Opinion for the court filed by Circuit Judge RANDOLPH.
The Trans Alaska Pipeline System stretches 800 miles across the Alaskan wilderness from the vast North Slope oil field to the all-weather port of Valdez on the southern coast of the State. Built by a consortium of oil companies and opened in 1977, the pipeline currently transports nearly two million barrels of oil per day.
We will assume familiarity with the pipeline’s extensive history recounted in the opinions cited in the margin.
1
Originally
*762
projected to cost one billion dollars, the pipeline wound up costing more than $9 billion. The Interstate Commerce Commission (replaced in late 1977 by the Federal Energy Regulatory Commission) instituted a massive initial rate-making investigation. The main participants were the oil companies who own and operate the pipeline and the State of Alaska, which is interested in maintaining low oil transportation rates because its substantial royalties and tax revenues from the pipeline are calculated on a “netback” basis. In 1985, facing the prospect of many years of additional litigation and a record already filling some 150,000 pages, Alaska and the pipeline owners reached a comprehensive private settlement. The centerpiece of the agreement consisted of the “TAPS Settlement Methodology,” a rate-setting mechanism designed to determine pipeline rates through the year 2011. The Commission, in a decision this court sustained, approved the settlement.
Arctic Slope Regional Corp. v. FERC,
The dispute before us today began in December 1989, when the pipeline owners filed their proposed 1990 tariffs. These rates were substantially higher than those sought for previous years, in part because they included $120 million in costs associated with the repair of corrosion damage to the pipeline. Alaska protested the inclusion of these costs, charging that they were incurred as the result of “imprudence” on the part of the pipeline owners. The Commission instituted a formal investigation and allowed Alaska to intervene pursuant to 18 C.F.R. § 385.214. Amerada Hess Pipeline Corp., 49 F.E.R.C. ¶ 62,320 (1989). Petro Star Inc., a pipeline shipper, also intervened in the rate challenge. 2
Several months later, the pipeline owners moved for “partial summary disposition” before the presiding Administrative Law Judge. See 18 C.F.R. § 385.217. The owners argued that the 1985 agreement, which by its terms settled “all outstanding issues of dispute” between the parties, Settlement Agreement § 1-1 (June 28, 1985), precluded the State from objecting to the owners’ including in their rates any costs stemming from imprudent actions taken before January 1, 1985, the effective date of the releases contained in the settlement. Alaska responded that the corrosion problems were not an issue of dispute in the original rate proceeding, and thus were not covered by the settlement. The Administrative Law Judge, finding the owners’ characterization of the agreement to be supported by undisputed material facts, granted their motion. Amerada Hess Pipeline Corp., 51 F.E.R.C. ¶ 63,004 (1990). The Commission affirmed, Amerada Hess Pipeline Corp., 53 F.E.R.C. ¶ 61,061 (1990), and Alaska sought immediate review in this court. 3 The pipeline owners intervened to defend the Commission’s ruling. 4
*763
We do not reach the merits. Under 28 U.S.C. § 2342(5), we would have jurisdiction only if the Commission’s decision constituted a “final order.”
Cf. American Train Dispatchers Ass’n v. ICC,
The rate-making is a proceeding between the Commission as regulator, see 42 U.S.C. §§ 7155, 7172(b), and the pipeline owners whose interstate rates are within the Commission’s regulatory authority. Alaska’s nominal status is as an intervenor “directly affected by the outcome of the proceeding.” 18 C.F.R. § 385.214(b)(2)(h),• see 49 F.E.R.C. at 63,465. The Commission’s ruling limits Alaska’s intervention to the portion of the rate challenge focusing on allegations of post-settlement imprudence.
In
Public Service Commission of New York v. Federal Power Commission,
Limitations on the scope of intervention are treated differently.
Stringfellow v. Concerned Neighbors in Action,
Here the Commission’s order does not preclude Alaska from bringing a petition for review to challenge any past or future Commission ruling after the Commission has reached a decision definitively imposing an obligation, denying a right, or fixing a legal relationship. Final Commission orders may be appealed by “[a]ny party aggrieved.” 28 U.S.C. § 2344. We have routinely interpreted this phrase to allow petitions by parties who were intervenors before the Commission and who would suffer injury-in-fact from its final disposition.
