The Randolph Construction Company, the appellee in both eases, hereinafter referred to as Randolph, brought suit for work and services performed for Kings East Corporation, the appellant in both cases, hereinafter referred to as Kings. Thereafter, Kings claimed damages as a result of Randolph’s breach of a written contract. The trial court found the issues for Randolph in both cases and Kings has appealed in both cases. The parties agree that a resolution of the issues presented on appeal in the first case will control the disposition of both cases.
Kings has assigned error in several of the court’s conclusions. The trial court’s conclusions are tested by the finding.
1
State
v.
Villafane,
The finding reveals the following facts which are relevant to the claims of the appellant: Kings is a corporation engaged in the business of building
On August 19, 1970, Bandolph’s lawyer wrote Kings asking for a copy of the revised plans. Kings replied that the plans would be ready shortly. On August 27, 1970, Bandolph wrote Kings that since the “agreement between (the parties) is incomplete and . . . there was no full meeting of the minds as to the work that was to be performed by . . . [Bandolph . . . Bandolph] considers that there is no agreement . . . and that the document executed August 5, 1970 ... in failing to reflect the work to be performed, is a nullity.” No plans bearing the date August 5, 1970, were in existence until the latter part of September, 1970. Kings never asked Bandolph to initial any plans, nor did Kings ever give any plans to Bandolph. The final plans prepared in late September differed substantially from the revised plans produced by Lauer in his meeting with Baiti on August 5,1970.
At Kings’ request, Bandolph commenced work on September 30, 1970, and continued to perform work and supply materials to Kings until some time in November, 1970. As a result of nonpayment by Kings, Bandolph withdrew from the job and on November 17, 1970, instituted an action for compensation for labor and materials rendered.
Kings has assigned error essentially in three of the court’s conclusions. The conclusions reached by the trial court are tested by the finding and must
Kings first assigns error in the court’s conclusion that the final plans as actually drawn differed substantially from the work and plans considered by the parties at the meeting on August 5, 1970. This conclusion is supported by the trial court’s finding that the final plans added drawings of fireplaces and the garage exterior, substantially increased the size of piers for the garage and also deviated from the plans as revised by Lauer on August 5, 1970, in nomenclature and cross-reference designations. The issue of substantiality, a determination of whether the enumerated differences in the final plans were substantial, is a question of fact which depends on a consideration of the circumstances. See
Anderson
v.
Yaworski,
Kings next asserts that the trial court erred in concluding that the writing dated August 5, 1970, and signed by the parties was substantially incomplete and a nullity. The question presented by this assignment of error is whether a contract which incorporates documents not yet in existence binds the parties despite substantial changes in the documents when later prepared. Generally, incorporation by reference of existing documents produces a single contract which includes the contents of the incorporated papers. “Where . . . the signatories execute a contract which refers to another instrument in such a manner as to establish that they intended to make the terms and conditions of that other instrument a part of their understanding, the two may be interpreted together as the agreement of the parties.”
Batter Building Materials Co.
v.
Kirschner,
It may be argued that a contract which incorporates nonexisting documents is valid on the condition that the documents be in existence before either party attempts to enforce performance; 4 Williston, Contracts (3d Ed.) § 581; and in some instances, the law will uphold performance requirements beyond those apparent in the plans or specifications of a building contract. See
New England General Contracting Co.
v.
Brennan Stone Co.,
The appellant’s final assignment of error addresses itself to the court’s conclusion that the
There is no error in the first case. Accordingly, as conceded by the parties, there is no error in the second ease.
In this opinion the other judges concurred.
Notes
The appellant assigns error in the finding and specifically attacks the court’s failure to find material facts as set forth in thirty-one paragraphs of the draft finding. Seven of these paragraphs were in fact found or were implicit in the finding. A finding need not be in language identical with the draft finding.
Walsh
v.
Turlick,
The appellant also assigns error in thirteen of the trial court’s findings. Two of these findings constitute conclusions;
Gary Excavating, Inc.
v.
North Haven,
