission‘s findings and conclusions that the settlement agreement established rates that were just, reasonable, and fair, and that the agreement is in the public interest are supported by competent, substantial evidence.
A. Findings in Final Order
The Commission‘s final order contains an extensive procedural background of the case explaining how the settlement agreement was considered and ultimately approved. The order also describes the major elements of the proposed agreements and how those terms were modified in the settlement agreement that was incorporated into the final order. Further, the order describes the basis for each revenue increase and how the incentive mechanism is intended to function, including that the Commission can terminate the program after two years.
Regarding its findings, first, the Commission found that the GBRA is in the public interest because: “[I]t provides a benefit to both FPL‘s customers and FPL. We already approved the need for the Canaveral, Riviera, and Port Everglades Modernization Projects when we considered FPL‘s need determination petitions. The GBRA provides the mechanism for FPL to recover the costs to modernize these plants and bring them into commercial service.” The Commission then found that the pilot incentive mechanism is in the public interest, stating, “The pilot incentive mechanism program is beneficial
B. The Settlement Agreement Benefits Only Narrow Customer Interests12
Citizens argues that the settlement only benefits narrow interests and that its “opposition to the proposed disposition disprove[s] the conclusion at page [seven] of the Final Order that the settlement reasonably resolves all issues.” This argument appears to invite the Court to reweigh competing evidence considered by the Commission, which, as stated above, is not this Court‘s function on review. Even if this argument is not an invitation to reweigh the evidence, Citizens fails to demonstrate that the Commission‘s conclusion that the settlement agreement benefits “FPL‘s customers” is not supported by competent, substantial evidence.
Witnesses Renae Deaton and Moray Dewhurst testified that FPL‘s residential customer bills will remain the lowest in Florida, bills for commercial and industrial customers will be more competitive with other, similar utilities in the region, and small business customers will not receive an increase. Specifically, witness Deaton testified that the revenue requirements of $378 million under the proposed agreement, which later became $350 million with $18 million of the reductions going specifically to the residential customer class under the modified agreement, would impact a June 2013 residential bill by increasing rates by $1.54 a month or five cents per day, which represents less than a 2% increase from current rates. Deaton also testified that parity—the extent to which the revenues of a rate class cover the cost of service to that rate class—is improved under the proposed settlement agreement, with all rate classes being either within the range of 90% to 110% of parity, or being moved toward that objective. The rates for residential customers would remain very close to the ideal of 100% under the proposed settlement
Witness Dewhurst also testified that customers would continue to enjoy good reliability and excellent customer service over a four-year period. Dewhurst further testified that “[t]he proposed settlement agreement provides for a roughly 25% reduction in FPL‘s January 2013 base rate increase request, from $517 million to $378 million.” The final approved revenue increase was reduced further to $350 million.
Witness Terry Deason, a former commissioner of the Commission, testified regarding the benefits of the settlement and how they served the public interest. He testified that FPL “significantly reduc[ed] the amount of their request“; the agreement is for a four-year term, which provides a great deal of certainty and predictability; and the settlement “reduces uncertainty in the process,” which positions FPL to “continue to have the financial integrity to go forward with their construction program, which benefits customers, and to be able to maintain a high degree of service.” Further, the four-year term eliminates the unnecessary expenditure of taxpayer funds to consider FPL‘s rates in another proceeding. Accordingly, Citizens cannot demonstrate that the Commission‘s conclusion that the settlement agreement benefits “FPL‘s customers” is not supported by competent, substantial evidence.
C. The Commission‘s Conclusion That the Settlement is a Fair and Reasonable Resolution is not Supported by Competent, Substantial Evidence
Citizens argues that the settlement consists of concessions to FPL for which non-signatories of the settlement agreement receive no concomitant benefits in return. Thus, Citizens argues that the Commission‘s conclusion that the settlement is a reasonable disposition of all issues is not supported by competent, substantial evidence, and is clearly erroneous. According to Citizens, the following six provisions of the settlement agreement are evidence that the settlement was not a reasonable compromise.
