In 1985, PMC, thе plaintiff in this toxic-waste suit, bought from the defendant, Sher-win-Williams, a plant on the south side of Chicago in which Sherwin-Williams had been manufacturing paints, insecticides, and other chemicals for a century or so. Since 1992, PMC has been required by Illinois’ environmental protection agency to clean up toxic waste discovered at the site, and it faces the prospect of future costs in an unknown amount to comply fully with the agency’s demands. On the authority of sections 107(a) and 113(f)(1) of CERCLA (Comprehensive Environmental Response, Compensation and Liability Act, 42 U.S.C. §§ 9607(a), 9613(f)(1)); RCRA (Resource Conservation and Recovery Act, 42 U.S.C. §§ 6900 et seq.), and the Illinois Contribution Act, 740 ILCS 100/1 et seq., PMC seeks to recover from Sherwin-Williams both the costs that it has incurred and the costs that it will incur. After a bench trial, the district judge awarded essentially all the relief asked for by PMC, including recovery of past costs under the state statute and of future costs under CERCLA; an injunction, largely duplicative of the CERCLA relief, under RCRA directing Sherwin-Williams to assume full responsibility for cleaning up the site; and an award under RCRA of PMC’s attorney’s fees allocable to obtaining the injunction. Basically, the fight is over five clean ups that PMC has already conducted, one costly environmental site-assessment that it conducted in advance of the clean ups, and the costs of whatever future clean ups PMC may be required to conduct.
Both companies, as respectively the owner of the polluted site and the former owner who polluted it, are liable under CERCLA (see 42 U.S.C. § 9607(a)) and other environmental statutes for the expense of cleаning up the site. Parties are free, however, to allocate such expenses between themselves by contract. See, e.g., 42 U.S.C. § 9607(e)(1);
Truck Components Inc. v. Beartrice Co.,
Sherwin-Williams does not question this principle of interpretation or its application to CERCLA, and so we need not pursue the matter further. It argues that the contract of sale did clearly allocate to PMC all clean-up costs that accrued more than two years after the sale. It points to a clause which provides that “all representations, warranties, covenants and obligations contained in this Agreement shall terminate twenty-four (24) months after the Closing Date.” The district judge, however, pointed to another provision of the contract: “S-W expressly recognizes its responsibility for the following matters” — and the matters then set forth include all environmental harms resulting from toxic waste activities at the site before the sale. The judge found no ambiguity in the language of the contract that would *614 justify taking evidence to determine whether the 24-month cut-off might apply to liability for toxic wastes; he thought it evident from the “expressly recognizes” clause that it did not.
We think he was right. Read naturally, the cutоff provision refers to obligations created by the contract itself, such as warranties, rather than to obligations created by law. The former are obligations “contained” in the contract; the latter are not. Sherwin-Williams didn’t want PMC to be bringing a suit for breach of warranty many years after the sale; hence the two-year cut-off. But by the same token PMC didn’t want to be stuck with the liabilities that Sherwin-Williams had incurred as a result of operating a chemical plant. Applying the two-year cut-off to Sherwin-Williams’s statutory obligations would extinguish PMC’s legal rights to obtain from its seller a sharing of the costs of whatever clean-up duties the environmental protection authorities might impose on it. It could be argued that Sherwin-Williams would be unlikely to write PMC a blank check for the cost of cleanup, lest PMC decide to make the site superclean. But against this it could be argued that Sherwin-Williams probably knew better than PMC how polluted the site was and hence could better estimate the cost of cleaning it up, especially since Shеrwin-Williams retained ownership of a property, for which it had clean-up responsibilities, contiguous to the property that it sold to PMC. These speculative arguments cancel, leaving us with contractual language unambiguously supportive of PMC’s interpretation.
Sherwin-Williams wants to introduce evidence that would create an ambiguity. The doctrine of extrinsic (or latent) ambiguity on which it relies (a doctrine that is a part of Ohio law, which the contract provides shall govern any disputes arising under it) rests on a recognition that a contract which might appear to be perfectly clear to someone who read it in ignorance of its context might, once context was restored, seem either unclear, or clear the opposite way. E.g.,
Graham v. Drydock Coal Co.,
But if the doctrine of extrinsic ambiguity were stretched too far, an important function of a written contract — protecting the parties from the vagaries of a judge’s or a jury’s weighing of the parties’ self-serving testimony as to what they
really
meant (opposite to what the contract, seemingly clearly, said) — would be thwarted. This is why, to be admissible to create an ambiguity in a clear-seeming written contract, the extrinsic evidence must be objective.
