Opinion for the Court filed by Senior Circuit Judge WILLIAMS.
The Federal Energy Regulatory Commission issued an order directing Midland Power Cooperative, an Iowa electric utility, to “reconnect” to a wind generator within its territory.
Swecker v. Midland Power Cooperative,
The orders under review arise out of a prolonged dispute between Gregory and Beverly Swecker and Midland. The Sweckers own and operate on their Iowa farm a 65kW wind generator that is classified as a qualifying facility (“QF”) under § 210 of the Public Utility Regulatory Policies Act of 1978 (“PURPA”), Pub.L. 95-617, 92 Stat. 3144 (codified at 16 U.S.C. § 824a-3). QFs comprise cogenerators (which produce both electricity and steam or some other form of useful energy) and “small power production facilities]” (which have a production capacity of no more than 80 megawatts and rely on various forms of renewable resources). 16 U.S.C. §§ 796(18)(A), 796(17)(A); see also
FERC v. Mississippi,
Section 210 and the ensuing regulatory scheme require Midland to be ready to purchase power from the Sweckers’ QF and also to supply them with retail power. The parties have long fought over the proper calculation of “avoided cost.” The Sweckers, in response to Midland’s failure to pay what they view as the correct rate, stopped paying Midland for retail power. By the fall of 2011 they claimed that Midland owed them some $60,000 and acknowledged an accumulated unpaid bill from Midland of about $600. Their failure to pay the retail bill led Midland, after giving notice and securing the approval of the Iowa Utilities Board, to begin procedures to disconnect the Sweckers. As Midland’s purchases from the Sweckers are effected through the same interconnection as its supply of retail power, the disconnection had the effect of ending Midland’s purchases as well. The Sweckers filed notice of the disconnection with FERC and requested an expedited order of reconnection.
Midland naturally contends we have jurisdiction, and FERC appears to acquiesce (except for a claim that petitioners failed to “urge[ ]” the issues adequately in their petitions for rehearing, a claim we need not address). But we are, of course, obliged to address the question on our own.
Basardh v. Gates,
There are two apparent avenues to our jurisdiction, the first one directly through the Federal Power Act’s provision for review (§ 313(b) of the FPA, 16 U.S.C. § 825i(b)), the second via PURPA § 210’s provision on “enforcement,” 16 U.S.C. 824a-3(h), which is said by Midland to forge a link to § 313(b). We take the theories in that order.
Section 313(b) of the FPA reads as follows as it appears in the United States Code:
(b) Judicial review
Any party to a proceeding under this chapter aggrieved by an order issued by the Commission in such proceeding may obtain a review of such order in the United States court of appeals for any circuit wherein the licensee or public utility to which the order relates is located or has its principal place of business, or in the United States Court of Appeals for the District of Columbia....
FPA § 313(b), 16 U.S.C. § 825Z(b) (emphasis added). Section 210 of PURPA is codified within the same chapter as § 313 (chapter 12 of title 16). Thus, at first glance, Midland appears to be the exact sort of party “aggrieved by an order” entitled to review in the court of appeals.
But as enacted in the Statutes at Large, § 313 uses the word “Act” where the codifiers used the word “chapter.” See 49 Stat. 860 (“Any party to a proceeding under this Act aggrieved by an order ... ”). In cases, like this, where the two versions conflict, the rule is that the Statutes at Large version controls. “Though the United States Code is ‘prima facie’ evidence that a provision has the force of law, 1 U.S.C. § 204(a), it is the Statutes at Large that provides the ‘legal evidence of laws,’ § 112....”
United States Nat’l Bank of Ore. v. Independent Ins. Agents of America, Inc.,
(h) Commission enforcement
(1) For purposes of enforcement of any rule prescribed by the Commission under subsection (a) of this section with respect to any operations of an electric utility, a qualifying cogeneration facility or a qualifying small power production facility which are subject to the jurisdiction of the Commission under part II of the Federal Power Act [16 U.S.C. § 824 et seq.], such rule shall be treated as a rule under the Federal Power Act [16 U.S.C. § 791a et seq.]....
(2)(A) The Commission may enforce the requirements of subsection (f) of this section against any State regulatory authority or nonregulated electric utility. For purposes of any such enforcement, the requirements of subsection (f)(1) of this section shall be treated as a rule enforceable under the Federal Power Act [16 U.S.C. § 791a et seq.]. For purposes of any such action, a State regulatory authority or nonregulated electric utility shall be treatéd as a person within the meaning of the Federal Power Act. No enforcement action may be brought by the Commission under this section other than-
(i) an action against the State regulatory authority or nonregulated electric utility for failure to comply with the requirements of subsection (f) of this section or
(ii) an action under paragraph (1).
(B) Any electric utility, qualifying co-generator, or qualifying small power producer may petition the Commission to enforce the requirements of subsection (f) of this section as provided in subparagraph (A) of this paragraph. If the Commission does not initiate an enforcement action under subparagraph (A) against a State regulatory authority or nonregulated electric utility within 60 days following the date on which a petition is filed under this subparagraph with respect to such authority, the petitioner may bring an action in the appropriate United States district court to require such State regulatory authority or nonregulated electric utility to comply with such requirements, and such court may issue such injunctive or other relief as may be appropriate. The Commission may intervene as a matter of right in any such action.
PURPA § 210(h), 16 U.S.C. § 824a-3(h).
Midland argues that the orders here “create new rules” regarding disconnections of retail service for customers’ nonpayment (and do so without using notice- and-comment rulemaking), and that they then purport to enforce these rules directly against Midland, “rather than bringing action in federal court as required” by § 210. Petitioners’ Br. 5. Midland fits these acts into FPA § 313(b) by invoking § 210(h)(2)(A)’s provision that “the requirements of subsection (f)(1) of [§ 210] shall be treated as a rule enforceable under the Federal Power Act.” Id. If FERC’s orders put in issue the application of a “rule under the Federal Power Act,” it argues, then FPA § 313(b) provides for review in the court of appeals.