1. The 10.5% ROE Results in Unfair and Unreasonable Rates
Citizens argues that FPL‘s original request for a ROE midpoint of 11.25%, and a performance adder of .25%, was not supported by competent, substantial evidence. Citizens recognizes that many FPL witnesses and other signatory witnesses testified that the ROE was warranted or that a 10.5% ROE was reasonable given the other elements of the settlement agreement, but Citizens nevertheless argues that its experts’ testimony demonstrated that the ROE was too high. In United Telephone Co. v. Mayo, 345 So. 2d 648, 654 (Fla. 1977), this Court recognized that the Commission had the difficult task of determining a reasonable rate of return for a utility, but that it was the Commission‘s “prerogative to evaluate the testimony of competing experts and accord whatever weight to the conflicting opinions it deems appropriate.” Thus, as discussed below, although there was competing expert testimony offered by Citizens, competent, substantial evidence supports the Commission‘s conclusion.
Citizens argues that FPL‘s ROE should have been reduced, not increased, from the 10% approved in 2010 primarily because interest rates are low and cost of capital has declined. FPL‘s witnesses and other witnesses, however, supported the increase in ROE. Witness William Avera, a principal of Financial Concepts and Applications,
Citizens argues that witness Jeffry Pollock‘s testimony regarding the ROE ignored the impact of FPL‘s extremely high 59.62% equity ratio. Witness Avera, however, testified that the ROE is not a function of a single financial statistic because it does not account for other factors considered by investors, “including the impact of purchased power commitments and the other exposures unique to FPL.” Further, he testified that the ROE requested was reasonable because “the availability of capital is particularly important to FPL‘s customers because of the need for financial strength inherent in FPL‘s location and characteristics.” Also notable is that FPL requested a midpoint ROE of 11.25%, negotiated a 10.7% midpoint, and ultimately agreed to a 10.5% midpoint ROE, which was only slightly higher than the minimum range of ROE requested. Finally, witness Pollock testified that the 10.7% ROE provided a competitive ROE that was above average relative to returns authorized by other commissions for investor-owned electric utilities, but stated that it would enable FPL to maintain an A credit rating and that it was not a sufficient ground to reject the settlement. Pollock also observed that other utilities in this comparison (southeastern utilities) currently had authorized ROEs higher than 10.7%, including a Florida investor-owned utility earning a ROE of 11.25%. All of the testimony referenced above supports a ROE figure higher than the 10.5% sum contained within the settlement agreement. Accordingly, the Commission‘s conclusion that a 10.5% ROE as part of a settlement agreement is a reasonable resolution of the issue is supported by competent, substantial evidence.
2. The $350 Million Rate Base Increase Results in Unfair and Unreasonable Rates
Citizens argues that its litigation position was that FPL‘s $516.5 million request was $140 million above what it should have been. Thus, according to Citizens, any effort to characterize this reduction from $516.5 million to $350 million as a “compromise” is untenable and “[n]o reasonable mind would regard a term that reflects the surrendering of practically all litigated rate base adjustments as offsetting an unduly high ROE, or otherwise providing substantial evidence reasonably tending to support the conclusion that the final order approves a fair and reasonable compromise settlement.” In short, Citizens argues that FPL did not compromise at all on this position because it lowered its requested revenue requirements. However, competent, substantial evidence supports the Commission‘s conclusion.
The rate base filing, which requested $516.5 million, is supported by many witnesses. Marlene Santos, Vice President
Kim Ousdahl, Vice President, Controller, and Chief Accounting Officer of FPL, also testified. Her testimony was in reference to methodologies employed to account for FPL‘s costs. She testified that FPL‘s adjusted ROE was estimated to be 8.2% absent rate relief. Roxane Kennedy, Vice President of Power Generation Operations at FPL, testified regarding costs related to FPL‘s fossil plant fleet. She testified that FPL‘s annual fossil base capital expenditures were projected to increase $164.8 million from $206.6 million in 2010 to $371.4 million in 2013. Further, she testified that the primary drivers of the increase are investments in combustion turbine (CT) hot end component upgrades ($95.6 million), CT planned maintenance overhauls ($41.1 million), work being done on Martin Unit 1 ($12.7 million) while the Electrostatic Precipitator outage is performed, and maintenance work at West County 3 ($11.3 million) and Canaveral Modernization Project ($2.7 million), units which were not in operation in 2010. Kathleen Slattery, Senior Director of Executive Services and Compensation at FPL, testified regarding costs related to human resources. She testified that FPL‘s gross total compensation and benefits cost was projected to be $1.261 billion for 2013, and FPL‘s gross total compensation and benefits cost was projected to be $1.049 billion for 2013.16
Finally, Robert Barrett, Jr., Vice President of Finance at FPL, testified regarding the necessity of a base rate increase.