See, e.g., Maine Pub. Serv. Co. v. FERC,
What we have written thus far is sufficient to explain why the Commission’s decision placing limitations on the actions Alaska may take as an intervenor in the tariff proceeding is not an appealable final order. However, the parties have treated
*764
the Commission’s order as akin to a grant of partial summary judgment. Even if this description were accurate, it would not transform the Commission’s action into a final order. In the civil context, grants of partial summary judgment are generally considered interlocutory orders, not subject to immediate review.
See Liberty Mut. Ins. Co. v. Wetzel,
We can see no basis for an exception in this case.
6
None is created by statute. If anything, the Administrative Procedure Act is against Alaska’s position. The second sentence of section 10(c) states that “A preliminary, procedural, or intermediate agency action or ruling not directly reviewable is subject to review on the review of the final agency action.” 5 U.S.C. § 704. The provision was inserted in order to negate any inference that non-final orders would be immediately reviewable when later review is adequate and available.
See
Attorney General’s Manual on the Administrative Procedure Act 103 (1947). Moreover, as the Commission and pipeline owners observe, further proceedings before the agency may satisfy Alaska completely if it turns out that all of the challenged expenses resulted from post-settlement imprudence, such as failure properly to maintain the corrosion prevention system. All parties agree that such a ruling would preclude the owners from including the repair costs in their 1990-92 rates, and thus would have the practical effect of mooting this petition. Alaska’s counter-argument is that if it cannot bring its claim before the court at this time, it may never get a chance because the Commission could drop its investigation at some future date.
Cf. Papago Tribal Util. Auth.,
Citing
Abbott Laboratories v. Gardner,
Alaska’s remaining complaint is that the Commission only raised the finality issue in its brief, filed some 21 months after Alaska filed its petition for review, although our Local Rule 7(i) provides that all motions “which, if granted, would dispose of the appeal or petition for review in its entirety” must be filed within 45 days of the docketing of a case. See D.C.Cir.R. 7(i). Alaska does not explain how a local rule can preclude a party from raising a jurisdictional issue at any point during the proceeding. In any event, the rule deals with motions. It does not forbid parties from raising dis-positive arguments in their briefs even though those briefs typically will be filed outside the 45-day period.
We hold that we are without jurisdiction to consider Alaska’s petition for review, which is accordingly dismissed without prejudice to the rights of any party to raise the substantive issues presented upon petition from a final Commission order.
Notes
.
See Arctic Slope Regional Corp. v. FERC,
. The pipeline owners’ proposed 1991 and 1992 tariffs included another $297 million in corrosion repair costs. Alaska filed a timely protest to each rate proposal, and in each case the Commission instituted an investigation, consolidated it with its 1990 tariff investigation, and granted Alaska’s motion to intervene. See Amerada Hess Pipeline Corp., 57 F.E.R.C. ¶ 62,274 (1991); Amerada Hess Pipeline Corp., 53 F.E.R.C. ¶ 62,285 (1990).
. At the same time, the Commission held that Petro Star could challenge pre-settlement imprudence because it was not a party to the settlement. See 53 F.E.R.C. at 61,195-96. The pipeline owners filed a petition for review of this portion of the Commission order, Amerada Hess Pipeline Corp. v. FERC, No. 91-1086 (D.C.Cir.), which has been held in abeyance pending settlement negotiations between Petro Star and the owners. The Commission has approved a private settlement between those parties. See Amerada Hess Pipeline Corp., 58 F.E.R.C. ¶ 61,173 (1992).
.During the pendency of this petition for review, Alaska and the owners have pursued a private resolution of the corrosion costs issue through alternative dispute resolution. The ADR agreement allowed Alaska to pursue this petition, but this fact cannot, of course, affect our jurisdiction. See Amerada Hess Pipeline Corp., 53 F.E.R.C. ¶ 61,266 (1990). The Commission has suspended its investigation into the 1990-92 tariffs through February 1993, while the ADR proceeds. Amerada Hess Pipeline Corp., 58 F.E.R.C. ¶ 61,175 (1992).
. The Commission analogizes its procedure for summary disposition to Rule 56 summary judgment practice in the federal district courts.
See, e.g., Tennessee Gas Pipeline Co.,
41 F.E.R.C. ¶ 63,006, at 65,008 (1987);
Coastal States Marketing, Inc. v. Texas-New Mexico Pipeline Co.,
25 F.E.R.C. ¶ 61,164, at 61,452 (1983).
See also Citizens for Allegan County, Inc. v. Federal Power Comm’n,
. This court’s discussion of an analogous issue in
InverWorld, Ltd. v. Commissioner of Internal Revenue,
