History
  • No items yet
midpage
Shirley's Iron Works, Inc. v. City of Union
403 S.C. 560
| S.C. | 2013
Read the full case

Background

  • The SPPA and TCA interplay are at issue after subcontractors Shirley’s Iron Works and Tindall were unpaid on a City project where Gilbert Group was the general contractor and no payment bond was secured.
  • The City did not require a payment bond and offered a $25,000 settlement to each Respondent; they refused and funds were reallocated to other unpaid subcontractors.
  • Respondents sued in 2003 alleging SPPA violations and later asserted third-party beneficiary, tort, breach-of-contract, quantum meruit, and fees claims; the City answered and Gilbert was joined as a third-party defendant.
  • Lower courts: summary judgment for the City; court of appeals reversed, holding SPPA created a tort remedy and the law-of-the-case theory could support third-party beneficiary breach claims.
  • Sloan I held SPPA applies to subcontractors and implies liability for breach of contract, but not a private tort action; it later clarified the extent of liability under SPPA, leading to questions on law-of-the-case and third-party beneficiary theories.
  • This Court grants certiorari and affirms in part, reverses in part, and remands to address only the surviving third-party beneficiary breach of contract claim.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Does SPPA create a private tort action against a government entity? Respondents rely on Sloan I to allow tort recovery for SPPA breach. TCA provides the exclusive remedy for torts against government; SPPA creates contract-based protection, not a tort. SPPA does not provide a private tort action against a government entity.
Is the SPPA claim actionable as a contract-based, third-party beneficiary breach of contract? Subcontractors are direct third-party beneficiaries to the City–Gilbert contract because SPPA bonding was mandated and incorporated. No valid third-party beneficiary breach theory under SPPA as a tort or independent cause of action; claim should fail. SPPA supports a third-party beneficiary breach of contract claim against the government.
Did the law-of-the-case doctrine bar Respondents' third-party beneficiary claim? Judges Short and John implicitly resolved the third-party beneficiary issue as part of the City’s liability framework. Previous orders did not resolve the third-party beneficiary issue; law-of-the-case does not foreclose it. Law-of-the-case does not foreclose the third-party beneficiary breach of contract claim.
Whether quantum meruit recovery was proper given an express contract exists? Respondents may recover under quantum meruit for partial performance when the contract remains in force. Quantum meruit is improper where an express contract governs the dispute. Reversed as to quantum meruit; reinstated summary judgment for the City on that claim.
Should the case be remanded or resolved on the remaining issues? Liability under the surviving SPPA-based third-party beneficiary claim should be determined. Issues can be resolved on remand with proper focus on SPPA-based liability. Remand to resolve liability and damages limited to the surviving third-party beneficiary contract claim.

Key Cases Cited

  • Sloan Constr. Co. v. Southco Grassing, Inc., 377 S.C. 108 (2008) (SPPA compatibility; private tort action not required; government liable for breach of contract only)
  • Sloan Constr. Co. v. Southco Grassing, Inc. (Sloan II), 395 S.C. 164 (2011) (governmental duty to maintain payment bond not continuing; remand guidance limited)
  • A.E.I. Music Network, Inc. v. Bus. Computers, Inc., 290 F.3d 952 (7th Cir. 2002) (bonding requirements create contract-based protections and third-party beneficiary rights)
  • Hawkins v. City of Greenville, 358 S.C. 280 (Ct. App. 2004) (TCA limitations; no private tort remedy for SPPA enforcement)
  • Proctor v. Dep’t of Health & Envtl. Control, 368 S.C. 279 (Ct. App. 2006) (TCA exclusive civil remedy; no tort claims against government for SPPA duties)
  • State v. McKnight, 352 S.C. 635 (2003) (presumption of knowledge of prior legislation; legislative intent considerations)
Read the full case

Case Details

Case Name: Shirley's Iron Works, Inc. v. City of Union
Court Name: Supreme Court of South Carolina
Date Published: May 29, 2013
Citation: 403 S.C. 560
Docket Number: Appellate Case No. 2010-170066; No. 27256
Court Abbreviation: S.C.