Barrett testified that the rate base increase was determined as the difference between FPL‘s projected net operating income of $1.156 billion and FPL‘s required
Moreover, pursuant to the agreement, FPL foregoes its right to seek rate increases over the four-year term, regardless of FPL‘s increased expenses, lost revenues, or new non-generation capital projects during that period.17 Accordingly, the Commission‘s conclusion that a $350 million rate base increase would result in reasonable and fair rates is supported by competent, substantial evidence.
3. Competent, Substantial Evidence Does Not Support the Commission‘s Conclusion That the GBRAs for Riviera Beach and Port Everglades are Part of a Reasonable Compromise
Citizens argues that the GBRAs for the Riviera Beach and Port Everglades modernization projects would ensure that FPL receives more revenues under the compromise than it would have earned under the original petition, even if the 11.5% ROE had been authorized. Further, Citizens argues that in the past FPL has absorbed several power plants without the necessity of any increases and that the GBRAS agreed to here would relieve FPL from the burden of demonstrating that it requires an increase in base rates given the totality of its operations. As shown below, however, the Commission‘s conclusion that the GBRAs are part of a reasonable compromise and in the public interest is supported by competent, substantial evidence.
Witness Barrett testified that additional base rate increases would be necessary during the four-year term of the settlement to provide FPL an opportunity to recover the revenue requirements for these projects. He also testified that there were several reasons why it was unlikely to avoid rate base increases for these modernization projects: (1) absent rate adjustments, FPL will experience declines in earned ROE of 148 and 136 basis points when the projects go into service;
Further, the GBRA mechanism is reasonable and inures to everyone‘s benefit. The GBRA mechanism safeguards customers—absent special circumstances, the costs recovered through the GBRA cannot exceed the estimated construction costs approved in the need determination proceedings, which the Commission has already determined is the most cost-effective alternative. Further, witness Barrett testified that if actual costs upon completion are lower than projected, customer rates are automatically lowered. Customers also experience an additional reduction in fuel charges at the time the plants come into service.
Regarding Citizens’ argument that FPL did not demonstrate a need for the rate base adjustments, the costs associated with these units were thoroughly reviewed and approved by the Commission in prior need determination proceedings. Witness Deason testified that “the rigors of cost review and operational scrutiny was as great or greater in the need determinations as the level of review and scrutiny when those plants were placed in rate base in a rate case.” Need determination proceedings involve an extensive analysis of the costs of generation projects, and FPL effectively proved that the projects would improve customer bill affordability. Finally, when implemented, the GBRAs will not increase FPL‘s ROE above 10.5%. Accordingly, competent, substantial evidence supports the Commission‘s conclusion that the GBRAs are in the public interest and are part of a reasonable compromise of all the issues.
4. Amortization of Dismantlement Reserves Results in Unfair Rates
Citizens also argues that the proper purpose of amortization of a reserve is to eliminate intergenerational inequity, not enhance earnings as done here. Thus, Citizens argues that this provision is not a reasonable resolution of the disputed issues and results in unfair rates. As demonstrated below, there is competent, substantial evidence supporting the reasonableness of the amortization of the dismantlement reserve.
Witness Dewhurst testified that the “ability to flexibly amortize certain non-cash expense credits or debits over the period of an agreement has been used on multiple occasions,” and that “this flexibility is motivated in part by the economic life extension of the three major generation sites that FPL is currently modernizing, effectively deferring much further into the future the need to utilize a portion of the dismantlement reserve.” Witness Barrett testified:
FPL‘s dismantlement reserve for the Modernization Project sites contains amounts collected for dismantlement costs that have now been deferred substantially beyond the timeframe assumed in the currently authorized accruals. Thus, it does not violate the matching principle to provide an accelerated return of a portion of the dismantlement reserve to the customers who have been funding it. That is, in fact, precisely the effect of the dismantlement reserve amortization in the Proposed Settlement Agreement.
