History
  • No items yet
midpage
195 Conn.App. 695
Conn. App. Ct.
2020
Read the full case

Background

  • Semac contracted with Skanska to perform all electrical work on a Stamford Hospital expansion; the subcontract price was initially ~$14.8M and, after 38 change orders, the revised contract price used at trial was $19,114,535.
  • On October 19, 2015 Semac sent a "Notice of Cardinal Change," demanding extra money and stating it would stop work if not paid; Skanska declared Semac in default on October 21 and terminated the subcontract on October 22 without giving the 48‑hour cure period set out in the subcontract.
  • Semac sued for wrongful termination and related claims; Skanska counterclaimed for breach, overbilling, and sought setoffs; Skanska also impleaded Semac’s CFO (Pope) and president (Scanlon) for alleged fraud in sworn invoices.
  • The trial court found no cardinal change, concluded Semac materially breached by abandoning the job, but also found Skanska breached by failing to provide the contractual 48‑hour cure period, converting a for‑cause termination into a termination for convenience.
  • The court calculated Semac had completed 65% of the work, computed a termination payment, then offset amounts Semac had been overpaid and amounts improperly billed to obtain a judgment for Skanska of $3,857,130.77 (plus prejudgment interest to a total of $4,262,390.56). The court rejected Skanska’s fraud claim against Pope and Scanlon.

Issues

Issue Plaintiff's Argument (Semac) Defendant's Argument (Skanska) Held
Was there a cardinal change excusing Semac's performance? Delays and resequencing materially altered the character and cost of the electrical work, constituting a cardinal change. The work remained the same in character; delays and coordination problems were contemplated and addressed by contract/change orders. No cardinal change; contract language and change orders show alterations were addressable under the contract; Semac breached by abandoning the job.
Did Skanska materially breach by terminating without a 48‑hour cure period? (Responding) Skanska was required to give the contractual cure period; failure to do so breached the contract. Skanska asserted Semac had repudiated/abandoned the contract and that common‑law doctrines made the cure period inapplicable or futile. Skanska breached: it failed to comply with the unqualified §12.1 cure requirement; common‑law doctrines cannot be used to evade express contract terms.
Were the damages awarded to Skanska proper? (calculation and remedies) Semac argued it was entitled to a termination payment and that the court erred in crediting Skanska for amounts billed/paid. Skanska argued Semac’s breach excused Skanska and entitled it to expectation damages; alternatively, setoff for overpayments and costs to complete were proper. Award upheld: because both breached and Skanska failed to follow the contract, termination became for convenience; the court reasonably calculated Semac’s entitlement by percentage complete and applied offsets for overbilling and unpaid subcontractor amounts.
Did Pope and Scanlon commit fraud by swearing to inaccurate invoices? Semac (and the third‑party defendants) argued their sworn invoices were not fraudulent but improperly managed/accounted. Skanska argued the sworn misrepresentations were false, knowingly made, and induced payment. No fraud: trial court found insufficient clear and convincing evidence of intent or recklessness; credibility findings deferred to the trial judge.

Key Cases Cited

  • Randolph Constr. Co. v. Kings East Corp., 165 Conn. 269 (Conn. 1973) (establishes test for substantial/cardinal change: whether alterations unreasonably alter character of work or unduly increase cost)
  • Air‑A‑Plane Corp. v. United States, 408 F.2d 1030 (Ct. Cl. 1969) (framework for determining whether ordered deviations change the nature of the work contracted for)
  • Pellerin Constr., Inc. v. Witco Corp., 169 F. Supp. 2d 568 (E.D. La. 2001) (cardinal change defined as a drastic modification beyond contract scope, not redressable under contract)
  • Coppola Constr. Co. v. Hoffman Enters. Ltd. P’ship, 157 Conn. App. 139 (Conn. App. 2015) (failure to give contractually required termination notice constitutes material breach)
  • Collins v. Sears, Roebuck & Co., 164 Conn. 369 (Conn. 1973) (court may not rewrite or create new contract terms)
  • Trumbull v. Palmer, 123 Conn. App. 244 (Conn. App. 2010) (fraud elements and heightened clear‑and‑convincing proof standard)
  • McLeod v. A Better Way Wholesale Autos, Inc., 177 Conn. App. 423 (Conn. App. 2017) (appellate deference to trial court credibility and factual findings)
Read the full case

Case Details

Case Name: Semac Electric Co. v. Skanska USA Building, Inc.
Court Name: Connecticut Appellate Court
Date Published: Feb 11, 2020
Citations: 195 Conn.App. 695; 226 A.3d 1095; AC41054
Docket Number: AC41054
Court Abbreviation: Conn. App. Ct.
Log In