53 F.4th 236
D.C. Cir.2022Background:
- NRC issued a 30-year materials license in 2007 for the American Centrifuge Plant (initially held by U.S. Enrichment Corp.) authorizing enrichment up to 10% U-235; the plant was never built and the license later transferred to American Centrifuge.
- In 2019 American Centrifuge contracted with DOE to demonstrate production of HALEU (up to 19.75% enrichment) and sought an NRC license amendment to authorize possession/production (requested possession up to 25% to account for variance).
- American Centrifuge submitted an environmental report; the NRC posted notice of the amendment request as required by regulation.
- Petitioners (Ohio Nuclear and Beyond Nuclear) emailed a letter to NRC staff urging preparation of an Environmental Impact Statement (EIS) and raising NEPA concerns but did not file a hearing request or seek to intervene under NRC procedures (10 C.F.R. § 2.309).
- NRC conducted an Environmental Assessment (EA), issued a Finding of No Significant Impact (FONSI), and granted the amended license; petitioners then filed a timely petition for review in this Court challenging the adequacy of NEPA review.
- The Court concluded petitioners were not parties to the NRC adjudication because they failed to use the prescribed intervention/hearing procedures and therefore dismissed the petition for lack of jurisdiction under the Hobbs Act.
Issues:
| Issue | Plaintiff's Argument | Defendant's Argument | Held |
|---|---|---|---|
| Whether this Court has jurisdiction under the Hobbs Act to review the NRC order | Petitioners claim NEPA violations and seek judicial review of the amended license | NRC argues Hobbs Act jurisdiction requires petitioners to have been parties in the NRC proceeding (party aggrieved) | Held: No jurisdiction — petitioners were not parties below, so cannot invoke Hobbs Act review |
| Whether the petitioners’ informal letter to NRC sufficed to make them parties/intervenors | Letter raised substantive NEPA objections and should suffice to preserve review | Informal submissions do not satisfy AEA/NRC rule requirement to request a hearing and plead admissible contentions | Held: Informal letter insufficient; must file a hearing request with contentions per 10 C.F.R. § 2.309 |
| Whether NEPA creates an independent right to judicial review that bypasses AEA/NRC intervention procedures | Petitioners argue NEPA violations justify direct judicial review | Government: NEPA does not alter NRC’s statutory/regulatory intervention requirements | Held: NEPA does not displace NRC hearing procedures; petitioners still had to intervene to seek review |
| Whether the NRC erred in relying on an EA rather than preparing an EIS (merits) | Petitioners contend EA was inadequate and EIS required | Respondents dispute jurisdiction and did not pursue merits before Court | Held: Court did not reach merits; dismissed for lack of jurisdiction |
Key Cases Cited
- Nuclear Info. & Res. Serv. v. NRC, 509 F.3d 562 (D.C. Cir. 2007) (describing NRC authority under the Atomic Energy Act)
- Nat. Res. Def. Council v. NRC, 823 F.3d 641 (D.C. Cir. 2016) (intervention required to challenge NRC license actions)
- Myersville Citizens for a Rural Cmty., Inc. v. FERC, 783 F.3d 1301 (D.C. Cir. 2015) (EA vs. EIS standards under NEPA)
- ACA Int’l v. FCC, 885 F.3d 687 (D.C. Cir. 2018) ("party aggrieved" requires participation in agency proceedings)
- Alaska v. FERC, 980 F.2d 761 (D.C. Cir. 1992) (party/intervenor requirement for review)
- Water Transp. Ass’n v. ICC, 819 F.2d 1189 (D.C. Cir. 1987) (intervention prerequisite to judicial review)
- Gage v. U.S. Atomic Energy Comm’n, 479 F.2d 1214 (D.C. Cir. 1973) (administrative procedure must be invoked before seeking court review)
- Theodore Roosevelt Conservation P’ship v. Salazar, 616 F.3d 497 (D.C. Cir. 2010) (NEPA does not create a free-standing cause of action to bypass administrative procedures)
- Beyond Nuclear v. NRC, 704 F.3d 12 (1st Cir. 2013) (NEPA does not alter NRC hearing procedures)
- Union of Concerned Scientists v. NRC, 920 F.2d 50 (D.C. Cir. 1990) (procedures for raising NEPA contentions in NRC hearings)