He also noted that the use of an accelerated amortization coupled with a reserve surplus position was advocated by Citizens in FPL‘s last rate case proceeding. It was also advocated by Citizens in FPL‘s 2002
Witness Kollen also testified regarding this provision. Kollen testified that the provision was in the public interest because: (1) the settlement avoids future rate base increases over the next four years by allowing FPL to amortize the remainder of the depreciation surplus and a portion of the dismantlement reserve previously recovered from customers to maintain its ROE within the range established in these proceedings subject to an amortization limit of $400 million; (2) it ensures that customers retain the full amount of the excess depreciation reserve that actually existed on December 31, 2012, if it is greater than the amount projected by FPL and, if the actual amount is less than FPL projected, FPL bears the risk; and (3) continued amortization of the excess depreciation reserve returns the excess amounts collected in prior years to customers over a shorter period of time than if the excess depreciation reserve were returned to customers over the remaining lives of the underlying assets as reflected in FPL‘s approved depreciation rates. Accordingly, there is competent, substantial evidence supporting the reasonableness of the amortization of the dismantlement reserve.
5. Postponement of Depreciation and Fossil Dismantlement Studies is not Part of a Reasonable Compromise and Results in Unfair Rates
Although fossil dismantlement studies were not a major component of the settlement agreement noted in the final order, there is competent, substantial evidence supporting the conclusion that this provision contributes to a reasonable resolution of all the issues, is in the public interest, and does not result in unfair rates.
Witness Barrett testified that this provision was in the public interest because rate stability and predictability were important in this settlement and FPL has agreed to manage currently unknown and unanticipated cost and revenue changes during the next four years without the ability to file an application for a change in rates. Thus, according to Barrett, FPL could not commit to a settlement with fixed base rates, while assuming the risk of depreciation or dismantlement accrual increases during the settlement term. Barrett also explained that it would be unreasonable to expect customers to have fixed base rates if FPL‘s depreciation accruals were reduced.
Witness Kollen also testified that this provision was in the public interest because “it is essential to ensure that [FPL] and its customers both obtain the benefit of the settlement bargain and the relationship between base revenues and the expenses used to support the base revenue requirement. . . .” Further, Kollen testified that “[because the settlement precludes a change in base rates to reflect changes in depreciation expense] there should be no change in depreciation rates during the next four years. . . .” Kollen also reiterated Barrett‘s testimony that it would be unfair for either customers or FPL to commit to fixed rates and then have dismantlement accrual increases or decreases that normally would be accompanied with a change in rates. Accordingly, competent, substantial evidence supports the Commission‘s conclusion that this provision is part of a reasonable resolution of all the issues resulting
6. The Asset Optimization and Gains Sharing Provision is not Part of a Reasonable Resolution of All the Issues
Citizens argues that this provision authorizes FPL to exact “bonuses” from customers for fundamental service activities that FPL already provides. Further, Citizens argues that FPL‘s customers would have paid FPL $47 million for economy power purchases between 2001 and the present if FPL‘s proposal had been in place during those years. Thus, according to Citizens, no reasonable mind would regard this provision as competent, substantial evidence supporting the conclusion that the settlement is a reasonable compromise of counterbalancing provisions. As demonstrated below, competent, substantial evidence demonstrates that this provision is part of a reasonable resolution of all the issues, is in the public interest, and does not result in unfair rates.
Witness Sam Forrest, Vice President of Energy Marketing and Trading at FPL, testified that the asset optimization provision in the settlement agreement overhauls an incentive program that was created in 2000. He also testified that from 2001 to 2011, FPL delivered approximately $158 million in benefits to customers while sharing in just under $2 million, but has not shared any benefits since 2006. He testified that the mechanism seeks to enhance the existing one by expanding the focus of the incentives to encourage FPL to pursue a wider range of gains for the benefit of customers. Further, it would update the sharing threshold to provide a more meaningful opportunity for FPL to share in the benefits that it delivers to customers, but only if FPL is successful in delivering additional value to customers.
