History
  • No items yet
midpage
Murray Energy Corp. v. Federal Energy Regulatory Commission
629 F.3d 231
D.C. Cir.
2011
Read the full case

Background

  • FERC issued a section 7 certificate for the REX-East pipeline with Condition 147 requiring collaboration with Murray to develop a plan to maintain pipeline integrity without impeding mining, or alternate routing if collaboration failed.
  • Murray Energy owns the Century Mine and fears subsidence from mining could stress the pipeline crossing the mining reserves.
  • REX and Murray exchanged extensive communications, submitted a construction and operations plan (Dec. 23, 2008), and proposed mitigation measures for subsidence.
  • FERC authorized construction on March 19, 2009, stating approval was in accordance with the Certificate Order and Condition 147.
  • Murray sought rehearing (July 15, 2009) arguing lack of proper collaboration and plan deficiencies; FERC granted rehearing in part and found REX satisfied collaboration.
  • REX began construction in May 2009, completed by August 2009, and gas flowed in November 2009; Murray petitioned for judicial review under 15 U.S.C. § 717r(b).

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Whether the Chief of Gas Branch 2 lacked authority to issue the Construction Order. Murray argues improper delegation under 18 C.F.R. § 375.308; designee not comparable to deputy/ division head. FERC ratified delegation by adopting the Director's action through his designee. Authority properly ratified by FERC via the Rehearing Order.
Whether Condition 147's collaboration requirement was met by REX. Murray contends REX did not truly collaborate and should have filed an alternate route. REX engaged in extensive discussions and the record supports collaboration. FERC reasonably concluded collaboration satisfied Condition 147.
Whether FERC's construction plan adequately protects pipeline safety. Experts show potential safety concerns and plan lacks binding protective measures. FERC credited credible experts and found measures adequate; explained safety rationale. FERC's safety determinations supported by substantial evidence.
Whether FERC properly addressed PHMSA's project-specific mitigation expectations. PHMSA guidelines should mandatorily bind REX to mitigation requirements. PHMSA guidelines were non-mandatory; FERC required compliance with PHMSA as actually necessary. FERC did not act arbitrarily in balancing PHMSA views; not required to adopt non-mandatory guidelines.

Key Cases Cited

  • Sacramento Mun. Utils. Dist. v. FERC, 616 F.3d 520 (D.C. Cir. 2010) (arbitrary and capricious review; substantial evidence standard)
  • Am. Gas Ass'n v. FERC, 593 F.3d 14 (D.C. Cir. 2010) (substantial evidence and rational connection principles)
  • Dana Corp. v. ICC, 703 F.2d 1297 (D.C. Cir. 1983) (agency ratification of authority problems reinforces action)
  • Elec. Consumers Res. Council v. FERC, 407 F.3d 1232 (D.C. Cir. 2005) (deference to agency’s factual determinations in disputes between experts)
  • City of Pittsburgh v. Fed. Power Comm'n, 237 F.2d 741 (D.C. Cir. 1956) (respect for other agencies' views on specialized matters)
  • Colo. Interstate Gas v. FERC, 599 F.3d 698 (D.C. Cir. 2010) (substantial evidence standard applied to agency findings)
Read the full case

Case Details

Case Name: Murray Energy Corp. v. Federal Energy Regulatory Commission
Court Name: Court of Appeals for the D.C. Circuit
Date Published: Jan 7, 2011
Citation: 629 F.3d 231
Docket Number: 09-1207
Court Abbreviation: D.C. Cir.