Mathews v. Sears.Pension Plan, supra,
But it is not enough that a party has
some
objective evidence to offer on the meaning of the contract. The evidence must create a sufficient doubt about what the con
*615
tract means to warrant submitting that meaning to determination by a trial, notwithstanding the apparent clarity of the written word. The three bits of evidence sought to be introduced by Sherwin-Williams do not satisfy this test. Cf.
Mathews v. Sears Pension Plan, supra,
This is not to deny that a contract’s price term can be helpful evidence of the contract’s meaning (and, of course, it’s objective evidence — it is part of the written contract).
Rhone-Poulenc, Inc. v. International Ins. Co.,
The doctrine of extrinsic ambiguity is an exception to the rulé that contracts clear on their face will be enforced as written. It should be interpreted narrowly lest it swallow the rule and make written contracts mere scraps of paper. Unless the evidence sought to be intrоduced not only is objective but would if believed make a compelling case that the contract means other than what it seems to mean, it should be kept out.
We conclude that the contract did not extinguish PMC’s statutory rights against Sherwin-Williams, and let us consider now what they are. For PMC argues not that the contract requires Sherwin-Williams to indemnify PMC for any clean-up costs that.it is forced to incur, but only that the contract does not require PMC to indemnify Sherwin-Williams for clean-up costs or waive PMC’s statutory rights against Sherwin-Williams.
Althоugh both parties are, as we said, strictly liable for the costs of cleaning up the toxic wastes at the site, CERCLA permits one of the “responsible parties” (as liable parties are called under CERCLA) to sue the other (or others) for reimbursement of the costs of clean up that have been or will be borne by the plaintiff. 42 U.S.C. § 9607(a)(4)(B). In a suit of this sort between responsible parties, section 113(f)(1), 42 U.S.C. § 9613(f)(1), authorizes the district court to order “contribution” based on the balance .of the equities. So if in a case betwеen two responsible parties, party A had *616 incurred 50 percent of the clean-up costs but was adjudged by the district court only one-fourth as culpable as B (maybe because A had dumped only one-fourth as much toxic waste), B would be ordered to pay A 60 percent of A’s .costs. Sixty percent of A’s costs is 30 percent of the total costs. Adding that to the 50 percent of the total costs incurred by B yields 80 percent of the total costs — B’s adjudged share on the assumption that it is four times as culpаble as A, since 80 percent plus one-fourth of 80 percent (20 percent) equals 100 percent.
mi The district judge decided to make Sherwin-Williams not 80 or 90 or 95 but 100 pei'cent responsible for the costs of cleaning up the site. This would be an unexceptionable decision if all the pollution had occurred before PMC took over the property. But PMC concedes that between the purchase in 1985 and the bringing of this suit in 1993 it dumped toxic wastes at the site on a number of occasions. Sherwin-Williams argues that in light оf this concession, the district judge abused his equitable discretion
(AL Tech Specialty Steel Corp. v. Allegheny Int'l Credit Corp., supra,
There is an issue of prematurity concerning the allocation of the clean-up costs thаt PMC has not yet incurred.
United States v. Hardage,
There is another and more serious roadblock to the award of contribution to PMC under section 113(f)(1). The right created by that section does not arise automatically from a finding that a responsible party has paid more than its fair share of clean-up costs, as PMC was found to have done. The party must also show that it incurred these costs in compliance with the federal EPA’s “national contingency plan.” 42 U.S.C. § 9607(a)(4)(B);
Washington State Dept. of Transportation v. Washington Natural Gas Co.,
For completeness we should note that the district judge awarded site-assessment costs to PMC not only under section 113(f) but also under section 107(a), which authorizes suits for damages against owners of contaminated sites by persons who incur costs in cleaning up the sites. 42 U.S.C. § 9607(a)(4)(B). It is this provision, which creates strict liability, that imposed on PMC a legal duty to clean up the property that it had bought from Sherwin-Williams. In rеcognition that CERCLA liability is strict, Congress created an “innocent landowner” defense not here invoked, 42 U.S.C. §§ 9601(35), 9607(b)(3), plus the contribution provision of section 113(f). Two of our decisions hold that an innocent landowner can also sue under section 107(a).
