History
  • No items yet
midpage
Rai Industrial Fabricators, LLC v. Federal Insurance Company
5:16-cv-03674
N.D. Cal.
Oct 23, 2018
Read the full case

Background

  • Sauer contracted with the U.S. Army to design/build a military training complex and subcontracted steel erection to Agate under a December 2014 Erection Subcontract.
  • Subcontract contemplated 121 days for Agate’s work; Agate began March 12, 2015, but alleges it worked 422 days due to design changes and nonconforming steel supplied by Sauer.
  • Agate claims Sauer directed extra work, withheld change orders and time extensions, supplied nonconforming fabricated pieces and disassembled stair components, and refused payment for extra work.
  • Agate’s Second Amended Counterclaim (SAC) asserts breach of contract, delay/disruption, unjust enrichment, a claim labeled “Palpable Unilateral Mistake,” and breach of the implied covenant of good faith and fair dealing.
  • Sauer moved to dismiss the “Palpable Unilateral Mistake” claim and the implied covenant claim under Rule 12(b)(6).
  • The Court granted dismissal of the unilateral mistake claim (without leave to amend) and denied dismissal of the implied covenant claim; Sauer was ordered to answer by November 6, 2018.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Validity of "Palpable Unilateral Mistake" claim / rescission Agate alleges Sauer knew Agate’s bid was substantially lower and failed to notify Agate of an obvious mistake, so no contract formed Sauer argues the claim is procedurally improper (no leave to add new claim) and "palpable unilateral mistake" is not a recognized standalone cause of action; Agate did not plead facts showing Agate made a mistake Dismissed: claim improper as new claim and, on merits, not a cognizable independent theory; rescission elements not pleaded; dismissal without leave to amend
Breach of implied covenant of good faith and fair dealing Sauer refused to issue change orders, denied time extensions, withheld payment and thereby frustrated Agate’s contractual benefits Sauer contends the implied covenant claim merely duplicates breach of contract and must allege conduct beyond a contractual breach Denied: SAC alleges conduct (refusal to approve change orders/time extensions, forcing Agate to finance extra work) that could show interference with Agate’s rights and expectations; claim is sufficiently pleaded to proceed

Key Cases Cited

  • Ashcroft v. Iqbal, 556 U.S. 662 (pleading standard: plausible claim required)
  • Donovan v. RRL Corp., 26 Cal.4th 261 (elements for rescission based on mistake)
  • M.F. Kemper Constr. Co. v. City of Los Angeles, 37 Cal.2d 696 (discussion of unilateral mistake and rescission)
  • Careau & Co. v. Security Pacific Business Credit, Inc., 222 Cal. App. 3d 1371 (implied covenant requires conduct beyond mere contract breach)
  • Metcalf Const. Co., Inc. v. United States, 742 F.3d 984 (duty not to hinder and duty to cooperate as aspects of implied covenant)
Read the full case

Case Details

Case Name: Rai Industrial Fabricators, LLC v. Federal Insurance Company
Court Name: District Court, N.D. California
Date Published: Oct 23, 2018
Docket Number: 5:16-cv-03674
Court Abbreviation: N.D. Cal.