There are several difficulties with this theory. An initial one is that § 210(f)(1) addresses only rules prescribed by the Commission relating to the implementation of § 210 by state regulatory authorities vis-a-vis any “electric utility for which it has ratemaking authority,” and Midland is not such a utility. See Joint Appendix 12; Petitioners’ Br. 14. Moreover, § 210(h)(2)(A) provides for treatment of § 210(f)(1) requirements “as a rule en
But most obviously fatal is that FERC never purported to adopt a general rule on disconnections by utilities whose customers refused to pay their bills (or conditioned payment of their bills on concessions regarding “avoided cost”). Midland cites no rule-creating language in either of the orders.
Rather than announcing a new general rule, FERC noted in its Order on Rehearing that the EPAct of 2005 had expanded its powers. Its most articulate explanation of its “reconnect” order reads as follows:
Prior to the Commission’s implementation of section 210(m) of PURPA, which was added to PURPA by EPAct 2005, the Commission, as Midland points out, in practice left issues regarding disconnection of QFs for nonpayment of bills to state regulatory authorities or no-nregulated utilities. In implementing EPAct 2005, however, the Commission addressed, and provided specific regulations on, how an electric utility may terminate its obligations to purchase from and sell to QFs.
Order on Rehearing,
It is true that the addition of subsection (m) to § 210 (via the EPAct of 2005) conferred on FERC new authority relating to the QFs that § 210 benefits. See, e.g., § 210(m)(3) (authorizing FERC review of utilities’ applications for relief from mandatory purchase obligations on a territory-wide basis and allowing the Commission to “make a final determination” on whether applicant met the specified conditions); § 210(m)(4) (stating that FERC “shall issue an order” reinstating an obligation to purchase under specified conditions). But those changes have no effect on our jurisdiction here (even if they might do so in other cases). While the Commission developed regulations implementing the EPAct of 2005,
New PURPA Section 210(m) Regulations Applicable to Small Power Prod. & Cogeneration Facilities,
Further, our prior decisions addressing jurisdiction to review FERC orders under § 210 have repeatedly emphasized Congress’s decision to leave § 210’s enforcement to the district court (subject to review in the relevant court of appeals). In the first of these,
Industrial Cogenerators v. FERC,
The FERC implements § 210 by promulgating rules designed to encourage cogeneration and small power production, 16 U.S.C. § 824a — 3(a)—(c); those rules are in turn implemented by state regulatory authorities and by “each no-nregulated electric utility.” 16 U.S.C. § 824a-3(f). If an entity of either type fails to implement the FERC rules, then the Commission may, upon its own motion or upon petition, bring an enforcement action in district court to ensure compliance with the Act; if the Commission fails to act upon a petition for enforcement, then the petitioner may itself bring such an action. 16 U.S.C. § 824a-3(h)(2)(B). The PURPA does not provide any other means by which the FERC or a petitioner can force a state regulatory authority or a nonregulated utility to comply with § 210 of the Act.
Id.
at 1232. Throughout the opinion we stressed Congress’s decision to vest enforcement of § 210 exclusively in the dis
Industrial Cogenerators
explicitly left open the possibility of direct review in the court of appeals of FERC orders under § 210 that “embody[ ], for example, a rule of general application, not tied to a particular set of facts....”
We note that on a number of occasions we have in fact directly reviewed FERC decisions under § 210. See
American Forest & Paper Ass’n v. FERC,
A special characteristic of the orders at issue in
Industrial Cogenerators
and its sequels might serve as a basis for distinction — namely, that the disputed FERC decision was “much like a memorandum of law,” see
Industrial Cogenerators,
FERC has, however, manifested no intent that its orders here would be so far out of the line of its ordinary § 210 orders. The initial “ordering paragraph” mentions neither any deadline by which it expected Midland to comply nor any possible consequence of non-compliance. The reasoning in the Order on Rehearing, quoted above, manifested no intent to go beyond a statement of FERC’s views of Midland’s obligations. Oral argument tended only to confirm this reading.
FERC counsel: [Traditionally, in the PURPA context the Commission would issue a declaratory order and nothing more.
Court: Was it not issuing an order on penalty of contempt?
FERC counsel: The order does not say that. Yes, there’s one ordering paragraph that says Midland shall reconnect, it doesn’t have a time period by which Midland has to comply, it doesn’t-say it’s under penalty, and in fact, in that same order they are, the Commission is ordering settlement procedures to try to get the parties to work this out.
Oral Arg. Tr. 23. Similarly, FERC counsel said, “[A]ny time FERC orders anyone to do anything!,] that is only enforceable in District. Court, the same would be true here.”
Id.
at 21. It is true that when asked how a recipient of such an order is “supposed to think,” FERC counsel replied, “I would treat it as mandatory, however, they did not seek clarification.” But that answer seems no more than a claim of ambiguity, a claim that counsel’s other answers suggested should be resolved in favor of treating the order as declaratory only. We cannot imagine that a responsible federal regulatory agency would intentionally expose a party to fines up to $1,000,000 a day on the basis of language that left the agency itself so perplexed. Accordingly we need not now resolve
As the case falls squarely within the principles of
Industrial Cogenerators,
we lack jurisdiction to review the orders. As the parties have neither briefed nor argued the question of review in the district court under the Administrative Procedure Act, we express no opinion on the subject. Cf.
Niagara Mohawk Power Corp. v. FERC,
The petition for review is
Dismissed.
