History
  • No items yet
midpage
Portland General Electric Co. v. Federal Energy Regulatory Commission
2017 U.S. App. LEXIS 7222
| D.C. Cir. | 2017
Read the full case

Background

  • PáTu Wind Farm (9 MW, qualifying PURPA small power producer) sells power to Portland General Electric under an OPUC‑approved "off‑system" standard power‑purchase agreement; PáTu’s output is transmitted via Wasco and Bonneville to Portland’s Troutdale substation.
  • PáTu contends Portland must purchase all energy PáTu "produces" (including unscheduled or real‑time output) and that Portland must use dynamic scheduling (dynamic transfer) to accept that variable output.
  • Portland requires day‑ahead whole‑MW schedules and pays avoided‑cost rates only for scheduled deliveries; unscheduled shortfalls/overages are settled at market rates or must be made up, per Portland’s practice.
  • OPUC concluded Portland must purchase all power PáTu delivers but saw no contractual requirement for dynamic scheduling; Oregon Court of Appeals affirmed without opinion.
  • PáTu petitioned FERC, arguing PURPA (18 C.F.R. § 292.303(a)) requires purchase of any energy made available and that Portland’s refusal to provide dynamic scheduling and alleged discriminatory conduct violated FERC rules; FERC ordered Portland to accept PáTu’s entire net output but declined to require dynamic scheduling and dismissed FPA discrimination/standards‑of‑conduct claims.
  • Portland and PáTu separately sought review in this Court; court consolidated petitions, dismissed Portland’s petition for lack of jurisdiction and denied PáTu’s petition on the merits.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Does this Court have jurisdiction to review Portland’s challenge to FERC’s PURPA order? Portland: FERC’s order is mandatory and fixes rights, so directly reviewable under FPA § 313(b) via the Midland exception. FERC: Order is declaratory/advisory (no deadline or enforcement consequence), so not reviewable here. Dismissed for lack of jurisdiction: the orders are non‑binding/declaratory per Midland, so § 313(b) review is unavailable.
Did FERC properly interpret PURPA to require Portland to purchase PáTu’s entire net output? PáTu: PURPA and the PPA require purchase of all energy produced/delivered; dynamic scheduling is needed to effectuate that duty. Portland: Purchase obligation is governed by state contract/scheduling rules; FERC cannot impose methods like dynamic scheduling on a state‑regulated contract. FERC’s interpretation stands: Portland must accept PáTu’s entire net output as a matter of PURPA obligations, but FERC declined to mandate dynamic scheduling.
Can FERC require Portland to provide dynamic scheduling or is that a transmission‑service (FPA) issue? PáTu: Denial of dynamic scheduling is discriminatory and violates FPA anti‑discrimination and standards‑of‑conduct rules. Portland/FERC: Dynamic scheduling is transmission service territory; PáTu is not Portland’s transmission customer (Wasco/Bonneville are), so those FPA rules do not apply. Denied: FERC properly rejected claims under FPA anti‑discrimination and standards‑of‑conduct rules because PáTu is not Portland’s transmission customer; FERC may enforce PURPA purchase obligations but need not prescribe dynamic scheduling.
Did FERC err by rejecting PáTu’s procedural filing requesting tariff modification for dynamic scheduling? PáTu: Filing should have been considered, not rejected as an impermissible "answer to an answer." FERC: The submission functionally was an answer to an answer and was barred by procedural rule; agency interpretation of its rules controls. Denied: Court defers to FERC’s reasonable interpretation and application of its procedural rule; PáTu did not challenge that interpretation as unreasonable.

Key Cases Cited

  • FERC v. Mississippi, 456 U.S. 742 (discussing PURPA’s purposes and state enforcement role)
  • American Paper Institute, Inc. v. American Electric Power Service Corp., 461 U.S. 402 (explaining PURPA’s encouragement of cogeneration and small power production)
  • Niagara Mohawk Power Corp. v. FERC, 117 F.3d 1485 (describing PURPA’s self-contained scheme)
  • Midland Power Co‑op. v. FERC, 774 F.3d 1 (holding declaratory FERC PURPA orders without enforcement consequences are not reviewable under FPA § 313(b))
  • Industrial Cogenerators v. FERC, 47 F.3d 1231 (explaining enforcement channeling of PURPA § 210(h) into FPA district‑court scheme)
  • New York v. FERC, 535 U.S. 1 (describing FERC’s FPA jurisdiction over wholesale sales and transmission)
  • Consumers Energy Co. v. FERC, 428 F.3d 1065 (deference to FERC interpretations of its own orders)
Read the full case

Case Details

Case Name: Portland General Electric Co. v. Federal Energy Regulatory Commission
Court Name: Court of Appeals for the D.C. Circuit
Date Published: Apr 25, 2017
Citation: 2017 U.S. App. LEXIS 7222
Docket Number: 15-1237 Consolidated with 15-1275
Court Abbreviation: D.C. Cir.