History
  • No items yet
midpage
802 F.3d 876
7th Cir.
2015
Read the full case

Background

  • In 1920 Peoples and Koppers (Beazer’s predecessor) entered a contract creating Chicago By-Product Coke Co. (Coke); Koppers agreed to finance, build, and operate a coke plant at Crawford Station, with Coke issuing bonds and Peoples purchasing the plant’s gas and coke.
  • Koppers operated the plant until 1938; Peoples later acquired Coke’s assets and some site land; decades later EPA and Illinois EPA oversaw investigations and removal actions at Crawford Station.
  • Peoples executed three administrative settlement agreements with EPA (2007 AOC, 2008 AOC, 2011 AOC) and incurred over $70 million in investigation/removal costs.
  • In 2014 Peoples sued Beazer under CERCLA: Count I (cost recovery under §107) and Count II (contribution under §113(f)(3)(B)). Beazer moved to dismiss, arguing a 1920 contract released Koppers from liability and that some claims were time‑barred.
  • The district court dismissed Count I (holding Peoples had an administrative settlement and thus only a contribution claim), dismissed with prejudice contribution claims tied to the 2007/2008 AOCs as time‑barred, and dismissed contribution to the extent based on Koppers’ operator liability; Peoples voluntarily dismissed remaining ownership‑based claim and appealed.
  • On appeal the Seventh Circuit addressed whether the 1920 agreement bars contribution liability for Koppers’ operator role and whether 2007/2008 AOC claims were time‑barred; the court affirmed dismissal based on the 1920 agreement and did not reach the statute‑of‑limitations issue.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Whether the 1920 contract precludes CERCLA contribution for Koppers’ operator liability The 1920 agreement did not clearly and unambiguously release environmental/CERCLA liabilities and thus does not bar contribution The 1920 agreement releases Koppers "without liability of any character," so it bars future environmental/CERCLA contribution claims The contract unambiguously releases Koppers of all liability for operation; contribution claims barred
Whether pre‑CERCLA indemnities must be "unqualified" to cover CERCLA liability Pre‑CERCLA releases must be expressly unqualified to cover CERCLA; paragraph 48 is not sufficiently specific Federal precedent permits broad pre‑CERCLA indemnities that are general enough to include environmental liability Broad language ("without liability of any character") is sufficient to encompass CERCLA contribution
Whether the second sentence of paragraph 48 is an express assumption of liability The sentence (Koppers assumes responsibility for operation/maintenance) shows Koppers expressly assumed operational liabilities The sentence describes scope of Koppers’ operative duties, not a retention of liability; Coke bears expenses/losses The clause describes limited operational duties and is harmonized with the release; it does not negate the release language
Whether the court needed to address §113(f) claims tied to 2007/2008 AOCs given the contract ruling Plaintiffs argued the statute‑of‑limitations ruling was erroneous and should be addressed Defendant argued contract ruling disposed of the case and made limitation analysis unnecessary Because the contract bars contribution, the court declined to reach the statute‑of‑limitations issue for the 2007/2008 AOCs

Key Cases Cited

  • Burlington Northern & Santa Fe Ry. Co. v. United States, 556 U.S. 599 (describing CERCLA’s purpose and liable party classes)
  • PMC, Inc. v. Sherwin‑Williams Co., 151 F.3d 610 (parties may allocate CERCLA expenses by contract)
  • Kerr‑McGee Chem. Corp. v. Lefton Iron & Metal Co., 14 F.3d 321 (pre‑CERCLA indemnity enforceable if it covers later liability)
  • Harley‑Davidson, Inc. v. Minstar, Inc., 41 F.3d 341 (§107(e)(1) allows indemnities though it preserves government’s remedies)
  • SmithKline Beecham Corp. v. Rohm & Haas Co., 89 F.3d 154 (broad pre‑CERCLA language can encompass CERCLA liability)
  • Beazer East, Inc. v. Mead Corp., 34 F.3d 206 (analysis of contractual scope for environmental liabilities)
  • E.I. Du Pont de Nemours & Co. v. United States, 365 F.3d 1367 (government indemnity clause construed to include CERCLA liability)
  • LaSalle Nat’l Trust, N.A. v. ECM Motor Co., 76 F.3d 140 (apply state contract law to construe indemnity clauses)
  • Thompson v. Gordon, 241 Ill.2d 428 (Illinois rule against interpreting contracts to render clauses meaningless)
Read the full case

Case Details

Case Name: Peoples Gas Light and Coke Com v. Beazer East Inc.
Court Name: Court of Appeals for the Seventh Circuit
Date Published: Sep 21, 2015
Citations: 802 F.3d 876; 2015 WL 5535803; 2015 U.S. App. LEXIS 16745; 81 ERC (BNA) 1249; 45 Envtl. L. Rep. (Envtl. Law Inst.) 20180; 14-3634
Docket Number: 14-3634
Court Abbreviation: 7th Cir.
Log In