Rumpke of Indiana, Inc. v. Cummins Engine Co.,
As far as the already incurred costs (other than the site-assessmеnt costs), which PMC can’t obtain contribution for under any provision of CERCLA, are concerned, PMC has another string to its bow — the Illinois Contribution Act. This is a general statute governing contribution among joint tortfeasors, not anything designed for environmental cases, and so naturally it contains no public-comment requirement. Since the dumping of toxic wastes — the tort — occurred in Illinois, we may assume as the parties do that the Act is applicable despite the choice of law provision in their contract, a рrovision presumably limited to contract disputes.
The district judge allowed PMC to obtain under the Illinois statute the contribution for past costs incurred that it also but unsuccessfully sought under CERCLA. Sherwin-Williams • argues that this award improperly circumvents CERCLA’s limitation on contribution. PMC replies by pointing to CERC-LA’s broad savings clause, which provides that nothing in CERCLA “shall affect or modify in any way the obligations or liabilities of any person under other Federal or State law, including common law, with respect to releases of hazardous substances оr other pollutants or contaminants.” 42 U.S.C. § 9652(d). Despite this clause, one court has held that section 113(f)(1) provides the exclusive means of obtaining contribution by one responsible party from another.
In re Reading Co., supra,
The purpose of CERCLA’s savings clause is to preserve to victims of-toxic wastes the other remedies they may have under federal or state law.
Beck v. Atlantic Richfield Co.,
Common law courts traditionally did not consider the claim of one joint tortfeasor for a sharing of the costs of liability by the other one worthy of
any
judicial time and attention, except in casеs in which the second tortfeasor had agreed (or was treated as having agreed) to indemnify the first.
Union Stock Yards Co. v. Chicago, Burlington & Quincy Ry.,
A savings clause is not intended to allow specific provisions of the statute that contains it to be nullified.
American Tel. & Tel. Co. v. Central Office Telephone, Inc.,
- U.S. -, -,
Let us turn to the RCRA injunction that PMC obtained. Sherwin-Williams argues that a RCRA tail should not be allowed to wag a CERCLA dog. Since, as we have pointed out, PMC is not a victim of pollution, it may indeed seem odd to allow it to obtain relief under a pollution-control statute. But no odder than allowing it to obtain relief-in the form of contribution under another pollution сontrol statute, namely CERCLA. In any event, we rejected this argument in
AM Int’l, Inc. v. Datacard Corp.,
We are mindful that a citizen’s (that is, that PMC’s) suit under RCRA is barred if the state at the time of suit “has commenced and is diligently prosecuting an action” in a federal or state court under the statute to clean up the site. 42 U.S.C. § 6972(b)(2)(C); see § 6972(a)(1)(B). When PMC sued, Illinois had already taken certain administrative actions to bring about PMC’s compliance with RCRA, but had not filed a lawsuit. Preliminary and informal in character, these were not “actions” in the legal sеnse in which the statute appears to be using the term, that is, formal proceedings whether in a court or before an agency. Writing a letter
*619
would hardly be described as “commencing”, or “prosecuting” an “action.” Although a broad reading of “actions” would be consistent with Congress’s evident desire that citizens’ suits supplement rather than displace state enforcement,
Givcdtney of Smithfield, Ltd. v. Chesapeake Bay Foundation, Inc.,
Sherwin-Williams argues in the аlternative that the district court should have abstained in favor of the state administrative proceeding,
Burford v. Sun Oil Co.,
Only two other issues need to be discussed. The first is the
form
of the RCRA injunction that the district court issued. It reads in its entirety as follows: “This Court therefore orders SherwinWilliams to take full responsibility for the future remediation of the PMC facility.” This form of words fails to comply with the requirements of Fed. R. Civ. P. 65 that an injunсtion be precise and self-contained, so that a person subject to it who reads it and nothing else has a sufficiently clear and exact knowledge of the duties it imposes on him that if he violates it he can be adjudged guilty of criminal contempt.
Schmidt v. Lessard,
Last, the explanation that the judge gave for exercising his discretion in favor of an award of attorney’s fees to PMC for obtaining the injunction was inadequate. He announced a conclusion, but gave no reasons for it, as we require.
AM Int’l, Inc. v. Datacard Corp.,
supra,
To summarize, the judgment of the district court is affirmed with three exceptions: the part of the judgment awarding contribution to PMC for costs already incurred by it in cleaning up the property is vacated with directions to dismiss this claim; the injunction is vacated and the case remanded for the entry of an injunction that will comply with Rule 65; and the award of attorney’s fees is vacated, to be recomputed on remand. There will be no award of costs in this court.
Affirmed in Part, Vacated in Part, and Remanded.