Specifically, under the terms of the agreement, customers will receive 100% of the gain on wholesale power purchases and sales up to $46 million annually, and gains above the $46 million will be shared between FPL and customers. Witness Dewhurst testified that “this term will encourage FPL to seek greater value for customers.” Witness Forrest also testified that the five years chosen by Citizens’ witness at the hearing show that FPL only received 0.38% of the total benefits in incentives under the current mechanism, which was insufficient to provide incentives to FPL. Under the new agreement during those same five years, customers would have received approximately 84% of the total benefits. Further, over the full eleven years in which the current incentive mechanism has been in place, FPL customers would have received more than 90% of the total benefits. Thus, according to witness Forrest, this proposed incentive mechanism does not unreasonably favor FPL.
Customers stand to make almost $11 million more in optimization benefits than they would otherwise receive without the new incentive mechanism. Additionally, witness Kollen testified that the provision is in the public interest because as the three modernization projects are completed, FPL should be able to reduce wholesale power purchases and increase sales. Thus, these gains will partially offset the GBRAs. Moreover, this is a four-year pilot program, which the Commission has the option to review after two years. If the Commission determines at that time that the program is unsatisfactory, it may terminate the program. Accordingly, the Commission‘s conclusion that the asset optimization incentive program is in the public interest and part of a reasonable resolution of disputed issues is supported by competent, substantial evidence.
D. Unfair and Unreasonable Rates are not in the Public Interest and the Commission‘s Approval of Them Exceeded the Limits of its Discretion
The determination of what is in the public interest rests exclusively with the Commission. See
CONCLUSION
Based on the foregoing, Citizens has not demonstrated that the Commission violated the essential requirements of the law or committed a material error in procedure by approving the negotiated settlement agreement over Citizens’ active objection, Citizens’ due process rights were not violated, and the Commission‘s findings and conclusions are supported by competent, substantial evidence and are not clearly erroneous. For these reasons, we affirm the Commission‘s final order approving the settlement agreement authorizing FPL to adjust its rates.
It is so ordered.
PARIENTE, LEWIS, CANADY, POLSTON, and PERRY, JJ., concur. QUINCE, J., concurs in result only.
NOT FINAL UNTIL TIME EXPIRES TO FILE REHEARING MOTION, AND IF FILED, DETERMINED.
An Appeal from the Florida Public Service Commission
James Ray Kelly, Public Counsel, Joseph Allan McGlothlin, Associate Public Counsel, Charles John Rehwinkel, Deputy Public Counsel, and Patricia Ann Christensen, Associate Public Counsel, Office of Public Counsel, Tallahassee, Florida, for Appellant
S. Curtis Kiser, General Counsel, Samantha M. Cibula, Attorney Supervisor, and Rosanne Gervasi, Senior Attorney, Tallahassee, Florida, for Appellee Florida Public Service Commission
Jon Cameron Moyle, Jr., Moyle Law Firm, Tallahassee, Florida, and Kenneth L. Wiseman and Mark F. Sundback, Andrews Kurth, L.L.P., Washington, District of Columbia, for Appellee Florida Industrial Power Users Group and South Florida Hospital and Health Care Association
John T. Butler, Assistant General Counsel-Regulatory and Maria Jose Moncada, Principal Attorney, Florida Power and Light Company, Juno Beach, Florida, and Alvin Bruce Davis and Raul B. Mañón, Squire Sanders (US) LLP, Miami, Florida, for Appellee Florida Power and Light Company
Julie Nepveu, AARP Foundation Litigation, Washington, District of Columbia, and Jack L. McRay, AARP Florida, Tallahassee, Florida, for Amicus Curiae AARP
Notes
Mayo, 333 So. 2d at 7-8 (footnote omitted). Ultimately, however, the Court remanded the case for further action because there were inadequate findings in the Commission‘s orders and there was a “material error in procedure” which “affected both the fairness and the correctness of the interim rate proceeding.” Id. at 8-9.Since the defect is not of constitutional significance, and despite the fact that public counsel was misled, we believe that it would be unduly harsh to punish Gulf Power by directing a refund of charges collected between December 30, 1974 and March 2, 1975. The Commission‘s procedural defect does not alone establish a failure by Gulf Power to justify the interim award. The test to be met is and was whether, from the record, Gulf Power developed substantial and competent evidence to sustain the interim award after the Commission first rejected its proposed rate increase as “unjust, unreasonable, unduly discriminatory or preferential, or otherwise unlawful.” On this point we simply lack sufficient information to proceed.