This appeal by A.E.I. Music Network, Inc., a subcontractor, from the dismissal of its diversity- suit against the Chicago Board of Education (the other defendants having dropped out of the case) presents questions of Illinois contract and construction law. The Board had hired Business Computers, Inc. (BCI) to install an audio-visual system in a high school, and BCI had subcontracted a part of the job to A.E.I. A.E.I. did the work called for in the subcontract but was not paid by BCI, which is broke. The Illinois Bond Act requires a public entity such as the Chicago Board of Education to require its contractors to.post bonds to assure the payment of any money owed by the contractors to their subcontractors. 30 ILCS 550/0.01
et seq.; MQ Construction Co. v. Intercargo Ins. Co.,
The applicability of the 180-day statute of limitations to a suit by a subcontractor complaining about a public agency’s having failed to require the contractor to post a bond has divided Illinois’s intermediate appellate court.
Shaw Industries, Inc. v. Community College Dist. No. 515, supra,
The requirement of posting a bond is found in section 1 of the Bond Act, 30 ILCS 550/1. The 180-day statute of limitations is found in section 2. Id., 550/2. That statute of limitations is applicable, however, by the very terms of section 2, only to “a claim for labor, and material^] as aforesaid”—and the claim to which “aforesaid” refers, further up in the section, is “the right to sue on such bond,” that is, the bond required by section 1. Section 2 couldn’t be clearer: “every person furnishing material or performing labor, either as an individual or as a subcontractor for any contractor, with the State, or a political subdivision thereof where bond or letter of credit shall be executed as provided in this Act, shall have the right to sue on such bond or letter of credit in the name of the State.” 30 ILCS 550/2 (emphasis added).
In short, the 180-day statute of limitations is applicable only to a suit on the bond. AE.I.’s suit against the Board of Education is not a suit on the bond. There is no bond, and so the statute is inapplicable. Cf.
Arbanis v. Noslo Engineering Consultants, Inc.,
The Board concedes that violations of section 1 of the Bond Act were not intended to be remediless. But it rightly insists that the remedy cannot be a suit on a nonexistent bond. Nor is there any indication of a statutory remedy except under the mechanic’s lien statute, and the remedy under that statute is unavailable if the public entity that should have required a
*955
bond for the protection of subcontractors has already paid the contractor, at least if the subcontractor failed, as A.E.I. did, to notify the public entity before it paid the contractor. See 770 ILCS 60/23(b);
Walker Process Equipment v. Advance Mechanical Systems, Inc.,
The natural remedy in such a case is a suit for breach of contract by the subcontractor against the public entity. The requirement of posting a bond found in section 1 of the Bond Act is read into every construction contract of a public entity,
Shaw Industries, Inc. v. Community College Dist. No. 515, supra,
Against this conclusion the Board argues that A.E.I. was merely an “incidental” and not a “direct” beneficiary of the Board’s contract with BCI. Third parties, that is, persons who are not parties to a contract, are permitted to enforce the contract if and only if the parties made clear in the contract an intention that they be permitted to do so.
XL Disposal Corp. v. John Sexton Contractors Co.,
In a ease such as this, in which the legislature interpolates a contractual term *956 that the parties are not free to vary, the relevant intentions are no longer those of the parties but those of the legislature. The Illinois legislature wants construction contracts made by public entities to protect the subcontractors. It must have realized that the only persons who would have a financial interest in enforcing a term forced on the contracting parties for the protection of the subcontractors would be—the subcontractors. So the carrying out of the purposes of the contract, one purpose being that of the, legislature to protect subcontractors, requires that the subcontractors be able to enforce the contract. Nothing more is required to make them “direct” third-party beneficiaries, entitled to sue.
The fact that A.E.I. was not named in the contract is thus irrelevant. E.g.,
Altevogt v. Brinkoetter, supra,
Might there be some basis for subjecting the implied provision of the contract requiring the posting of a bond to the 180-day statute of limitations in the Bond Act, when the rest of the contract is subject to a 4-year statute of limitations? None is suggested, and we cannot think of any ourselves. The reason for the short statute of limitations in the Bond Act may be that the public entity which let the contract and required the contractor to post a bond has an interest in minimizing the cost of the bond (which is likely to be passed on to the public entity in the form of a higher contract price) by protecting sureties against late claims. That interest falls away when there is no bond and so no surety in the picture. Or the reason for the short statute of limitations may be to enable the prime contractor to get paid sooner, since until the bond expires the public agency may be reluctant to pay him lest the subcontractors seek a remedy against the agency. That interest also is not engaged when there is no bond.
At the oral argument of the appeal the Board’s lawyer surprised us by arguing that A.E.I.’s suit is barred by the principle that contracts implied in fact cannot be enforced against public entities. The argument was waived by not being made in the Board’s brief, but is in any event without merit because the contract between the Board and BCI was not one implied in fact; it was an express contract with an implied term. A contract implied in fact is not an express contract that may have, as most contracts do, implied terms, such as the duty of good faith, which is read into every contract governed by Illinois law, e.g.,
J & B Steel Contractors, Inc. v. C. Iber & Sons, Inc.,
The reluctance to enforce contracts implied in fact against public agencies, like the parallel reluctance to apply notions of estoppel against such agencies,
Cities Service Oil Co. v. City of Des Plaines,
So AE.I.’s contract claim was incorrectly rejected on statute of limitations grounds and we turn now to its mechanics-lien claim. A lien is a method of attaching, in effect freezing, some designated property or fund, and so if there is no property or fund for the lien to seize hold of, there can’t be a lien. Hence the requirement that we mentioned at the outset that notice of a lien be filed while the person against whom it is filed still has the property or fund in his possession. See also
People ex rel. Anderson v. Village of Bradley,
The judgment is affirmed in part, reversed in part, and remanded for further proceedings consistent with this opinion.
